Archives: September 2019

Fourth District Affirms California Coastal Commission’s Authority to Impose Conditions on Coastal Development Permits Under Local Coastal Programs

In Lindstrom v. California Coastal Commission (2019) 40 Cal.App.5th 73, the Fourth District Court of Appeal partially reversed the trial court, finding the California Coastal Commission did not abuse its discretion when it imposed special conditions on a coastal development permit for a residential project proposed on a vacant lot in the City of Encinitas. The court found three of four conditions were consistent with the City’s local coastal program and within the Commission’s authority. The court rejected one condition because it was overbroad, unreasonable, and did not achieve the Commission’s purpose.

Background

In 2012, the Lindstroms applied for a coastal development permit with the City of Encinitas (City) to build a home atop a 70-foot high ocean-side bluff. To comply with the City’s Local Coastal Program (LCP), the permit application included a geotechnical report prepared by Geotechnical Exploration Inc. (GEI), an engineering firm hired by the Lindstroms. The LCP required the report to, among other things: (i) certify that the development would not endanger the bluff or require future bluff stabilization devices (i.e. coastal armoring or seawalls) based on a 1.5 safety factor over a 75-year time period, and (ii) calculate the minimum setback required for the development – a figure that could not be less than 40 feet. The GEI report concluded the proposed project could be built with a 40-foot setback without requiring bluff stabilizing measures in 75 years.

On May 2, 2013, the City’s planning commission approved the development permit with a condition requiring the Lindstroms to provide a letter stating the building could be removed in the event of endangerment. On May 28, 2013, GEI submitted a revised technical analysis which concluded the earlier report erred in calculating the development’s feasible setback. The new report stated the project would require a 72.25-foot setback, and proposed an alternate analysis based on the “natural angle of repose,” which would yield a 39.7-foot setback.

In June 2013, two Coastal Commission Commissioners appealed the City’s approval of the permit on grounds that it was inconsistent with the LCP. During the appeal process, the Lindstroms hired a second engineering firm, TerraCosta Consulting Group (TCG) and requested the Commission delay its decision. In October 2015, TCG prepared a new geotechnical report which concluded the slope would be safe with a 40-foot setback at a 1.29 safety level – a figure lower than the LCP-mandated 1.5 safety level.

The Coastal Commission heard the appeal in July 2016. As part of the appeal, a staff geologist concluded the proper setback should be 60 to 62 feet. The Commission agreed with the staff geologist, and approved the permit with four conditions. The first condition (“Condition 1.a”) required construction to adhere to a 60- to 62-foot setback. The second condition (“Condition 3.a”) prohibited all use of coastal armoring devices. The third condition (“Condition 3.b”) required removal of the home in the event a government agency deemed occupancy unsafe due to natural hazards. The fourth condition (“Condition 3.c”) imposed mandatory remediation measures that the landowners would be required to take in the event hazardous bluff conditions threatened the structure.

In August 2016, the Lindstroms filed a petition for writ of mandate challenging the Commission’s conditions of approval. The trial court partially granted the petition and found in favor of the Lindstroms as to the first and second conditions (Conditions 1.a and 3.a) but found the Commission did not abuse its discretion in imposing the third and fourth conditions (Conditions 3.b and 3.c). The Commission and the Lindstroms appealed.

The Fourth District’s Decision

The Court of Appeal for the Fourth District partially reversed the trial court’s holding. Relying on the plain language in the City’s LCP and the Coastal Commission’s authority to impose reasonable conditions so long as they are consistent with the Coastal Act and the LCP, the court found the Commission did not abuse its discretion when it imposed Conditions 1.a, 3.a, and 3.c.  The court held the Condition 3.b, however, was improperly broad and not reasonably related to achieving the LCP’s purpose. That condition required that the Lindstroms remove their home in the event a government agency deemed it a natural hazard. That condition, the court said, was poorly drafted and could have been read to require the Lindstroms to remove their home under unreasonable circumstances. The court therefore issued a writ of mandate requiring the Coastal Commission to either delete or revise and clarify the condition.

 

Bridget McDonald

Klamath River Renewal Project

Klamath River Renewal Project

The Klamath River Renewal Corporation (KRRC) proposes to take ownership of four PacifiCorp dams on the Klamath River—JC Boyle, Copco, No. 1 & 2, and Iron Gate—and then remove these dams, restore formerly inundated lands, and implement required mitigation measures in compliance with applicable federal, state, and local regulations. Removal of the four hydroelectric dams is the first crucial step to restore the health of the Klamath River and the communities that depend upon it. In order to accomplish these objectives, KRRC must first obtain approval from the Federal Energy Regulatory Commission (FERC). For the three dams within California (the JC Boyle Dam is in Oregon), KRRC must also obtain the approval of the State Water Resources Control Board. RMM attorney Jim Moose is part of the team of attorneys assisting KRRC with the acquisition of the approvals needed for removal of the three facilities within California.

California Vegetation Treatment Program

California Vegetation Treatment Program

The proposed CalVTP directs implementation of vegetation treatments on public and private land across the state as one component of the state’s efforts to reduce the risk of loss of lives and property, reduce fire suppression costs, and protect natural resources from wildfire. The California Board of Forestry and Fire Protection began analyzing the proposed program in early 2019 to consider and disclose the environmental effects of expanding CalFire’s vegetation treatment activities to cover a total of 250,000 acres per year (up from 33,000 acres per year on average in previous years) to help achieve the Governor’s goal of 500,000 annual acres of treatment on non-federal lands (Executive Order B-52-18). Vegetation treatments include wildland-urban interface fuel reduction, fuel breaks, and ecological restoration, through activities such as prescribed burning, mechanical and manual vegetation removal, prescribed grazing, and herbicides. RMM attorneys Jim Moose and Sabrina Teller advise the Board of Forestry regarding the preparation and certification of a Program EIR for the project.

Second District Invalidates EIR’s Project Description For Failing to Provide Sufficient Detail and Certainty.

In Stopthemillenniumhollywood.com et al. v. City of Los Angeles et al. (2019) 39 Cal.App.5th 1, the Second District Court of Appeal affirmed the trial court’s conclusion that an EIR for a mixed-use development project proposed by Millennium Hollywood, LLC (Millennium) in the City of Los Angeles (City) violated CEQA as a matter of law, because it failed to provide an accurate, stable, and finite project description.

In 2008, Millennium filed an application—which the Court of Appeal described as detailed—with the City proposing a mixed-use development project (2008 Proposal) on 4.47 acres in multiple parcels straddling two sides of Vine Street, between Yucca Street and Hollywood Boulevard, in the Hollywood Community Plan area of the City. The 2008 Proposal described a mixed-use development with 492 residential units, a 200-unit hotel, 100,000 square feet of office space, a 35,000-square-foot sports club and spa, 11,000 square feet of commercial uses, and 34,000 square feet of food and beverage uses. In total, proposed square footage was 1,163,079. Two historic buildings on site, the Capital Records Tower and Gogerty Building, would be preserved. The development would consist of two low-rise buildings, one on each side of Vine Street, with three towers intended to “frame” the Capital Records Tower. The 2008 Proposal would have required a zone change to allow the sports club, as well as a variance to allow the proposed density. After the City informed Millennium that a variance from the General Plan Floor Area Ratio (FAR) requirement would also be necessary, the project was put on hold.

In 2011, Millennium filed a new application with a new project description for the same site (2011 Project). Millennium still proposed a mixed-use development with residential, hotel, and retail uses totaling 1,166,970 square feet and a FAR of 6:1. Though the same mix of uses were proposed, the 2011 Project was “designed to create an impact ‘envelope’ within which a range of development scenarios can occur.” Thus, the specific shape, size, location, use, and number of buildings to be constructed on the site were not described, other than that the existing historic buildings would be preserved. Instead, Millennium sought to enter into a development agreement with the City that would establish the permitted developable floor area, land uses, design guidelines, and development standards for the site. Additionally, the 2011 Project included a land use equivalency program (LUEP) allowing the transfer of floor area between parcels on the site. The EIR analyzed the maximum level of impacts that could occur under the development agreement, regardless of which of the several development scenarios was actually constructed in the future.

Commenters on the Draft EIR complained that the imprecise project description hindered meaningful public participation. Nevertheless, the City approved the development agreement, certified the EIR, adopted mitigation for the analyzed maximum level of impacts and adopted a statement of overriding considerations. Petitioners, Stopthemillenniumhollywood.com, Communities United for Reasonable Development, and George Abrahams (collectively, Petitioners) petitioned the Los Angeles Superior Court for a writ of mandate setting aside project approval and certification of the EIR. Petitioners alleged three causes of action relating to violations of CEQA. First, they alleged that the EIR failed to include an accurate, stable, and finite project description. The second cause of action asserted that the City abused its discretion by failing to study traffic impacts to the 101 freeway despite Caltran’s direction that the City do so. The third cause of action alleged that the City failed to consult with the California Geological Survey regarding potential seismic hazards on the site. The trial court granted the petition as to the first and second causes of action, but not the third.

On the first cause of action, the trial court found that the project description was not stable or finite, and that the use of the word “or” in a condition of approval allowed Millennium, or future developers, to choose any permitted use listed for the C2 zone in the LAMC for future development, not just the list of proposed uses in the development agreement. The trial court reasoned that, though there may be circumstances where a project description may disclose only the physical parameters and maximum potential environmental impacts, no such circumstances were present here. The trial court distinguished Citizens for a Sustainable Treasure Island v. City and County of San Francisco (2014) 227 Cal.App.4th 1036 (Treasure Island), on the grounds that that case dealt with a site contaminated by hazardous materials, and it was unknown when cleanup of the site would be completed. The trial court noted that the development in Treasure Island included both fixed elements (including the street grid) and conceptual elements that would “likely” be subject to supplemental CEQA review. The trial court concluded that neither element was present here.

The trial court also found that, by including an ambiguous project description, the EIR impermissibly deferred part of the analysis of environmental impacts. Specifically, the trial court found that, because no specific “concept” was analyzed, the EIR did not explain how exceedance of the maximum impacts would be avoided when the project was actually designed and built; nor was additional CEQA review contemplated by either the EIR or the development agreement. The trial court determined that, without knowing the “bona fide subject” of the EIR, it would be impossible for the public and decisionmakers to accurately weigh the “environmental price tag” of the proposal and decide if the benefits outweigh that price.

The City and Millennium appealed the trial court’s decision as to the first and second cause of action, while Petitioners appealed the decision on the third cause of action. The Court of appeal, after ruling on the first cause of action, determined that it need not reach the other issues raised by the parties.

In affirming the trial court, the Court of Appeal looked to County of Inyo v. City of Los Angeles (1977) 71 Cal.App.3d 185 (County of Inyo), and Washoe Meadows Community v. Department of Parks and Recreation (2017) 17 Cal.App.5th 277 (Washoe Meadows). The Court cited County of Inyo for the proposition that, even where an inaccurate project description does not render invalid the analysis of environmental effects, it may nevertheless violate CEQA by interfering with “intelligent public participation.” The Court found further support for this position in Washoe Meadows, where the First District held that a failure to select or identify a specific project in the Draft EIR interfered with the public’s right to participate in CEQA review.

In the case before it, the Court found that the project description “fail[ed] to describe the siting, size, mass, or appearance of any building proposed to be built at the project site” and that the proposed development regulations imposed only vague and ambiguous limits on future construction choices. The Court held that, even if the analysis of maximum impacts were adequate—despite the project description, “CEQA’s purposes go beyond an evaluation of theoretical environmental impacts.” The Court determined that the project description violated CEQA as a matter of law.

In reaching its decision, the Court distinguished South of Market Community Action Network v. City and County of San Francisco (2019) 33 Cal.App.5th 321 (South of Market), on two grounds. First, the Court found that the only “uncertainty” at issue in South of Market was that the project description presented a choice of either a predominately office use or a predominately residential use, but the EIR did not select one or the other. Second, the Court found that the EIR in South of Market “included ‘site plans, illustrative massing, building elevations, cross-sections and representative floor plans for both options.”’ Because the EIR before it did not include these “technical characteristics” of the project, the Court concluded that it failed to comply with CEQA’s mandates. The Court also largely agreed with basis for the trial court’s distinguishing of Treasure Island, supra, 227 Cal.App.4th 1036, finding that no unusual circumstances were present in this case, and that future planning and development of the project would not be subject to additional environmental review. Lastly, the Court found the violation to be prejudicial because it interfered with public participation.

As stated above, the Court determined that it need not address the other issues raised by the parties. The Court dismissed an argument that Public Resources Code section 21168.9 required them to rule on each issue raised in a CEQA appeal. The Court found that section applied only to the trial court’s order on remand, which is to address only those mandates from the Court of Appeal that are necessary to comply with CEQA. The Court found that the trial court’s judgment was correct on at least one ground, so it was affirmed.

Nathan George

California Supreme Court Holds Adoption of Zoning Ordinance for Medical Marijuana Dispensaries is a “Project” Subject to CEQA

On August 19, 2019, the California Supreme Court issued its decision in Union of Medical Marijuana Patients, Inc. v. City of San Diego (2019) 7 Cal.5th 1171, in which the Court unanimously held that the City of San Diego’s adoption of a zoning ordinance for medical marijuana dispensaries is a “project” subject to CEQA. Although the Court agreed with the Fourth District Court of Appeal and the city in rejecting the petitioner’s argument that the adoption of a zoning ordinance is always a project, as a matter of law, under Public Resources Code section 21080, the Court reasoned that the adoption of the ordinance at issue was nonetheless the type of activity which, by its general nature, “is capable of causing a direct or reasonably foreseeable indirect physical change in the environment.” As such, the Court held, it is a “project” subject to CEQA.

Background

In 2014, the city adopted a zoning ordinance authorizing the establishment of medical marijuana dispensaries in the city and imposing various restrictions on their location and operation. The ordinance specified zones where dispensaries are permitted, included a cap on the number of dispensaries in any one district, restricted their proximity to sensitive uses, and imposed basic conditions on lighting, security, and hours of operation. At the time the ordinance was proposed, the city determined that the adoption of the ordinance did not constitute a “project” for purposes of CEQA. The city, therefore, did not conduct any environmental review prior to adopting the ordinance.

Following the city’s adoption of the ordinance, petitioner filed a petition for writ of mandate challenging the city’s decision not to conduct CEQA review. In the trial court, petitioner argued that the adoption of the ordinance should have been found to be a project under Public Resources Code section 21065, which defines a “project” as any activity undertaken or funded by, or requiring the approval of, a public agency that “may cause either a direct physical change in the environment, or a reasonably foreseeable indirect physical change in the environment.” According to the petitioner, the ordinance had the potential, among other effects, to cause increased vehicle traffic across the city, increase user cultivation, and concentrate dispensary development-related impacts in certain areas. The trial court rejected petitioner’s arguments and upheld the city’s decision, finding the petitioner’s claims were unsupported by evidence in the record.

On appeal, petitioner reiterated its argument regarding the potential to cause physical changes in the environment, and further argued that the adoption of the zoning ordinance was a project as a matter of law under Public Resources Code section 21080. Section 21080 states that CEQA “shall apply to discretionary projects proposed to be carried out or approved by public agencies, including, but not limited to, the enactment and amendment of zoning ordinances …” Pointing to this language, petitioner argued that the enactment of a zoning ordinance is automatically a project under CEQA, regardless of the potential for environmental change. Petitioner’s argument was based in part on the Third District’s decision in Rominger v. County of Colusa (2014) 229 Cal.App.4th 690, where the court held that the county’s approval of a tentative map—another activity expressly listed in section 21080—was a project as a matter of law.

Notwithstanding Rominger, the Fourth District Court of Appeal rejected both of petitioner’s arguments, holding that the enactment of a zoning ordinance is subject to the same “project” test as any other activity under Public Resources Code section 21065. Further, the court found no error in the city’s conclusion that the zoning ordinance was not a project because it lacked the potential to cause a physical change in the environment. According to the Fourth District, the potential environmental effects raised by the petitioner were unsupported by the record and too speculative to establish a potential to physically change the environment.

The Supreme Court’s Review

Seeking to resolve the split between the Fourth District’s decision and Rominger, the Supreme Court granted review to address two issues: (1) whether, under Public Resources Code section 21080, a public agency’s enactment of a zoning ordinance is always project under CEQA, as a matter of law; and (2) whether the enactment of the city’s zoning ordinance was a “project” under section 21065.

The Court began its analysis by placing the dispute into context. As the Court explained, CEQA proceeds by way of a three-step process or “decision tree.” First, the lead agency must determine whether the proposed activity is a “project” subject to CEQA at all. Second, assuming CEQA applies, the agency must determine whether the project qualifies for one or more of the many CEQA exemptions. Third, assuming no exemptions apply, the agency must undertake environmental review, namely, preparation of an initial study and a negative declaration, mitigated negative declaration, or an environmental impact report. At issue here was the very first step of the process—the city’s determination that the adoption of the zoning ordinance was not a “project” subject to CEQA at all.

Turning to the first issue, the Court agreed with the Fourth District that Public Resources Code section 21080 does not dictate the result as a matter of law. Engaging in a statutory interpretation analysis, the Court reasoned that while section 21080 is ambiguous when read in isolation, the Legislature’s use of the statutorily defined term “project” in that section must be read to incorporate the definition of “project” in section 21065. Accordingly, the language in PRC section 21080 that CEQA “shall apply to discretionary projects” must be read to provide that CEQA applies to activities that are both (1) discretionary; and (2) meet the definition of a “project” in section 20165. According to the Court, the specific activities listed in section 21080 are merely generic examples of the type of activities approved or carried out by public agencies to which CEQA could apply, however, the mere listing of an activity in that section does not supplant the potential “physical change” analysis required under section 21065.

The Court found further support for its reading of section 21080 in the definition of the term “project” in CEQA Guidelines section 15378, which makes clear the enactment of a zoning ordinance is merely an example of an activity undertaken by public agencies; policy considerations against subjecting activities to CEQA where there is no potential to effect the environment; and the legislative history of section 21065 revealing the Legislature’s intent to narrow CEQA’s application to activities posing a possibility of an environmental effect.

The Court also refuted the notion that its reading of the statute renders section 21080 mere surplusage, noting that the significance of section 21080 is that it states, in the affirmative, the additional requirement that projects must be “discretionary” for CEQA to apply.

After concluding that the adoption of a zoning ordinance is not a project as a matter of law, the Court turned to whether the adoption of the dispensary ordinance in this case was nonetheless a project subject to CEQA under Public Resources Code section 21065. The Court disagreed with the appellate court and answered the question in the affirmative.

As the Court explained, the governing decision for the “project” inquiry is Muzzy Ranch Co. v. Solano County Airport Land Use Commission (2007) 41 Cal.4th 372. In that case, the Court observed, “Whether an activity constitutes a project subject to CEQA is a categorical question respecting whether the activity is of a general kind with which CEQA is concerned, without regard to whether the activity will actually have environmental impact.” In other words, an agency’s task in determining whether a proposed activity is a project is to determine if, by its general nature, the activity is capable of a causing physical change in the environment, without regard to whether actual effects will occur under the circumstances.

Applying Muzzy Ranch, the Court held that the city erred in determining that the adoption of the zoning ordinance was not a project subject to CEQA. The Court noted that the ordinance would permit the establishment of a sizable number of new businesses, which could foreseeably result in new construction. Furthermore, the ordinance could cause changes in vehicle traffic patterns as a result of customers, employees, and suppliers. Finally, the Court explained, the necessary casual connection between the ordinance and these effects was satisfied because the adoption of the ordinance was “an essential step culminating in action . . . which may affect the environment.” For these reasons, the Court held, the adoption of the zoning ordinance was a “project” subject to CEQA.

Collin McCarthy