In a Case of First Impression, First District Court of Appeal Holds That Presentation of Five Alternatives in EIR, Without Designation of One as the ‘Project,’ Does Not Satisfy CEQA’s Requirement for a Stable Project Description

In Washoe Meadows Community v. Department of Parks and Recreation (2017) 17 Cal.App.5th 277, the First District Court of Appeal upheld the trial court’s decision directing the Department of Parks and Recreation and the State Park and Recreation Commission to set aside project approvals where the draft EIR analyzed five alternative projects in detail, but did not identify one preferred alternative.

In 1984, the Department of Parks and Recreation acquired 777 acres of land in the Lake Tahoe Basin—608 acres of the property were designated as Washoe Meadows State Park and the remainder contained an existing golf course. Studies conducted in the early 2000s indicated that the layout of the golf course was contributing to sediment running into Lake Tahoe, which contributed to deterioration of habitat and water quality in the lake.

In 2010, the Department circulated a draft EIR to address the concerns about the golf course. The draft EIR analyzed five alternatives in equal detail, with the stated purpose of “improv[ing] geomorphic processes, ecological functions, and habitat values of the Upper Truckee River within the study area, helping to reduce the river’s discharge of nutrients and sediment that diminish Lake Tahoe’s clarity while providing access to public recreation opportunities ….” The draft EIR did not identify one preferred alternative. In the final EIR, the Department identified the preferred alternative as a refined version of the original alternative 2, which provided for river restoration and reconfiguration of the golf course. In 2012, the Department certified the EIR and approved the preferred alternative.

Framing the issue as a question of law, the court found that the draft EIR did not “provide the public with an accurate, stable and finite description of the project,” because it did not identify a preferred alternative. The court found that by describing a range of possible projects, the Department had presented the public with “a moving target,” which required the public to comment on all of the alternatives rather than just one project. The court determined that this presented an undue burden on the public.

The court compared the draft EIR to County of Inyo v. City of Los Angeles (1977) 71 Cal.App.3d 185, where the court found an EIR insufficient because the project description described a much smaller project than was analyzed in other sections of the EIR. The court in Washoe Meadows found that rather than providing inconsistent descriptions like in County of Inyo, the draft EIR had not described a project at all. Thus, the court directed the Department to set aside the project approvals.