Author Archives: Chris Stiles

FIFTH DISTRICT HOLDS AIR RESOURCES BOARD COMPLIED WITH CEQA IN ADOPTING ADVANCED CLEAN TRUCKS REGULATION

In California Natural Gas Vehicle Coalition v. State Air Resources Board (2024)___Cal.App.5th___, the Fifth District Court of Appeal upheld the State Air Resources Board’s (CARB) decision to not implement a low-Nitrous Oxide (low-NOx) vehicle credit within its Advanced Clean Trucks Regulation. The court affirmed the trial court’s ruling that CARB did not violate CEQA or the Administrative Procedure Act (APA) in rejecting this proposed alternative.

Background

In 2018, CARB issued a notice of preparation regarding the Advanced Clean Trucks Regulation, which aimed to transition the class of medium- and heavy-duty trucks in California to zero-emission capable technology over time. Despite input urging for the inclusion of a low-NOx vehicle credit throughout multiple rounds of public comment, the suggested alternative was not considered and ultimately rejected in the Regulation’s Final EIR. CARB reasoned that this alternative ran counter to the goals of the Regulation, as promoting the sale of low-emitting vehicles would not advance the transition of the vehicle market to electric, zero-emission vehicles.

The California Natural Gas Vehicle Coalition, an association of companies and other interested parties that utilize natural gas (low-NOx fuel) technologies, filed a petition for writ of mandate alleging that CARB violated CEQA and the APA. Regarding CEQA, the Coalition alleged that the low-NOx vehicle credit was not sufficiently considered as an alternative or mitigation measure. It also argued that the EIR failed to consider a reasonable range of alternatives and did not adequately respond to public comments. The Coalition’s APA claim also revolved around the failure to consider a low-NOx vehicle credit alternative; however, it also contended that CARB’s economic impact analysis failed to consider the Regulation’s impact on those that invested in low-NOx technologies. The trial court denied the petition. The Coalition appealed.

The Court of Appeal’s Decision

CEQA

The Court of Appeal concluded that CARB’s decision not to discuss the low-NOx vehicle credit option as an alternative or mitigation measure was supported by substantial evidence.

CARB argued that a low-NOx alternative was not feasible as it undercut the regulation’s objective—encouraging the sale of lower-emitting vehicles subverted its goal of enhancing zero-emission vehicle sales. The Coalition, in contrast, asserted that the alternative was at least “potentially feasible,” and that CARB could not reject a project alternative merely because it did not meet one or several of the project’s goals. Rejecting the Coalition’s argument, the court found the alternative did not just fail to meet a single project goal; it ran counter to the Regulation’s underlying objective. As the court explained, CEQA allows agencies to reject alternatives that are infeasible or cannot achieve a project’s fundamental purpose. Here, as the goals of the Project and the low-NOx vehicle credit were contradictory, the alternative could be deemed “infeasible,” and thus, CARB was justified in rejecting it.

The Coalition also argued that the low-NOx option should have been considered as a mitigation measure because the Regulation would cause an increase in the use of electric vehicles—leading to short-term air quality impacts from increased manufacturing of these vehicles and the construction of new charging stations. The court ruled, however, that CARB was not required to look to mitigation measures that hampered its Regulation’s objectives. Because the vehicle credits were properly deemed infeasible as an alternative, CARB properly rejected them as a mitigation measure as well.

Finally, the Coalition alleged that CARB failed to respond to comments regarding the implementation of a low-NOx vehicle credit in the Final EIR. The court found, however, that CARB implemented the public’s suggestions into its analysis when it rejected the low-NOx vehicle credit option as an alternative. The court found that this was sufficient to “put the public on notice” that the comments were considered, and thus, the failure to directly respond was not prejudicial to public participation.

APA

The court also rejected the Coalition’s argument that CARB violated the APA. The Coalition first argued that CARB failed to consider the economic impact of the Regulation on businesses and individuals that have already adopted or invested in low-NOx emitting technologies. Under the APA, the economic impact assessment of a regulation must sufficiently cover all known cost impacts that California’s businesses and private individuals could incur by complying with the regulation. The Coalition argued that CARB’s analysis was too limited because those who invested heavily in low-NOx technologies would suffer from a regulation that encouraged the use of zero-emission vehicle technology but were not assessed as a group. The court disagreed, finding that this “group” was not impacted by the Regulation because they were not mandated by the Regulation to adopt and purchase zero-emission technologies, and therefore, did not need to be considered in the analysis. The court sided with CARB again regarding its rejection of the low-NOx vehicle credit as an alternative under the APA using similar reasoning to its CEQA analysis. The low-NOx vehicle credit alternative undercut the objectives of the Regulation and was therefore ineffective in implementing a zero-emission sales requirement.

– Adam Nir

SECOND DISTRICT REJECTS CEQA CHALLENGE TO ACTIONS IMPLEMENTING THE CITY OF LOS ANGELES’ WESTSIDE MOBILITY PLAN

In Westside Los Angeles Neighbors Network v. City of Los Angeles (2024) ___ Cal.App.5th ___, the Second District Court of Appeal affirmed the trial court’s decision upholding an EIR and CEQA exemptions for several actions implementing the City of Los Angeles’ Westside Mobility Plan.

Background

The Westside Mobility Plan is a comprehensive study that was undertaken by the City of Los Angeles to develop potential short-term solutions and long-term plans addressing congestion and mobility challenges within that part of the city. In 2018, the city’s planning commission took actions to implement three of the six components of the Mobility Plan. These actions included (1) amendments to transportation impact assessment fee programs for two existing specific plans (Fee Program Updates); and (2) adoption of a Streetscape Plan setting guidelines and standards for streetscape elements such as street trees and landscaping, sidewalk paving, street lighting, and pedestrian crossings for the Mobility Plan area. While the Fee Program Updates and Streetscape Plan are largely separate, implementation of the Streetscape Plan could be funded through the transportation impact fees included in the Fee Program Updates.

The city prepared an EIR for the Fee Program Updates, which noted that the Mobility Plan’s other components, including the Streetscape Plan, were exempt from CEQA. The planning commission subsequently certified the EIR and also determined that the Fee Program Updates were statutorily and categorically exempt from CEQA.

The petitioner filed a petition for writ of mandate challenging the planning commission’s authority to certify the EIR, the adequacy of the EIR, and the use of CEQA exemptions.  The trial court denied the petition. The petitioner appealed.

The Court of Appeal’s Decision

The Court of Appeal first considered whether the planning commission had authority to certify the EIR.  The petitioner argued that for a multi-component project like this, only the entity authorized to implement the component constituting the “primary source” of the project’s environmental impacts has the authority to certify the EIR, and that here, the primary source of the project’s impacts was the Fee Program Updates, which could only be approved by the City Council.  The court disagreed.

The court explained that under CEQA and the CEQA Gudelines, a non-elected decision-making body within a local agency (like the planning commission here) may certify an EIR. The court further found that, taken together, the applicable Guidelines establish that a “decision-making body” is any person or group of people within a public agency permitted by law to commit an agency to a definite course of action for a project. Accordingly, rather than asking whether the entity can implement the portion of the project constituting “the primary source” of the project’s environmental effects, as suggested by the petition, the relevant question is whether the entity at issue can make a decision that commits the agency to a definite course of action with respect to the whole project, even if the project is subject to multiple discretionary approvals.  Here, given the overlap between the Fee Program Updates and the Streetscape Plan, the court concluded that, by virtue of its power to adopt the Streetscape Plan, the planning commission could make a decision committing the City to a definite course of action in regard to the project (both the Fee Program Updates and the Streetscape Plan), even though further discretionary action by the City Council (i.e., adoption of the Fee Program Updates) was required to implement it.

The court next turned to the question of whether the Streetscape Plan falls within the scope of the Class 1 categorical exemption for minor alterations of existing facilities with negligible or no expansion of use. Answering in the affirmative, the court found that the Streetscape Plan, which includes standards for various streetscape elements, would result in only minor alterations to existing rights-of way that would improve aesthetics, functionality, and safety rather than expand their use.

The court rejected the petitioner’s contention that the Streetscape Plan did not meet the requirements of the Class 1 categorical exemption because the EIR and Statement of Overriding Considerations identified significant and unavoidable impacts related to the Fee Program Updates due to air quality, noise and vibration and transportation. The court explained that neither the EIR nor the city’s Statement of Overriding Considerations related to the improvements to be implemented as part of the Streetscape Plan, or more importantly, addressed whether the Streetscape Plan involved an expansion of use of an existing facility.

In relation to the EIR, the court observed that the petitioner appeared to be arguing that the EIR’s growth-inducing impact analysis was deficient because it failed to address concerns that the project would spur economic and population growth or directly or indirectly result in the construction of new housing raised in two comments received on the draft EIR. Despite the lack of clarity, the court nevertheless rejected the petitioner’s assertion. The court noted that the city addressed these concerns in the final EIR, concluding in responses to comments that the Fee Program Update would not induce growth. The court further noted that the petitioner had not raised any issues with the final EIR’s responses to the comments.

Finally, the petitioner argued that the EIR was insufficient because it failed to ensure how a neighborhood protection program, required as mitigation for the Fee Program Updates, would be funded. The court disagreed. The EIR specified that the program would be funded through fees obtained from the Fee Program Updates and the mitigation measure included specific thresholds that would trigger implementation of the program.

– Adam Nir

FOURTH DISTRICT UPHOLDS MITIGATED NEGATIVE DECLARATION FOR WAREHOUSE PROJECT

In Upland Community First v. City of Upland (2024) __Cal.App.5th__, the Fourth District Court of Appeal reversed a trial court order setting aside an MND for a warehouse project.  The Court of Appeal rejected the petitioner’s claims that impacts related to GHG emissions and traffic triggered the need for an EIR.

Background

The project, as initially proposed, included three warehouse buildings totaling 977,246 square feet located on a 50-acre parcel used for a rock and gravel crushing operation. In response to concerns that the project was too large, the applicant reduced the size to a single, one-level warehouse of 201,096 square feet.

The city prepared an MND for the project. The MND concluded that the project’s GHG emissions would be less than significant based on the South Coast Air Quality Management District’s 10,000 MTCO2e/yr threshold for “heavy industrial stationary projects,” as well as a qualitative evaluation of the project’s consistency with the city’s general plan and climate action plan. In response to comments urging the city to use SCAQMD’s 3,000 MTCO2e/yr threshold for mixed-use commercial/non-industrial projects, the project was revised to include sustainability features that reduced GHG emissions to below the 3,000 MTCO2e/yr threshold. In connection with the project revisions, a supplemental GHG analysis was prepared using revised (increased) baseline emissions, which included the existing rock and gravel crushing activity on the project site. The revised GHG analysis concluded that the project would generate less than 3,000 MTCO2e/yr.

The petitioner filed a petition for writ of mandate alleging that an EIR was required because a fair argument could be made that the project would have significant impacts on traffic, transportation, air quality, and GHG emissions. The trial court granted the petition on the sole ground that substantial evidence failed to support the use of the 10,000 MTCO2e/yr threshold. Additionally, the trial court found that even if the 3,000 MTCO2e/yr had been applied, there was no explanation for the revised baseline used in the supplemental analysis.

The developer and the petitioner both appealed.

Court of Appeal’s Decision

Reversing the trial court, the Court of Appeal held that substantial evidence supported the city’s determination that the 3,000 MTCO2e/yr was an appropriate numerical threshold for measuring the project’s GHG emissions. The court found that expert evidence explaining why the 10,000 MTCO2e/yr threshold was inappropriate and urging the city to use instead the more stringent standard demonstrated a scientific and factual basis for use of the 3,000 MTCO2e/yr threshold.

The court further held that the 3,000 MTCO2e/yr threshold was an appropriate threshold for cumulative impacts resulting from a project’s GHG emissions. The court reasoned that in developing the 3,000 MTCO2e/yr, SCAQMD relied on data collected by the Governor’s Office of Planning and Research, which shows that the 90 percent capture rate for commercial/mixed use commercial projects ranged from 1,390 to 1,481 MTCO2e/yr.

As applied to this project, the court observed that the use of the 3,000 MTCO2e/yr was conservative since the project is mixed-use commercial/industrial which would generally have higher GHG emissions compared to a mixed-use commercial/residential project.

Regarding the increase in baseline emissions used in the supplemental GHG analysis, the court agreed with the petitioner that the MND did not explain the reason for the increase in baseline emissions. The court nevertheless found that circumstantial evidence in the record showed that the increase was attributable to 78 truck trips used in the existing rock and gravel crushing operation that had not been included in the initial GHG analysis. The court therefore upheld the baseline emissions used in the supplemental GHG analysis.

Regarding the project’s traffic impacts, the petitioner argued that the MND’s analysis was inadequate because it underestimated the project’s daily passenger car equivalent (PCE) trips by using the incorrect trip generation rate classification. The court determined, however, that evidence in the record showed the project would not result in significant impacts using either classification.

The court also rejected the petitioner’s claim that the MND did not explain how delivery vans and truck trips were accounted for in the trip estimates. The court found that the trip generation rate classification used in the traffic analysis included delivery vans and truck traffic, and that additional discussion in the MND was not required.

Finally, the court held that the petitioner’s traffic claims related to congestion were moot given CEQA’s shift to using VMT as the metric for traffic impacts pursuant to CEQA Guidelines section 15064.3.

 

FIRST DISTRICT UPHOLDS CLASS 1 CATEGORICAL EXEMPTION FOR CONVERSION OF OIL WELL TO INJECTION WELL

In Sunflower Alliance v. California Department of Conservation, the First District Court of Appeal found that conversion of a former oil well into an injection constituted a negligible expansion of use and upheld the agency’s factual determination that the project fell within the scope of the Class 1 categorical exemption for existing facilitates.

Background

The project at issue involves the conversion of a former oil well into an injection well. The project involves modest changes to the existing injection well site, including removal of a well plug, installation of injection equipment inside the well, with the same continued use of the existing well pad and access road. The injected water will be confined to the aquifer by a barrier of about 1,000 vertical feet of shale.

The project was reviewed by Department of Conservation’s Division of Geologic Energy Management (CalGEM), the State Water Resources Control Board, and the Regional Water Quality Control Board. As the lead agency, CalGEM found that the project fit within the Class 1 categorical exemption. According to CEQA Guidelines section 15301, Class 1 consists of “the operation, repair, maintenance, permitting, leasing, licensing, or minor alteration of existing public or private structures, facilities, mechanical equipment, or topographical features, involving negligible or no expansion of existing or former use.” CalGEM found that the injection equipment would be installed within the existing well boring and would require no significant surface equipment or new drilling and would further eliminate the need for routine trucking of produced water from the applicant’s active oil wells.

The petitioner filed a petition for writ of mandate challenging CalGEM’s determination that the project was categorically exempt from CEQA. The trial court granted the petition on grounds that injection, rather than extraction, constitutes a “significantly different use” and issued a writ directing CalGEM to set aside its approval of the project.

CalGEM complied with the writ, but the project applicant appealed.

The Court of Appeal’s Decision

The First District Court of Appeal reversed. The court considered whether well conversion projects, as a group, are beyond the scope of the Class 1 exemption. The petitioner argued that any new use of a modified well is an impermissible expansion. In contrast, the applicant argued that the applicability of the Class 1 exemption turns on the degree of change occurring as part of a project.

The court did not fully agree with either the petitioner or applicant. The court found that adopting petitioner’s approach would render the term “negligible” superfluous contrary to established principles of statutory interpretation. Instead, the court focused on the environmental consequences of a change in use to conclude that application of the Class 1 exemption is appropriate where the risk of environmental harm resulting from a change in use is negligible. The court also noted this interpretation aligns with the fundamental purpose of categorical exemptions, which is to exclude from CEQA review certain classes of projects that have been determined to not have significant environmental impacts.

As applied here, the court found that the project fell within the scope of the Class 1 categorical exemption. The court reasoned that not only does the project involve only minor alteration to existing equipment, but also that the environmental risks of the conversion are negligible because the project’s approval includes a regulatory determination ensuring that the injected water cannot escape the underlying aquifer and harm people, property, or the environment.

The court found petitioner’s claims regarding environmental impacts were unsupported by substantial evidence and speculative. The court similarly rejected the petitioner’s claim that CalGEM’s request for additional technical information regarding migration of injected water as part of its review was evidence of a potentially significant environmental effect. The court noted that based on additional analysis and a requirement to conduct testing to confirm that analysis, any concerns regarding impacts to water quality had been resolved.

Finally, the petitioner argued that imposition of mitigation measures to eliminate the project’s alleged environmental impacts precluded use of the Class 1 categorical exemption. The court disagreed, finding that although numerous special conditions had been imposed as part of the project approval, the conditions were standards required for issuance of the permit, and therefore were not appropriately construed as CEQA mitigation measures.

– Hannah Rider

SIXTH DISTRICT HOLDS STATUTE OF LIMITATIONS FOR CEQA CHALLENGE TO AN EIR RUNS FROM DATE OF FILING OF NOTICE OF DETERMINATION FOLLOWING AGENCY’S FINAL APPROVAL OF A PROJECT

In Center for Biological Diversity v. County of San Benito (2024) 104 Cal.App.5th 22, the Sixth District held that CEQA’s 30-day statute of limitations begins to run from the date of filing the notice of determination (NOD) following the lead agency’s final approval of a project, in this case the denial of petitioners’ administrative appeal. In doing so, the court held that the finality of a project approval is governed by local rules pursuant to CEQA Guidelines section 15352.

Factual Background

On October 12, 2022, the county planning commission certified an EIR and approved a conditional use permit for the Betabel Project, a commercial roadside attraction that included a gas station, convenience store, a restaurant, a motel and other amenities. The county filed an NOD on October 14, 2022, following the planning commission’s approval. Petitioners appealed the planning commission’s decision to the board of supervisors. On November 10, 2022, the board voted to deny the appeals and approve the Project. The county filed a second NOD on the same day. On December 9, 2022, the petitioners filed writ petitions alleging violations of CEQA.

Real Parties in Interest demurred alleging the CEQA claims were filed more than 30 days after filing the NOD, and thus were time-barred. Real Parties contended that the NOD filed on October 14, 2022, triggered the 30-day statute of limitations, and that the petitioners’ administrative appeals did not affect the expiration of the 30-day limitation after the filing of the first NOD. The trial court agreed and sustained Real Parties’ demurrer. The petitioners appealed.

The Court of Appeal’s Decision

Reversing the trial court, the Court of Appeal applied a straightforward analysis of statutory construction to rule that the writ petitions were timely filed under the plain meaning of the Public Resources Code and the relevant county code provisions. The court noted that Public Resources Code section 21152, subdivision (a), requires a local agency to file an NOD within five working days after the approval or determination becomes final, and that local rules govern the finality of a project pursuant to CEQA Guidelines section 15352, subdivision (a). Here, the county code provided that the planning commission’s approval of a conditional use permit becomes final when the deadline to appeal expires without the filing of an appeal. A separate county code provision expressly provided that those “applications which have been appealed shall be deemed not approved until the board takes action to approve or deny.” Because the planning commission’s decision on the Project was timely appealed by the petitioners, the NOD filed after the planning commission’s action did not constitute a final approval and therefore did not trigger the 30-day statute of limitations.

The court noted that to rule that the writ petitions were untimely would run afoul of the principles of administrative law, requiring petitioners to bring a CEQA action to challenge a non-final decision without first exhausting their administrative remedies before filing suit.

– Natasha Roland

SUPREME COURT ADOPTS “BRIGHT LINE” RULE RESOLVING WHEN THE TIME TO APPEAL STARTS TO RUN IN WRIT OF ADMINISTRATIVE MANDATE PROCEEDINGS

In Meinhardt v. City of Sunnyvale (2024) 16 Cal.5th 643, the California Supreme Court adopted a new “bright line” rule for the time to appeal in administrative mandate proceedings. The Court held that the time to appeal begins to run from the date of entry of judgment or service of notice of entry of judgment, rather than with the filing of—or service of notice of the filing of—an order or other ruling. In doing so, the Court overturned the Fourth District Court of Appeal’s decision and settled a split in published authority.

Background

In May 2019, a petitioner filed a petition for writ of administrative mandate against the City of Sunnyvale challenging a temporary suspension of employment. On August 6, 2020, the trial court filed an order denying the petition. The trial court entered judgment on September 25, 2020.

The petitioner filed a notice of appeal on October 15, 2020. The Court of Appeal dismissed the appeal as untimely holding that the order filed on August 6, 2020, was the “final judgment” that triggered the time to appeal.  The Court of Appeal reasoned that the August 6, 2020, order denied the petition leaving no further action to be contemplated. In its decision, the Court of Appeal acknowledged a split in authority on the timeliness issue.

The California Supreme Court granted review.

The Supreme Court’s Decision

The Supreme Court began its discussion by explaining that Code of Civil Procedure Section 904.1 sets forth a list of appealable judgments and orders, one of which is commonly referred to as the “one final judgment” rule. The Court observed that an order granting or denying a petition for writ of mandate is not one of the appealable orders listed in Section 904.1, and the language of Code of Civil Procedure section 1094.5 contemplated entry of a judgment in an administrative writ proceeding. Therefore, the Court concluded, that in administrative writ proceedings, it is the entry of judgment—rather than the filing of an order—that signals the end of the proceeding.

The Supreme Court found that in some instances, including writ proceedings, courts have exercised discretion to allow a premature notice of appeal prior to official entry of judgment where an order or ruling is “sufficiently final,” in the context of preserving a right to appeal. The Supreme Court underscored, in contrast, that it was unaware of any case where a court construed a ruling as a judgment for the purposes of dismissing an appeal as untimely. Accordingly, the Court declined to do so here holding that the time to appeal an administrative mandate proceeding begins with the entry of judgment or service of notice of entry of judgment, not with the filing of an order or other ruling.

The Court explained that a bright line rule provides clarity to litigants. If any order deemed “sufficiently final” could start the time to appeal, parties would need to guess whether that, or any prior ruling, would be construed by the appellate court as the judgment that commenced the running of the clock. Without such clarity, filing of multiple protective appeals to ensure they are not untimely would become the norm.

– Adam Nir

FIRST DISTRICT UPHOLDS INFILL EXEMPTION FOR HOUSING PROJECT

In Nassiri v. City of Lafayette (2024) (June 27, 2024, No. A165324) ___ Cal.App.5th ___, the First District Court of Appeal held that the City of Lafayette properly relied on the “Class 32” infill exemption under CEQA Guidelines section 15332 for a 12-unit condominium project located adjacent to commercial buildings and a creek that provided habitat for Bird Species of Conservation Concern by the U.S. Fish and Wildlife Service. The Court clarified the circumstances in which a species may be considered “rare” under CEQA for purposes of the infill exemption.

Background

In 2018, a developer applied to demolish a vacant building and construct a new 4-story, 12-unit condominium building on a 0.3-acre lot adjacent to commercial buildings and a creek. The City Council adopted a resolution approving the project and finding it exempt from CEQA pursuant to the infill exemption under CEQA Guidelines section 15332.

The owner of an office building adjacent to the project filed a petition for writ of mandate, alleging that the approval of the project violated CEQA. The trial court granted the petition based on its finding that substantial evidence did not support the City’s determination that the project site held no value as a habitat for endangered, rare or threatened species, but rejected the other CEQA claims.

The developer and the City filed a motion for new trial arguing that the only potential habitat for rare birds near the project was an area not part of the project site under CEQA Guidelines section 15332, subdivision (b) (citing Protect Tustin Ranch v. City of Tustin (2021) 70 Cal.App.5th 951 (Tustin Ranch)). The trial court granted the motion for based on its finding that substantial evidence in the administrative record supported the developer’s and City’s position. The trial court subsequently entered judgment denying the petition for writ of mandate. Petitioner appealed.

The Court of Appeal’s Decision

Habitat for Rare Species

The Court of Appeal concluded that substantial evidence supported the City’s finding that the project site was not known to have any value as habitat for rare species.

To qualify for the infill exemption, the project site must have no value as habitat for endangered, rare or threatened species. A species is considered “rare” under CEQA when it meets the criteria of CEQA Guidelines section 15380, subdivision (b)(2), and either: (A) “exist[s] in such small numbers throughout all or a significant portion of its range that it may become endangered if its environment worsens,” or (B) “is likely to become endangered within the foreseeable future throughout all or a significant portion of its range and may be considered ‘threatened’ as that term is used in the Federal Endangered Species Act.”

The Court explained that while two bird species listed as Bird Species of Conservation Concern by the U.S. Fish and Wildlife Service were observed on the parcel near the proposed project, Petitioner provided no authority or legal analysis to support its claim that said species are “rare” under the CEQA Guidelines section 15380, subdivision (b)(2). The Court noted that Petitioner’s expert biologist never specifically addressed the definition of “rare” under the CEQA Guidelines, and only opined that the project site provided habitat value for “special-status species” without connecting this opinion to a conclusion that the species were therefore “rare.” The Court concluded that the City, on the other hand, provided substantial evidence in the form of expert reports explaining that the bird species were not “rare” based on the criteria listed under CEQA Guidelines section 15380. Moreover, the Court noted that even if Petitioner’s expert had provided an opinion that the bird species are rare, such a conclusion would only serve as evidence that the Court could weigh against evidence to the contrary.

While the Court did not reach the City’s argument that the “creek area” of the parcel where the bird species were observed was not part of the “project site” based on Tustin Ranch, supra, 70 Cal.App.5th 951, it did distinguish that case. Tustin Ranch held that an agency can consider a project site to be only part of an existing parcel for purposes of calculating the required 5-acre maximum site size for the CEQA infill development exemption. Here, the court explained, nothing suggested that the City considered the project site to exclude the “creek area.”

Air Quality

The Court also rejected Petitioner’s argument that the City lacked substantial evidence to conclude that the project would not result in a significant effect on air quality, another one of the criteria that must be satisfied before an agency can rely on the infill exemption.  Specifically, the Court disagreed with Petitioner’s argument that evidence in the form of a consultant firm’s report submitted by Petitioner constituted evidence that the project “would” result in significant effects on air quality, because the report only concluded that the project “may” result in impacts on the surrounding environment and “could” result in a potentially significant impact on air quality. The Court emphasized this distinction because the infill exemption “depends on if [a project] will have a significant effect.” Moreover, the Court agreed with the City that the consultant’s report did not constitute substantial evidence because it did not accurately reflect the scope of construction for the project or provide an accurate estimate of the associated health risks.

THIRD DISTRICT HOLDS TRIAL COURT MUST DETERMINE REVISED EIR IS CONSISTENT WITH PREVIOUS APPELLATE DECISION BEFORE DISCHARGING WRIT ON REMAND; THE ISSUE CAN BE HEARD BY CHALLENGE TO WRIT RETURN

In Save the Capitol, Save the Trees v. Department of General Services (2024) 101 Cal.App.5th 1237, the Third District Court of Appeal reversed the trial court’s discharge of a peremptory writ of mandate and found that on remand, the trial court must determine whether a revised Final EIR remedied the CEQA violations identified by the appellate court in its earlier opinion before discharging the writ. The court held that the matter could be brought by a challenge to the writ return because the court retained jurisdiction to address issues within the scope of the previous merits challenge.

Background

In an earlier case, Save Our Capitol! v. Department of General Services (2023) 87 Cal.App.5th 655, 711 (Save Our Capitol), the Court of Appeal determined that an EIR analyzing alterations to the California State Capitol violated CEQA. The court remanded the matter with directions to the trial court to issue a writ “directing [the Department of General Services] (DGS) to partially vacate its certification of the EIR and to revise and recirculate the deficient portions of the EIR consistent with this opinion before it considers recertifying the EIR.” On remand, the trial court ordered: (1) partial EIR decertification and vacation of the project approvals “consistent with the Opinion of the Court of Appeal”; (2) suspension of activities that would physically alter the capitol and no further discretionary approvals in reliance on the decertified EIR; and (3) for DGS to file a final return to the writ “upon certification of a revised EIR.”

DGS partially vacated its certification of the EIR and the associated project approvals and revised, recirculated, and certified the Final EIR. DGS then partially reapproved the project without a visitor center component that was part of the originally approved project. DGS then filed a final return, requesting that the court discharge the writ. The trial court discharged the writ, over plaintiff Save the Capitol’s objection, without determining whether the revised Final EIR remedied the CEQA violations identified by the appellate court.

The Court of Appeal’s Opinion

Remedial Action Ordered

The Court of Appeal held that the trial court could not discharge the writ without determining whether the revised EIR remedied the CEQA deficiencies identified earlier in Save Our Capitol. The trial court’s peremptory writ issued all three types of mandates authorized by Public Resources Code section 21168.9: (1) to void the action or decision by the agency under subdivision (a)(1); (2) to suspend project activities that affect the physical environment until action is taken to bring the situation into compliance under subdivision (a)(2); and (3) to take specific action to bring the determination into compliance under subdivision (a)(3). The court emphasized that the third directive required DGS to remedy the CEQA deficiencies consistent with the appellate court’s earlier opinion. In addition, section 21168.9, subdivision (b), required the trial court to retain jurisdiction, pending compliance with CEQA. The court noted that “ensur[ing] CEQA compliance after violations have been identified” is the “manifest purpose of a peremptory writ in this context.”

The court distinguished McCann v. City of San Diego (2023) 94 Cal.App.5th 284, as an instance where the appellate court’s prior direction to the trial court did not order remedial action in compliance with CEQA.

Writ Return Challenge

The parties disagreed whether Save the Capitol was permitted to challenge the sufficiency of the discharge of the writ by writ return or whether it was required to file a new action. The court held that it was acceptable for Save the Capitol to proceed by writ return challenge because the court retained jurisdiction under Public Resources Code section 21168.9, subdivision (b), as expressly stated in the writ.

The court rejected DGS’s argument that Save the Capitol should have used clearer language in the writ to make its preferred interpretation explicit, finding instead that the writ properly encompassed applicable law, the purpose of the writ, and the court’s order. The court also rejected DGS’s argument that requiring remedial action could result in inconsistent adjudications of the same issue if one plaintiff challenges the adequacy of the revised EIR via a new writ, while another does so by objection to the writ return. The court explained that such a result could be eliminated through a consolidation order. The court was similarly unpersuaded by DGS’s argument that allowing Save the Capitol to challenge the revised EIR via objection to the writ return would open the door to new merits challenges because no new issues are permitted to be raised in this manner.

Lastly, the court disagreed with Save the Capitol’s argument that discharge of the writ was premature because one component of the project was not yet reapproved. The court held that that because that component was not reapproved, it was no longer part of the project, and any later approval of that component would trigger a new deadline to challenge the action under CEQA.

CALIFORNIA SUPREME COURT UPHOLDS EIR FOR UC BERKELEY’S LONG-RANGE DEVELOPMENT PLAN AND PEOPLE’S PARK HOUSING PROJECT PURSUANT TO AB 1307 CEQA AMENDMENTS

In Make UC a Good Neighbor v. The Regents of the University of California (2024) 16 Cal.5th 43, the California Supreme Court held that the EIR for UC Berkeley’s Long-Range Development Plan (LRDP) and the People’s Park housing project complied with CEQA, reversing an earlier decision by the First District Court of Appeal. In doing so, the Court relied on new CEQA amendments (“AB 1307”) enacted by the Legislature for the purpose of abrogating the Court of Appeal’s decision. Pursuant to AB 1307, the Court held that: (1) the EIR was not required to analyze potential impacts related to student noise that could result from either the LRDP or the People’s Park housing project, and (2) the EIR was not required to analyze alternative locations for the People’s Park housing project.

Factual and Procedural History

The Regents approved UC Berkeley’s LRDP in July 2021. The LRDP identifies campus space, housing, and parking needs and describes development strategies generally intended to assist the university in addressing these needs. Among other things, the LRDP proposed the development of 11,073 student beds and 549 faculty and staff beds, in anticipation of enrollment increases.

Shortly after, in September 2021, the Regents approved the People’s Park housing project. Consistent with the LRDP, the People’s Park housing project sought to redevelop the People’s Park site near the UC Berkeley campus to provide 1,113 new student beds, 125 affordable and supporting housing beds, and 1.7 acres of open landscape.

In the summer of 2021, ahead of these approvals, the Regents certified an EIR that analyzed the environmental impacts of both the LRDP (on a programmatic level) and the People’s Park housing project (on a project level).

CEQA Litigation

Petitioners Make UC a Good Neighbor and People’s Park Historic District Advocacy Group (together, “Good Neighbor”) filed a petition for writ of mandate in October 2021, seeking to void the certification of the EIR and overturn the approvals of the LRDP and the People’s Park housing project. The trial court denied the petition. Good Neighbor appealed.

The Court of Appeal reversed, holding that the EIR violated CEQA in two ways: (1) by failing to study the noise impacts resulting from an increase in loud student parties, and (2) by failing to consider a reasonable range of alternative sites for the People’s Park housing project.

Both Good Neighbor and the Regents petitioned for review. The Supreme Court granted the Regents’ petition and denied Good Neighbor’s petition.

AB 1307

While the case was pending in the Supreme Court, and in response to the appellate court’s decision, the Legislature passed AB 1307. Under CEQA, as amended by AB 1307, (1) “for residential projects, the effects of noise generated by project occupants and their guests on human beings is not a significant effect on the environment” and (2) “institutions of public higher education shall not be required, in an environmental impact report prepared for a residential or mixed-use housing project, to consider alternatives to the location [if certain requirements are met].”

The Supreme Court’s Decision

Applying AB 1307, the Supreme Court held that none of Good Neighbors’ claims had merit.

Good Neighbor conceded—and the Court agreed—that under AB 1307, social noise could not be considered an impact of the People’s Park housing project, and the Regents were not required to analyze alternative locations for the People’s Park housing project.

Good Neighbor argued, however, that the EIR was still required to consider social noise impacts resulting from the LRDP because, unlike the People’s Park housing project, the LRDP was not a “residential project” for purposes of AB 1307. The Court disagreed. After finding the meaning of the statutory term “residential projects” to be ambiguous and acknowledging the Legislature’s intent to abrogate the appellate court’s interpretation that CEQA covered social noise from students and their guests, the Court determined that the Legislature intended for AB 1307 to apply to the residential aspects of the LRDP as well as the People’s Park housing project.

Additionally, Good Neighbor argued that the Court should decide its “moot” claim regarding the need to consider alternative locations because it raised issues that involved the public interest and were likely to recur. The Court declined. The Court explained that the mootness doctrine only applies where it is impossible for a court to provide effective relief—not where, as in this case, a petitioner is not entitled to any relief. Accordingly, the Court found that Good Neighbor’s request to consider AB 1307’s application to future projects constituted an impermissible request for an advisory opinion.

Accordingly, the Court reversed the appellate court’s opinion and held that judgment should be entered in favor of the Regents.

-Louisa Rogers