Second District Holds County Violated CEQA by Increasing Project Building Height without Issuing a Supplemental EIR

The Second District Court of Appeal held the County of Ventura violated CEQA when it increased the height of a proposed building by 15 feet without filing a supplemental EIR. The county had filed an addendum considering the impact of the building’s change in location, but the addendum neglected to mention a change in building height from 75 feet to 90 feet. The court considered this a substantial change in the project requiring major revisions to the EIR. Ventura Foothill Neighbors v. County of Ventura, Case No. B254120 (Dec. 15, 2014).

In 1993, the County Board of Supervisors decided to construct a five-story ambulatory care clinic on the county’s Medical Center campus. The 1993 EIR stated that the building would be up to 75 feet tall. The county delayed construction until 2005, when the board decided the clinic should be relocated a few hundred feet northwest of the original location to reduce environmental impacts and to utilize a more parking-centric location. The county prepared an addendum for the relocation and filed a notice of determination (NOD). Neither the addendum nor the NOD stated that the clinic would exceed 75 feet. In 2008, a nearby resident inquired about the presence of a rig on the site, and learned that the relocated clinic was to be 90 feet tall. The height difference, petitioners claimed, would “significantly diminish the superior ocean view setting” of the Foothill residences. The trial court held in favor of the residents, and the court of appeal affirmed.

The court of appeal denied the county’s argument that the Ventura Foothill Neighbors were time-barred from challenging the decision to proceed with an addendum because the challenge fell outside CEQA’s 30-day statute of limitations. The court distinguished the California Supreme Court decision in Committee For Green Foothills v. Santa Clara County Bd. of Supervisors (2010) 48 Cal.4th 32, in which the Court held that filing of a valid NOD triggers a 30-day statute of limitations. Since the neither the addendum or the NOD made any mention of the increase in the building’s height, the timeline ran from the time of the neighbor’s inquiry.