Blog

First District Court of Appeal Upholds EIR for San Francisco’s Treasure Island Redevelopment Project

The Court of Appeal rejected petitioner’s argument that the city was required to prepare a program-level EIR rather than project-level EIR for a long-term development plan in the San Francisco Bay.  In Citizens for a Sustainable Treasure Island v. City and County of San Francisco (July 7, 2014, Case No. A137828), the court held that the EIR provided sufficient project-level information and properly relied on regulatory standards and guidelines. The court also upheld the EIR’s project description, analyses of hazardous substances and historic resources, and its discussion regarding conformity with the Tidelands Trust. In addition, the court held that the draft EIR did not need to be recirculated.

Background

The Treasure Island/Yerba Buena Island Project is a comprehensive plan to redevelop the former naval station located on Treasure Island and Yerba Buena Island in San Francisco into a mixed-use community. Among other amenities, the project will include up to 8,000 residential units, up to 140,000 square feet of commercial and retail space; up to 100,000 square feet of office space; 300 acres of parks, playgrounds, and open public space; restoration and reuse of historic buildings; bike and transit facilities; and a new ferry terminal and intermodal transit hub. Build-out of the project is planned to occur in phases over a 15- to 20-year period.

The City and County of San Francisco, along with the Treasure Island Development Authority, approved the project in June 2011. A group called Citizens for a Sustainable Treasure Island (CSTI) filed a petition for writ of mandate challenging the EIR for the project on various grounds. The trial court denied the petition in its entirety and CSTI appealed.

The Appellate Court’s Opinion

Before reaching the merits of CSTI’s arguments, the court clarified the applicable standard of review. Despite CSTI’s efforts to frame the issues to allege procedural violations under CEQA, the court determined that most of the issues raised on appeal were properly reviewed under the substantial evidence standard because they involved the sufficiency of the information provided to the public and to the decision makers. The court clarified that because CEQA requires an EIR to reflect a good faith effort at full disclosure, rather than perfect or exhaustive analysis, the absence of information in an EIR will normally rise to a failure to proceed in the manner required by law only if the analysis in the EIR is clearly inadequate or unsupported.

Project-Level v. Program-Level Analysis

CSTI’s primary argument on appeal was that the city was required to prepare a program EIR rather than a project EIR. It claimed that the project was only developed at a conceptual level by design, and therefore, the city was required to prepare a program EIR and analyze the project using “tiered” environmental review. The court rejected the argument, pointing out that CSTI failed to cite any authority suggesting that the city was required to prepare any particular type of EIR. The court emphasized that the label assigned to an EIR is less important than the EIR’s sufficiency as an informative document. Instead of focusing on labels when reviewing EIRs for legal adequacy, courts focus on whether EIRs provides decision makers and the public with sufficient analysis to intelligently consider the environmental consequences of a project. 

Adequacy of Project Description

The court next addressed CSTI’s argument that the project description was inadequate. Similar to its previous argument, CSTI claimed that the EIR analyzed only an “abstract and indeterminate ‘conceptual’ development scenario” lacking necessary project-level detail. It complained, for example, that the specific configuration and design for particular buildings is left for future review and the street layout is only conceptual, with the final layout also subject to future review by responsible agencies.

The court rejected these criticisms. While the EIR did not include the exact, final plans for each building or street, it identified numerous design standards “governing virtually every aspect of project development.” The court determined these design standards provided stable information regarding final building details, including heights, mass, bulk, and other design specifications, while still allowing flexibility at the early stage in the planning process to allow future revisions. The court also noted that future revisions would likely be the subject of further supplemental environmental review. Accordingly, the court determined the EIR’s project description was adequate.

Presence and Remediation of Hazardous Substances

The court next rejected CSTI’s argument that the EIR did not include enough detail about the hazardous materials on the project site and how the city might remediate them. It explained that the EIR included extensive information on the presence of toxic or hazardous substance in the project area. It also noted that the Navy assumed primary responsibility for the remediation of each parcel of land before transferring it to the City. Further, in the event the city or developer assumed responsibility for any cleanup efforts in the future, they would be subject to the same environmental regulations and regulatory oversight as the Navy, and these numerous regulatory requirements were described in a mitigation measure adopted with the EIR.

CSTI also argued the mitigation measure was improperly deferred because a remediation plan would not be developed until a future time. The court found this argument unconvincing. The EIR relied on the existing regulatory scheme and performance standards to ensure any potential future remediation would occur without generating significant environmental impacts.

Recirculation

CSTI also argued that the City was required to recirculate the draft EIR in light of “significant new information.” During the comment period, the Coast Guard submitted a comment suggesting the project could interfere with vessel safety and homeland security on San Francisco Bay by interfering with the Coast Guard’s Vessel Traffic Service (VTS).

In response to the comment, the City met with the Coast Guard and conducted additional technical studies to determine potential impacts of buildings on VTS equipment operations. The final EIR amended design standards for the project to require consultation with the Coast Guard if future proposals included buildings tall enough to interfere with VTS equipment. The design standards also require any building developer to work with the Coast Guard to make space for additional equipment, or reach a similar solution, to preserve the effectiveness of the VTS. The Coast Guard submitted an additional comment letter, indicating the consultation process addressed the agency’s prior concerns. When approving the project, the city explicitly found that this binding consultation process would eliminate any impacts to vessel safety on San Francisco Bay.

Finding that the Coast Guard’s letter did not raise significant new information within the meaning of CEQA, the court explained that the record contained substantial evidence indicating the continued effectiveness of the VTS system would be ensured, despite urban development on Treasure Island and the refinements made to the EIR to satisfy the Coast Guard’s concerns did not constitute the type of significant new information requiring recirculation of an EIR.

Historic Resources

CTSI also argued the EIR did not adequately disclose or mitigate potential impacts to two historic buildings in the project area because the EIR did not identify the precise and final disposition of those buildings. But again, the EIR identified binding design standards which would apply to any final architectural design proposals. The design standards require that rehabilitation of the historic buildings be conducted in accordance with the Secretary of the Interior’s Standards for the Rehabilitation and Guidelines for Rehabilitating Historic Buildings. The court noted that these standards serve as an explicit benchmark to establish whether a project will have a significant adverse impact to historic buildings. The court also noted that if a non-conforming use of the historic buildings was proposed in the future, the use would not be covered in the EIR and would therefore require supplemental environmental review. But the city was not required to study a hypothetical future change to the project in the current EIR.

Consistency with the Tidelands Trust

Finally, CSTI argued the EIR did not adequately discuss and analyze the potential impacts of the project on land subject to the Tidelands Trust. CSTI’s argument again centered on that fact that not all proposed uses within the Project area are known at this time. But the court rejected CSTI’s insinuations that non-trust uses would be permitted on lands subject to the trust. The EIR explained that the project must conform to the legal requirements of the Trust. The EIR also acknowledged the use restrictions the trust would impose on tidelands. And any proposed use is subject to the Tidelands Trust overlay zone and final approval and review by the Treasure Island Development Authority.

RMM Partners Whit Manley and Chip Wilkins, along with associates Jennifer Holman and Jeannie Lee, represented Real Party in Interest and Cross-Appellant Treasure Island Community Development, LLC.

Court of Appeal Upholds San Jose’s Eighth Addendum to Airport Master Plan EIR

The First District Court of Appeal held that changes to the City of San Jose’s Airport Master Plan did not constitute a new project as a matter of law and did not require supplemental review under Public Resources Code section 21166. The court ordered publication of the opinion – Citizens Against Airport Pollution v. City of San Jose (June 6, 2014, Case No. H038781) – on July 2, 2014.

The center of the dispute was an addendum to the City of San Jose’s 1997 EIR prepared for its International Airport Master Plan. The city had also prepared a Supplemental EIR for the plan in 2003. The addendum, which was the city’s eighth addendum to the 1997 EIR, assessed the impacts of proposed amendments to the Airport Master Plan, including changes to the size and location of future air cargo facilities, the replacement of air cargo facilities with 44 acres of general aviation facilities, and the modification of two taxiways to provide better access for corporate jets.

Petitioner Citizens Against Airport Pollution’s (CAAP) primary argument was that the amendments to the Airport Master Plan addressed in the eighth addendum constituted a new project as a matter of law, and therefore, an EIR addendum was barred under CEQA. Alternatively, CAAP argued that an EIR addendum could not be used to analyze the environmental impacts of the plan changes, since those changes were substantial and required major revisions to the EIR with respect to noise, greenhouse gas emissions, toxic air contaminants, and biological resources.

The Court of Appeal was not persuaded by CAAP’s argument that the changes to the Airport Master Plan constituted a new project as a matter of law, and that the city was therefore required to prepare a new EIR. The court confirmed that the an agency’s determination on whether supplemental environmental review is required is review under the substantial evidence test, distinguishing previous cases that applied the “fair argument” standard to the question of whether a subsequent approval was “within the scope” of a previous approval.

The court next turned to CAAP’s alternative argument that the city was required to prepare a supplemental EIR for the plan amendments because they were “substantial changes” requiring “major revisions” in the EIR. CAAP claimed that there would be new or more severe impacts in several areas including noise, greenhouse gas emissions, air quality, and biological resources.

Notably, the court rejected CAAP’s argument that the city was required to analyze Greenhouse Gas Emissions for the project since CEQA Guidelines section 15064.5, which requires analysis of GHG impacts in EIRs, was added to the Guidelines after the 1997 and 2003 EIRs were prepared. Relying on CREED v. City of San Diego (2011) 196 Cal.App.4th 515, the court held that the potential for GHG impacts was not substantial new information triggering the need for a supplemental EIR. Rather, the potential for GHG impacts have been known since well before the first EIR for the Master Plan was adopted.

The court also held that there was substantial evidence demonstrating that there would be no new or more severe impacts to biological resources. The addendum acknowledged that the project changes would result in the loss of four acres of burrowing owl habitat and included mitigation measures to mitigate the impact. The court explained that mitigation measures can be modified in an addendum if there is a legitimate reason and the changes are supported by substantial evidence. The mitigation measures in the addendum met that standard because they completely offset the loss of the four acres by establishing new permanent habitat. Moreover, the mitigation measure was only a change in the location of habitual preserved under a burrowing owl mitigation plan that as established for the 1997 EIR and it would be managed within the parameters of the established plan.

The court also upheld the city’s determination that potential changes in noise and air quality impacts did not trigger a supplemental environmental review because jet engines of today and the future are quieter and cleaner than the engines of 1997.

Sacramento Kings Request CEQA Petitioners Post $100 Million Bond to Cover Potential Lost Revenue

This week, Sacramento Kings CFO John Reinhart stated in court papers filed by the Kings and the city that even a short delay in the arena construction could result in huge losses for the team. Both parties urged the Sacramento Superior Court to require petitioners who oppose the project to post a hefty bond covering the potential losses.

If the arena does not open by 2017, the NBA has a right to buy back the team and move them out of town—a transfer the team avoided last year when it was purchased by Vivek Ranadive after the league vetoed another group’s attempt to move the Kings to Seattle. The team has already spent $60 million purchasing the Downtown Plaza and paying architect fees.

The NBA’s 2017 buy-back deadline is not the only source of potential loss, however. A delay could push completion of excavation activities into the winter rainy season, which would cause serious problems for the construction timeline. With arena construction delayed, the team would also face increased financing costs, potential NBA penalties, and substantial revenue losses.

The bond request comes after a group of petitioners filed a CEQA lawsuit seeking to enjoin the $477 million project.  In total, two groups have filed CEQA lawsuits against the city. The hearing on the injunction request is set for July 25. The Kings request that the petitioners post a $100 million bond, and the city requests an additional $5.7 million bond to cover its own investments.

The bond request was reported by the Sacramento Bee. Click here for the full article.

Fifth District Holds Interim Renewal Contracts for Central Valley Project Water are Exempt from CEQA

Even though the renewal contracts have expired, and thus the case was moot, the Court of Appeal nevertheless resolved the case, finding the renewal contracts both statutorily and categorically exempt from CEQA. In North Coast Rivers Alliance v. Westlands Water District, Case No. F067383 (July 3, 2014), the Fifth District Court of Appeal upheld the Westlands Water District’s interim renewal contracts with the United States Bureau of Reclamation, which continued the existing terms for water delivery from the Central Valley Project (CVP.) The court upheld the District’s findings that the interim contracts fell under the statutory exemption for ongoing pre-CEQA projects as well as the categorical exemption for the continued operation of existing facilities.

Westlands Water District and its related distribution districts serve more than 600,000 acres of farmland in San Joaquin Valley, and have a right to receive over one million acre-feet of water per year from the CVP, due to water service contracts that have been in place with the Bureau of Reclamation since the 1960s. In 2012, the Bureau and the water districts entered into two-year contracts to renew the districts’ contractual rights to receive CVP water, during which time the Bureau was set to complete the environmental review required for 25-year renewal contracts.

The water districts found that the renewals were statutorily and categorically exempt from CEQA because they involved ongoing receipt and delivery of water on identical terms as the prior water service contracts, with no expansion of service and no new facilities, and any changes related solely to minor administrative matters.

The court first rejected the water districts’ assertion that the renewal contracts were statutorily exempt under the statutory exemption for rate-setting activities under Public Resources Code section 21080, subdivision (b)(8). The court found no evidence that the renewal contracts involved any rate-setting activity.

But the court did uphold the water districts’ conclusion that the renewal contracts were statutorily exempt as ongoing projects approved before CEQA was enacted. (See CEQA Guidelines, § 15261 subd. (a).) The court found that the original contracts and construction of facilities predated CEQA’s enactment in November of 1970. Any assignment agreements and renewals entered into after CEQA’s enactment, the court found, did not result in an expansion or material modification of the underlying activity that was initially approved; rather, the agreements merely facilitated the districts’ ability to receive a stable and adequate water supply within the scope of the original project.

The court found that the renewal projects also came within the categorical exemption for operation of existing facilities. (CEQA Guidelines, § 15301.) Categorical exemptions, unlike statutory exemptions, are subject to exceptions. While the courts of appeal disagree on whether a fair argument standard or substantial evidence standard applies to exceptions, the court here found the disagreement irrelevant because it would reach the same conclusion under either standard.

Petitioners first argued that “unusual circumstances” exception applied. The court, however, agreed with the water districts that the project did not involve unusual circumstances because it was not uncommon for utility-type public agencies to have large-scale facilities operating at a large volume and to impact the environment to some extent simply by existing and functioning as utilities. The court noted that even if the large scale of the water diversion at issue constituted unusual circumstances, as petitioners argued, petitioners would still have to establish that there was a reasonable possibility the activity will have a significant effect on the environment due to such circumstances. Using the established levels of operations as the baseline, the court concluded there was insufficient evidence that there would be a substantial adverse change from the environmental baseline, and thus the exception did not apply. The court also rejected petitioners claim that the renewal contracts fell within cumulative impacts exception to the exemption. The court stated that the present litigation was not the proper time for petitioners to raise the cumulative-impact claim because the short-term interim renewal contracts did not constitute “successive projects of the same type” and therefore did not fit within the definition of the exception.

First District Upholds EIR for Project to Redevelop Former Naval Station on Treasure and Yerba Buena Islands

In a decision published July 7, 2014, the First District Court of Appeal upheld the EIR for a project designed to transform a former naval station on San Francisco’s Treasure Island into a vibrant mixed-use community. The project is a comprehensive plan to redevelop Naval Station Treasure Island, which ceased operations in 1997.  The project will be constructed over 15 to 20 years. It includes up to 8,000 new homes (with at least 25 percent designated as affordable units available at below-market prices); 500 hotel rooms; commercial, retail, and office space; and 300 acres of parks, playgrounds, and open space. The project also includes restoration and re-use of historic buildings, public utilities, bike and transit facilities, updated infrastructure, and a new Ferry Terminal and intermodal Transit Hub. Because the project will be built over time, with changing market conditions, it includes flexible parameters for certain project elements. All told, the project is expected to cost around $1.5 billion.

The City and County of San Francisco, along with the Treasure Island Development Authority, certified the EIR for the Treasure Island / Yerba Buena Island Project in June 2011. A group called Citizens for a Sustainable Treasure Island challenged the decision, claiming the environmental documents violated CEQA on several grounds. The trial court denied the petition in its entirety. On appeal, the First District Court of Appeal affirmed the trial court’s judgment.

The petitioner’s main argument on appeal was that the lead agencies abused their discretion by preparing a “project” EIR instead of a “program” EIR. Essentially, the petitioner argued that the project was too “flexible” and uncertain to support project-level review.  The court disagreed, noting that the question under CEQA case law is not whether a particular type of EIR is prepared, but rather whether the EIR meets CEQA’s mandate to adequately identify and address the environmental impacts of a project.

The court also upheld the EIR’s project description, analyses of hazardous substances and historic resources, and its discussion regarding conformity with the “Tidelands Trust.” In addition, the court held that the draft EIR did not need to be recirculated.

RMM partners Whit Manley and Chip Wilkins, along with associates Jennifer Holman and Jeannie Lee, represented Real Party in Interest Treasure Island Community Development, LLC, in the case. (Citizens for a Sustainable Treasure Island v. City and County of San Francisco, Case No. A137828, can be read here.)

U.S. Supreme Court Does Not Take Up Constitutionality of California’s Low Carbon Fuel Standard

The Supreme Court denied a petition for review in Rocky Mountain Farmers Union v. Corey, letting stand the Ninth Circuit’s holding that the state’s low carbon fuel standard (LCFS) is constitutional on its face. RMM previously wrote about the Ninth Circuit decision here. The issue before the court was whether the LCFS discriminates against out-of-state businesses, thereby violating the dormant commerce clause. The court held that the LCFS is neither facially discriminatory nor discriminatory in purpose or effect with respect to the regulation’s crude oil provisions.

On remand, the district court will be tasked with determining whether the regulation’s ethanol provisions place burdens on interstate commerce that outweigh the benefits, rendering the LCFS invalid, and also whether the Clean Air Act preempts the LCFS program.

Court of Appeal Upholds State Water Board’s Broad Authority to Prohibit Unreasonable Use of Water

The court held that the State Water Resources Control Board has broad regulatory authority to prevent the unreasonable use of water, upholding a Board regulation that prohibits certain diversions by grape growers in the Russian River watershed. The First District Court of Appeal issued a partially published opinion in Light v. State Water Resources Control Board (2014) __Cal.App.4th __ (Case No. A138440) on June 16, 2014.

In April 2008, young salmon were found to have been fatally stranded along the banks of the Russian River stream system. Scientists from the National Marine Fisheries Service concluded the deaths were caused by abrupt declines in water level that occurred when water was drained from the streams and sprayed on vineyards and orchards to prevent frost damage, a common practice in the watershed.

Following a series of hearings and the preparation of an EIR, the Board adopted Regulation 862 in September 2011. Regulation 862 is likely to require a reduction in diversion of water from the stream system for frost protection, at least under certain circumstances. It applies to “any diversion of water from the Russian River stream system … for purposes of frost protection from March 15 through May 15.” The regulation itself contains no substantive regulation of water use, instead delegating the task of formulating regulatory programs to “water demand management programs” (WDMPs), which will be created by self-organized groups of agricultural diverters who will act as the “governing bodies.” Each WDMP must be submitted annually to the Board for approval. The regulation declares that any water use inconsistent with the programs, once they have been formulated and approved by the Board, is unreasonable, and therefore prohibited.

Regulation 862 was challenged in two petitions for writ of mandate. The petitions alleged that the Board lacked regulatory authority to adopt the regulation and that the regulation would unlawfully interfere with plaintiffs’ use of water drawn from the Russian River stream system. The trial court granted a writ invalidating the regulation on several grounds. The Board appealed. The Court of Appeal reversed.

The Court of Appeal first addressed plaintiffs’ argument that Regulation 862 was invalid because the Board lacked sufficient regulatory authority to adopt the regulation. Plaintiffs argued that the Board lacked authority to adopt the regulation because, according to them, the Boards’ authority to regulate the unreasonable use of water was limited to enforcement actions. The Court of Appeal disagreed, finding that the Board may exercise its regulatory powers through the enactment of regulations, as well as through the pursuit of judicial and quasi-judicial proceedings. The court noted that the Board is charged with acting to prevent unreasonable and wasteful uses of water, regardless of the claim of right under which the water is diverted, and that the Board’s authority to enact regulations in furtherance of this purpose was addressed and upheld nearly 40 years ago in People ex rel. State Water Resources Control Bd. v. Forni (1976) 54 Cal.App.3d 743. The court concluded that, given the Board’s statutory charge to “prevent waste, unreasonable use, unreasonable method of use, or unreasonable method of diversion of water in this state” and the recognized power of the Legislature to pass legislation regulating reasonable uses of water, the Board’s grant of authority to “exercise the … regulatory functions of the state” necessarily includes the power to enact regulations governing the reasonable use of water.

The Court of Appeal next addressed Plaintiffs’ contention that the Board lacks regulatory authority to limit water use by riparian users and early (pre-1914) appropriators, whose diversion is beyond the permitting authority of the Board. Rejecting this argument, the court explained that, although the Board has no authority to require such users to obtain a permit to divert, that does not mean their use of California’s water is free from Board regulation. Preventing these users from the unreasonable use of water necessarily requires the imposition of limits on that use by the Board. The Court explained that there is “no question” the Board has the power to prevent riparian users and early appropriators from using water in an unreasonable manner.

The court also determined that the regulation did not violate the rule of priority. When the supply of water is insufficient to satisfy all persons and entities holding water rights, it is ordinarily the function of the rule of priority to determine the degree to which any particular use must be curtailed. Yet, as the court explained, even in these circumstances, the Board has the ultimate authority to allocate water in a manner inconsistent with the rule of priority, when doing so is necessary to prevent the unreasonable use of water. Because no one can have a protectable interest in the unreasonable use of water, when the rule of priority clashes with the rule against unreasonable use of water, the latter must prevail. The court was careful to point out that since this was a facial challenge, its holding extended only to whether the regulation was valid on its face. It explained that the regulation does not declare any specific diversion of water for frost protection unreasonable, much less all such use. Rather, frost protection diversion is unreasonable only when it occurs in violation of the WDMP. As among individual water rights holders, the regulation requires the WDMP’s to respect the rule of priority in assigning corrective actions. Thus, a determination of whether specific regulatory measures adopted by the WDMP’s violate the rule of priority, must await implementation of the regulation.

The court also concluded that the Board properly found the regulation to be necessary to enforce water use statutes and did not unlawfully delegate its authority by requiring local governing bodies to formulate the substantive regulations.

Lastly, in an unpublished portion of the opinion, the court upheld the Board’s certification of the EIR for the regulation.

 

 

Court Holds Petition Over Tree Removal in Community College Expansion Project Came Too Late

A published opinion by the First District Court of Appeal emphasizes the importance of filing timely CEQA lawsuits. In Citizens for a Green San Mateo v. San Mateo Community College District, the court determined that, even under the most generous interpretation of CEQA’s statute of limitations, a petitioner’s lawsuit was time-barred under Public Resources Code section 21167.

The controversy arose when the San Mateo Community College District removed and pruned over 200 invasive eucalyptus trees on the northern edge of the community college campus. The district began removing trees on December 28, 2010. On January 5, 2011, a member of Citizens for a Green San Mateo contacted the district expressing concern over the tree removal and pruning. Citizens for a Green San Mateo filed a petition for writ of mandate on July 1, 2011, alleging that the district violated CEQA and was required to prepare an EIR to study the tree removal. The trial court determined the challenge was timely and granted the petition, finding the district had violated CEQA. The district appealed.

The Appellate Court’s Decision

On appeal, the district argued the 30-day statute of limitations period established by Public Resources Code section 21167, subdivisions (b) or (e) applied to bar the CEQA lawsuit because the district filed a Notice of Determination. The NOD described the mitigated negative declaration prepared by the district when it approved the Facility Improvements at College of San Mateo project, or the “CSM Project,” in 2007.

The CSM Project included renovation, demolition, replacement, or new construction of about 25 buildings, numerous pedestrian and automobile circulation enhancements, and other improvements to modernize the campus. The negative declaration also determined that the proposed project would result in the removal and pruning of an unknown number of trees, but tree plantings proposed as part of the project would mitigate any unavoidable tree removal, resulting in a less than significant impact. At the hearing, a district trustee expressed concern regarding campus-wide tree removal proposed as part of the CSM Project, but noted that, due to the mitigation required by the negative declaration, “the number of newly planted trees will be greater than that of removed trees.” No public comments were offered at the hearing.

The appellate court rejected the petitioner’s claim that the tree removal was “materially different” from the activities discussed in the mitigated negative declaration and subsequent NOD that the community college district filed for the CSM Project. The court emphasized that the term “project,” for the purposes of CEQA, does not mean each separate governmental approval that may ultimately be required to complete the proposed action. The court concluded that the record demonstrated the tree removal was a subsequent activity encompassed within the scope of the CSM Project. Since the district filed an NOD recording its approval of the CSM Project, and the public was on notice that trees could be removed anywhere on campus as a result of the CSM Project, the 30-day statute of limitations established by section 21167, subdivisions (b) and (e) applied to bar the lawsuit.

Even if the 180-day limitations period, which applies when no NOD is filed, applied to this case, the appellate court determined the lawsuit was still time-barred. Assuming, for the purposes of analysis, that the district failed to adequately notify the public of the tree removal, any challenge would need to be filed within 180 days from the date of the district’s decision to carry out or approve the project, according to section 21167, subdivision (a). Here, the district committed to the tree removal at the public trustee meeting on November 17, 2010. The appellate court emphasized that section 21167, subdivision (a), does not require any special notice requirement to start the 180-day clock; all that is required is a formal decision by a public agency to carry out or approve the project. Therefore, the petition was time-barred, even assuming the tree removal was not described in the mitigated negative declaration certified for the CSM Project.

Finally, the appellate court was not persuaded by the efforts of Citizens for a Green San Mateo to avoid the result of filing its complaint outside CEQA’s statute of limitations. Citizens asserted it had no notice of the potential for tree removal activities until a neighbor/member observed the trees being cut down on January 5, 2011. To support this argument, the citizens cited the California Supreme Court’s opinion in Concerned Citizens of Costa Mesa, Inc. v. 32nd District Agricultural Association (1986) 42 Cal.3d 929. But the appellate court noted that the citizens interpreted the test established in that case incorrectly. In Concerned Citizens, the agency approved a fairground on six acres that would have seated 5,000. As constructed, the theater actually seated 7,000 across 10 acres, so the project constructed was materially different than the project the agency initially approved. Further, the agency never alerted the public to these changes. Therefore, the Supreme Court determined the 180-day statute of limitations ran from when the public reasonably should have known the project being constructed was different than the project approved. In contrast, the mitigated negative declaration prepared by the community college district notified the public that the district intended extensive landscaping improvements across campus that could require the removal of mature trees. Further, the tree removal activities conducted were not materially different from those approved by the district at an open hearing in November 2010. So even under the most generous interpretation of section 21167 and the case law established by the Supreme Court, Citizens for a Green San Mateo’s petition was time-barred.

RMM partners James Moose and Sabrina Teller represented the San Mateo Community College District.

President Obama Signs the Water Resources Reform and Development Act

On June 11, 2014, President Obama signed the Water Resources Reform and Development Act (WRRDA). Historically, water resources legislation has been enacted every two years to provide policy direction to the Army Corps of Engineers (Corps) and the Administration. The WRRDA is the first water resources bill that has been signed since 2007, however.

The WRRDA authorizes 34 federal, state, and local projects aimed at maintaining the nation’s ports, levees, dams, and harbors. For example, the WRRDA authorizes projects to deepen the Boston Harbor and the Port of Savannah, to restore the Everglades, and to strengthen levees in the Sacramento region. The Congressional Budget Office estimates the total cost to implement these projects will be $12.3 billion between 2014 and 2025. This cost will be offset by $18 billion in project deauthorizations contained in the WRRDA.

Some key components of the WRRDA:

  • Authorizes approximately $45 million for flood risk management measures for the Orestimba Creek in the San Joaquin River Basin to protect the City of Newman.
  • Authorizes approximately $689 million for flood risk management measures in the Sutter River Basin.
  • Allows local communities, which may have state or local funding sources, to carry out work in advance of the Corps and receive a credit for this work.
  • Requires the Corps to set firm deadlines for preparing its studies.
  • Expedites project permitting and approvals by reducing the number of studies to be performed by the Corps.
  • Requires the Corps to allow for regional variances regarding vegetation patterns and characteristics on levees, among other variances, with feedback from state, regional, and local entities.
  • Authorizes financial assistance through the Water Infrastructure Finance and Innovation Act of 2014 to carry out pilot projects by public or private entities for flood damage reduction, hurricane and storm damage reduction, environmental restoration, coastal or inland harbor navigation improvement, or inland and intracoastal waterways navigation improvement.
  • Deauthorizes $12 billion for old, inactive port projects.
  • Reforms and preserves the Inland Waterways Trust Fund, which is used to fund the construction and rehabilitation of the nation’s inland waterways system.

In addition to the aforementioned projects, the WRRDA authorizes construction activities to strengthen 24 miles of levees protecting over 100,000 residents and $7 billion in property in the Natomas area, north of downtown Sacramento. Federal maps show that a levee breach could put homes and businesses in the area under 20 feet of water. In 2012, the Sacramento Area Flood Control Agency finished upgrading 18 miles of Natomas levees. The WRRDA authorizes the Corps to complete upgrades to the remaining 24 miles of levees, which had been stalled because of the lack of federal authorization.

Read the full text of the WRRDA here.