Blog

Second District Finds for Respondents on All Counts, Upholding EIR for “Iconic Gateway” Project in West Hollywood

In Los Angeles Conservancy v. City of West Hollywood (2017) ­18 Cal.App.5th 1031, the Second Appellate District upheld the trial court’s denial of a petition for writ of mandate, finding that the EIR’s treatment of alternatives was sufficient and that the city adequately responded to comments.

In 2014, the city certified an EIR for a mixed–use development in the Melrose Triangle section of West Hollywood. The project was the product of city incentives to redevelop the area in order to create a unified site design with open space, pedestrian access, and an iconic “gateway” building to welcome visitors and promote economic development. The EIR concluded that a significant and unavoidable impact would result from the demolition of a building eligible for listing as a California historic resource.

One alternative would have preserved the building in its entirety, by reducing and redesigning the project. The preservation alternative was ultimately rejected as infeasible because it was inconsistent with project objectives, and would eliminate or disrupt the project’s critical design elements.

After circulating the draft EIR, the project’s architects developed a site design which incorporated the building’s façade and mandated this design as a condition of approval. Furthermore, a subsequent fire destroyed 25 percent of the building, but left the façade intact. The final EIR and conditions were approved in 2014. Petitioners immediately filed suit.

In the court below, petitioner argued that the EIR’s analysis of the preservation alternative was inadequate, the city did not respond to public comments, and that the city’s finding that the alternative was infeasible was not supported by substantial evidence. The respondents prevailed on all claims and petitioner appealed.

Finding for respondents, the court reiterated the Laurel Heights standard that an analysis of alternatives does not require perfection, only that the EIR provide sufficient information to support a reasonable range of alternatives. The court rejected petitioner’s contention that the EIR was required to include a conceptual drawing of the preservation alternative. Furthermore, the EIR’s statement that preservation of the building would preclude construction of other parts of the project was self-explanatory and did not require additional analysis. The EIR’s use of estimates to calculate how the preservation alternative would reduce the project’s footprint did not create ambiguities that would confuse the public. Such imprecision is simply inherent in the use of estimates.

The court also found that the city’s responses to the three comments cited by the petitioner were made in good faith and demonstrated reasoned analysis.  The court reiterated that a response is not insufficient when it cross-references relevant sections of the draft EIR, and that the level of detail required in a response can vary. Here, the West Hollywood Preservation Alliance and the President of the Art Deco Society of Los Angeles opined in comments that the building could be preserved while achieving the project’s objectives. The city adequately responded to these comments by referencing, and expanding upon, the EIR’s analysis of the preservation alternative, where this option was considered. The last comment was of a general nature, so the city’s brief, general response was appropriate.

Finally, the court found sufficient evidence to support the city’s finding that the preservation alternative was infeasible. An alternative is infeasible when it cannot meet project objectives or when policy considerations render it impractical or undesirable. An agency’s determination of infeasibility is presumed correct and entitled to deference, if supported by substantial evidence in the record. The court found that the city’s conclusion that the alternative is infeasible was supported by substantial evidence in the record. Development plans, photographs, and testimony from senior planning staff support the city’s conclusion that retaining the building and reducing the project would not fulfill the project objectives of creating a unified site design, promoting pedestrian uses, and encouraging regional economic development.  That another conclusion could have be reached did not render the city’s decision flawed.

A consistent theme underlying the court’s decision was the city’s clear goal of revitalizing the entire site, in order to create a functional and attractive gateway for West Hollywood. Critical to the project’s success was removing the specific building that the petitioner sought to preserve. The court appeared reluctant to overcome such a strong mandate by flyspecking the EIR’s analysis of this acknowledged significant impact.

2017 CEQA Case Law: The Year in Review

2017 CEQA Case Law: The Year in Review

2017 was a busy year in CEQA jurisprudence, with over two dozen published cases. Below is a list of the most significant, with links to the full case summaries from the RMM blog.

Center for Biological Diversity v. California Department of Fish and Wildlife (2017) __Cal.App.5th­­__ (Case No. B280815)

In a partially published decision filed December 4, 2017, the Second District Court of Appeal upheld the lower court’s judgment and order on remand in Center for Biological Diversity v. California Department of Fish and Wildlife (2017) __Cal.App.5th­­__ (Case No. B280815). The court concluded that the trial court did not abuse its discretion in decertifying only the affected sections of the EIR, enjoining all project construction, and suspending some (but not all) of the project approvals. This CEQA remedy also provided adequate relief for violations of the Fish and Game Code.

Case Summary: https://www.rmmenvirolaw.com/2017/12/second-district-upholds-limited-writ-in-second-newhall-ranch-appeal/

Monterey Coastkeeper v. Monterey Water Resources Agency (2017) ___ Cal.App.5th ___ (Case No. H042623)

In Monterey Coastkeeper v. Monterey Water Resources Agency (2017) ___ Cal.App.5th ___ (Case No. H042623), the Sixth District Court of Appeal reversed the trial court’s judgment granting Monterey Coastkeeper’s petition for writ of mandate for violation of section 13260 of the Porter-Cologne Act (failure to file a report of waste discharge), holding that the petitioner had failed to exhaust its administrative remedies.

Case Summary: https://www.rmmenvirolaw.com/2017/12/sixth-district-court-of-appeal-holds-breach-of-public-trust-doctrine-claim-not-ripe-for-adjudication-in-the-absence-of-petitioners-exhaustion-of-its-administrative-remedies/

Cleveland National Forest Foundation v. San Diego Association of Governments (2017) 17 Cal.App.5th 413

On November 11, 2017, the Fourth District, Division One in Cleveland National Forest Foundation v. San Diego Association of Governments (2017) 17 Cal.App.5th 413 (Cleveland II), resolved the remaining issues on remand from California Supreme Court’s decision earlier this year. The court found that the EIR’s analysis of impacts and mitigation measures for air quality and impacts to agricultural land were insufficient and not supported by substantial evidence.

Case summary: https://www.rmmenvirolaw.com/2017/12/on-remand-fourth-district-determines-that-case-challenging-sandags-rtp-is-not-mooted-by-later-eir-and-resolves-ceqa-issues-on-the-merits/

Washoe Meadows Community v. Department of Parks and Recreation (2017) 17 Cal.App.5th 277.

In Washoe Meadows Community v. Department of Parks and Recreation (2017) 17 Cal.App.5th 277, the First District Court of Appeal upheld the trial court’s decision directing the Department of Parks and Recreation and the State Park and Recreation Commission to set aside project approvals where the draft EIR analyzed five alternative projects in detail, but did not identify one preferred alternative.

Case Summary: https://www.rmmenvirolaw.com/2017/11/in-a-case-of-first-impression-first-district-court-of-appeal-holds-that-presentation-of-five-alternatives-in-eir-without-designation-of-one-as-the-project-does-not-satisfy-ceqa/

Association of Irritated Residents v. Kern County Board of Supervisors (2017) 17 Cal.App.5th 708.

On November 21, 2017, the Fifth District partially published its decision in Association of Irritated Residents v. Kern County Board of Supervisors (2017) 17 Cal.App.5th 708. The published sections covered arguments about the baseline used for the oil refinery modification project, the mitigation of greenhouse gas (GHG) emissions, and the extent to which federal preemption precludes aspects of CEQA review of project impacts. In reversing the trial court’s judgment denying the petition for writ of mandate, the Court of Appeal upheld the EIR’s treatment of the project baseline and GHG emissions but determined that the county erred in relying on federal preemption to avoid analyzing and mitigating impacts from off-site rail activities.

Case Summary: https://www.rmmenvirolaw.com/2017/11/fifth-district-court-of-appeal-approves-of-oil-refinery-eirs-use-of-cap-and-trade-program-to-mitigate-ghg-emissions-but-disapproves-of-kern-countys-reliance-on-federal-preemption-in/

Kennedy Commission v. City of Huntington Beach (2017) 16 Cal.App.5th 841

On October 31, 2017 in Kennedy Commission v. City of Huntington Beach  (2017) 16 Cal.App.5th 841, the Fourth Appellate District reversed the lower court, finding that the city was a charter city, and thus exempt from the requirement that zoning ordinances and specific plans be consistent with the general plan.

Case Summary: https://www.rmmenvirolaw.com/2017/11/fourth-district-rejects-challenge-to-the-city-of-huntington-beachs-housing-element-applying-charter-city-exemption/

Highway 68 Coalition v. County of Monterey (2017) 14 Cal.App.5th 883

The Sixth District Court of Appeal held in the partially-published opinion, Highway 68 Coalition v. County of Monterey (2017) 14 Cal.App.5th 883, that general plan consistency is not a CEQA issue, and therefore mandate procedures for CEQA violations are inapplicable.

Case Summary: https://www.rmmenvirolaw.com/2017/11/sixth-district-court-of-appeal-upholds-trial-courts-use-of-interlocutory-remand-on-determination-regarding-general-plan-consistency/

Placerville Historic Preservation League v. Judicial Council of California (2017) 16 Cal.App.5th 187

On October 16, 2017, the First District Court of Appeal published its decision in Placerville Historic Preservation League v. Judicial Council of California (2017) 16 Cal.App.5th 187, upholding the San Francisco County Superior Court’s denial of a petition for writ of mandate challenging the Judicial Council of California’s decision to certify a Final EIR and approve the New Placerville Courthouse Project.

Case Summary: https://www.rmmenvirolaw.com/2017/10/first-district-court-of-appeal-upholds-judicial-council-of-californias-determination-that-closure-of-downtown-placerville-courthouse-would-not-lead-to-significant-urban-decay-impacts/

Protect Telegraph Hill v. City and County of San Francisco (2017) 16 Cal.App.5th 261

In Protect Telegraph Hill v. City and County of San Francisco (2017) 16 Cal.App.5th 261, the First District Court of Appeal, Division Three, upheld the City and County of San Francisco’s finding that a conditional use authorization for the restoration of a small cottage and construction of a three-unit condominium on Telegraph Hill was categorically exempt from CEQA, and found that the city’s conditions of approval relating to construction were not mitigation for pedestrian and traffic impacts.

Case Summary: https://www.rmmenvirolaw.com/2017/10/first-district-upholds-categorical-exemption-with-conditions-of-approval-and-conditional-use-authorization-for-residential-project-on-infill-site-in-transit-priority-area/

Pesticide Action Network North America v. California Department of Pesticide Regulation (2017) 16 Cal.App.5th 224

In Pesticide Action Network North America v. California Department of Pesticide Regulation (2017) 16 Cal.App.5th 224 (republished as modified), the First Appellate District reversed the Alameda Superior Court and found that environmental documents prepared by the California Department of Pesticide Regulation, regarding amended labelling for two pesticides, inadequately analyzed potential impacts on honeybees. The court held that the Department was required to analyze the environmental baseline, alternatives, and cumulative impacts in documents promulgated under CEQA’s exemption for certified regulatory programs (CRP).

Case Summary: https://www.rmmenvirolaw.com/2017/10/first-circuit-finds-environmental-review-under-certified-regulatory-program-inadequate/

Respect Life South San Francisco v. City of South San Francisco (2017) 15 Cal.App.5th 449

In Respect Life South San Francisco v. City of South San Francisco (2017) 15 Cal.App.5th 449, the First District Court of Appeal, Division One, upheld the City of South San Francisco’s (City) finding that a conditional use permit for the conversion of an office building into a medical clinic was categorically exempt from CEQA, as well as the City’s implied finding that the unusual circumstances exception did not apply.

Case Summary: https://www.rmmenvirolaw.com/2017/09/first-district-upholds-categorical-exemption-for-planned-parenthood-clinic-and-implied-finding-of-no-unusual-circumstances-under-the-fair-argument-test/

Bridges v. Mt. San Jacinto Community College District (2017) 14 Cal.App.5th 104

In Bridges v. Mt. San Jacinto Community College District (2017) 14 Cal.App.5th 104, the Fourth District Court of Appeals held that a land acquisition agreement entered into by the Mt. San Jacinto Community College District to purchase property from the Riverside County Regional Park & Open-Space District for potential future use as the site of new campus did not trigger the duty to prepare an EIR.

Case Summary: https://www.rmmenvirolaw.com/2017/08/fourth-district-holds-that-land-acquisition-agreement-did-not-trigger-duty-to-prepare-an-eir/

Friends of the Eel River v. North Coast Railroad Authority (2017) 3 Cal.5th 677

In Friends of the Eel River v. North Coast Railroad Authority (2017) 3 Cal.5th 677, the California Supreme Court held that the Interstate Commerce Commission Termination Act does not preempt CEQA when a California public agency decides to undertake a new railroad project, even if the state agency later authorizes a private entity to operate the new rail line. The Court therefore concluded that the North Coast Railroad Authority was required to comply with CEQA prior to taking steps to reinitiate rail service on a segment of an interstate rail line that had gone out of operation for many years. The Court declined, however, to enjoin the ongoing operations of the railroad by NWPCo, the private operator. Because these operations had been occurring during the course of the litigation against NCRA, any such injunction would intrude into an area of activity that is preempted by the ICCTA, namely, private railroad operations.

Case Summary: https://www.rmmenvirolaw.com/2017/08/california-supreme-court-holds-that-state-agency-compliance-with-ceqa-is-not-preempted-by-the-iccta/

Cleveland National Forest Foundation v. San Diego Association of Governments (2017) 3 Cal. 5th 497

In a 6/1 opinion, the California Supreme Court held that the San Diego Association of Governments (SANDAG) did not abuse its discretion by failing to present a consistency analysis in the EIR for its 2011 regional transportation plan (RTP) comparing anticipated GHG emissions with the long-term reduction goals presented in Executive Order (EO) S-3-05, in Cleveland National Forest Foundation v. San Diego Association of Governments (2017) 3 Cal. 5th 497.  The court reasoned that SANDAG had adequately informed the public, using information available at the time, of inconsistencies with overall state climate goals.

Case Summary: https://www.rmmenvirolaw.com/2017/07/3822/

Friends of Outlet Creek v. Mendocino County Air Quality Management District (2017) 11 Cal.App.5th 1235

In Friends of Outlet Creek v. Mendocino County Air Quality Management District (2017) 11 Cal.App.5th 1235, the First District Court of Appeal held that a responsible agency air quality management district may be sued under CEQA, but such suit must be limited to the agency’s specific discretionary action and may not challenge prior lead agency approvals. In addition, the court held that such an action must be brought as an administrative mandamus proceeding under Code of Civil Procedure section 1094.5.

Case Summary: https://www.rmmenvirolaw.com/2017/07/first-district-reversal-allows-for-challenge-to-local-air-districts-limited-discretionary-approval-under-ceqa/

Grist Creek Aggregates, LLC v. The Superior Court of Mendocino County (2017) 12 Cal.App.5th­­­ 979

On June 14, 2017, Division One of the First Appellate District published its decision in Grist Creek Aggregates, LLC v. The Superior Court of Mendocino County (2017) 12 Cal.App.5th­­­ 979, in which the Court of Appeal held that a county air district board’s tie vote on the petitioner’s administrative appeal of an asphalt production facility’s construction permit, effectively resulted in the appeal’s denial, rendering the denial subject to judicial review.

Case Summary: https://www.rmmenvirolaw.com/2017/07/air-district-boards-tie-vote-on-authority-to-construct-permit-is-effectively-a-decision-not-to-revoke-it-which-is-reviewable-for-prejudicial-abuse-of-discretion/

Kutzke v. City of San Diego (2017) 11 Cal.App.5th 1034

On May 23, 2017, the Fourth District Court of Appeal court ordered published Kutzke v. City of San Diego (2017) 11 Cal.App.5th 1034. In a succinct opinion, the court upheld the city’s decision to deny a mitigated negative declaration (MND), initially approved by the planning commission, regarding an application to subdivide two hillside lots and build three residences.

Case Summary: https://www.rmmenvirolaw.com/2017/06/denial-of-mitigated-negative-declaration-upheld-for-small-san-diego-subdivision/

Sierra Club v. County of Sonoma (2017) 11 Cal.App.5th 11

On April 21, 2017, the First District Court of Appeal in Sierra Club v. County of Sonoma (2017) 11 Cal.App.5th 11, affirmed the trial court and ruled that Sonoma County’s ordinance, issuing an erosion-control permit to establish a vineyard was a ministerial act, not subject to CEQA.

Case Summary: https://www.rmmenvirolaw.com/2017/05/first-district-rules-that-issuing-erosion-control-permit-under-sonoma-county-ordinance-was-ministerial-act-exempt-from-ceqa/

Save our Heritage Organization v. City of San Diego (2017) 11 Cal.App.5th 154

In Save our Heritage Organization v. City of San Diego (2017) 11 Cal.App.5th 154, the Fourth District Court of Appeal upheld a trial court’s denial of a Code of Civil Procedure section 1025.1 attorneys’ fee award to the prevailing real party in interest.

Case Summary: https://www.rmmenvirolaw.com/2017/05/despite-being-a-successful-party-real-party-in-interest-denied-attorneys-fee-award-by-fourth-district/

POET, LLC v. State Air Resources Board (2017) 12 Cal.App.5th 52

In POET, LLC v. State Air Resources Board (2017) 12 Cal.App.5th 52 (“POET II”), the Fifth District Court of Appeal held that the California Air Resources Board (CARB) failed to comply with the terms of the writ of mandate issued by the same court in POET, LLC v. State Air Resources Board (2013) 218 Cal.App.4th 681 (“POET I”). The court invalidated the trial court’s discharge of the writ, modified the existing writ, and ordered CARB to correct its defective CEQA Environmental Analysis (EA).

Case Summary: https://www.rmmenvirolaw.com/2017/04/fifth-district-rules-carb-acted-in-bad-faith-in-selecting-baseline-for-analysis-of-low-carbon-fuel-standards-regulations/

Friends of the College of San Mateo v. San Mateo County Community College (2017) 11 Cal.App.5th 596

On remand from the Supreme Court’s holding in Friends of the College of San Mateo Gardens v. San Mateo County Community College (2016) 1 Cal.5th 926 (San Mateo I ), the First District interpreted the Supreme Court’s direction as requiring the application of the fair argument standard of review to claims challenging an addendum to a negative declaration in Friends of the College of San Mateo Gardens v. San Mateo County Community College District (2017) 11 Cal. App.5th 596.

Case Summary: https://www.rmmenvirolaw.com/category/blog/

The Urban Wildlands Group, Inc. v. City of Los Angeles (2017) 10 Cal.App.5th 993

In The Urban Wildlands Group, Inc. v. City of Los Angeles (2017) 10 Cal.App.5th 993, the Second District Court of Appeal held that the mandatory relief provisions of Code of Civil Procedure section 473, subdivision (b), do not apply where counsel fails to lodge the administrative record in a CEQA proceeding and receives a judgment denying the petition for writ of mandate.

Case Summary: https://www.rmmenvirolaw.com/2017/04/second-district-holds-that-failure-to-lodge-administrative-record-barred-post-trial-relief/

California Chamber of Commerce v. State Air Resources Board (2017) 10 Cal.App.5th 604

In a 2-1 opinion, the Third District Court of Appeal upheld the auction-sale component of the cap-and-trade program created by the State Air Resources Board pursuant to the California Global Warming Solutions Act of 2006 (“AB 32”) in California Chamber of Commerce v. State Air Resources Board (2017) 10 Cal.App.5th 604.

Case Summary: https://www.rmmenvirolaw.com/2017/04/third-district-court-of-appeal-upholds-state-air-resources-boards-ab-32-cap-and-trade-program/

Aptos Council v. County of Santa Cruz (2017) 10 Cal.App.5th 266

In Aptos Council v. County of Santa Cruz (2017) 10 Cal.App.5th 266, the Sixth District held that the County of Santa Cruz did not engage in piecemeal review when it separately adopted three different zoning ordinances. The court also upheld the negative declaration for an ordinance increasing the height and density of hotels.

Case Summary: https://www.rmmenvirolaw.com/2017/04/sixth-district-rules-county-of-santa-cruz-did-not-engage-in-piecemeal-review-and-upholds-negative-declaration/

Banning Ranch Conservancy v. City of Newport Beach (2017) 2 Cal.5th 918

In Banning Ranch Conservancy v. City of Newport Beach (2017) 2 Cal.5th 918, the California Supreme Court held that CEQA requires an EIR for a project located within a coastal zone to identify which areas in a project site might qualify as “environmentally sensitive habitat areas” (ESHA) under the California Coastal Act and account for those areas in its analysis of project alternatives and mitigation measures.

Case Summary: https://www.rmmenvirolaw.com/2017/03/california-supreme-court-holds-that-ceqa-requires-eirs-for-projects-located-within-coastal-zones-to-identify-potential-environmentally-sensitive-habitat-areas-as-defined-by-the-calif/

Residents Against Specific Plan 380 v. County of Riverside (2017) 9 Cal.App.5th 941

On March 15, 2017 the Fourth District certified for publication its February 4, 2017 decision in Residents Against Specific Plan 380 v. County of Riverside (2017) 9 Cal.App.5th 941, upholding the EIR for a master- planned community (project). A citizens group challenged the sufficiency of the EIR and the county’s approval process on six grounds. The court found for the county and real party in interest, Hanna Marital Trust (applicant), on every count.

Case Summary: https://www.rmmenvirolaw.com/2017/03/fourth-district-upholds-eir-for-master-planned-community-and-concludes-that-county-not-required-to-recirculate/

City of San Jose v. Superior Court of Santa Clara County (2017) 2 Cal.5th 608

In City of San Jose v. Superior Court of Santa Clara County (2017) 2 Cal.5th 608, the City of San Jose argued that messages communicated through personal accounts of city employees were not public records subject to disclosure under the California Public Records Act (“CPRA”). The Supreme Court disagreed, holding that a city employee’s emails about public business are not excluded from disclosure simply because they have been sent, received, or stored in a personal email account.

Case Summary: https://www.rmmenvirolaw.com/2017/03/california-supreme-court-rules-personal-emails-may-be-considered-public-records-subject-to-disclosure-under-the-public-records-act/

Central Coast Forest Association v. Fish and Game Commission (2017) 2 Cal.5th 594

On February 27, 2017, the California Supreme Court issued its unanimous opinion in Central Coast Forest Association v. Fish and Game Commission (2017) 2 Cal.5th 594, reversing an appellate decision holding that Plaintiff’s petition to delist coho salmon south of San Francisco from the register of endangered species was procedurally improper.

Case Summary: https://www.rmmenvirolaw.com/2017/03/high-court-reverses-appellate-decision-limiting-use-of-delisting-petitions-under-the-california-endangered-species-act-but-avoids-reaching-merits-of-fish-and-game-commissions-decision-denyin/

Second District Upholds Limited Writ in Second Newhall Ranch Appeal

In a partially published decision filed December 4, 2017, the Second District Court of Appeal upheld the lower court’s judgment and order on remand in Center for Biological Diversity v. California Department of Fish and Wildlife (2017) __Cal.App.5th­­__ (Case No. B280815).

This is the second appeal of the EIR for the Newhall Ranch development project. It follows the Supreme Court’s 2015 decision where the Court determined that the EIR’s analysis of GHG emissions improperly relied on a “business-as-usual” model and that mitigation adopted for the stickleback fish (catch and relocate) was itself a prohibited taking under the California Fish and Game Code. Subsequently, the Second District affirmed in part and reversed in part its original decision. The appellate court remanded the matter to the trial court, with instructions to issue an order consistent with the Supreme Court’s opinion, but otherwise granting the trial court discretion to resolve all outstanding matters under Public Resources Code section 21168.9.

After additional briefing and a hearing, the trial court issued a limited writ. The writ decertified those sections of the EIR concerning GHG emissions and mitigation measures for the stickleback; enjoined all project activity, including construction; and suspended two of the six project approvals. This appeal followed.

In the unpublished portion the of the opinion, the court found that the writ was not a separate appealable post-judgment order or injunction, and therefore the court had jurisdiction to hear the appeal under Code of Civil Procedure section 904.1.

The court reviewed the lower court’s interpretation of section 21168.9 de novo.  The court determined that the trial court did not abuse its discretion in partially decertifying the EIR, as section 21168.9 expressly permits decertification of an EIR “in whole or in part.” The court also held that after partial decertification, it is permissible to leave in place project approvals that do not relate to the affected section of the EIR. This is consistent with the statute’s implicit mandate that project activities that do not violate CEQA must be permitted to go forward.

The court found that the trial court did not abuse its discretion in issuing the limited writ. The lower court adequately supported its findings and demonstrated that project activities were severable, that severance would not prejudice compliance with CEQA, and that the remaining activities complied with CEQA. The court noted that prejudice with CEQA compliance is particularly unlikely here, given the court’s injunction against further construction.

Finally, the court rejected petitioners’ contention that the writ, issued under CEQA, does not provide an adequate remedy for California Fish and Game Code violations. While acknowledging that section 21168.9 is part of CEQA, the streambed alteration agreement, which remains in place, already prohibits the taking of sticklebacks. Furthermore, the injunction barring project construction provides a suitable remedy for this violation.

On Remand, Fourth District Determines that Case Challenging SANDAG’s RTP Is Not Mooted by Later EIR and Resolves CEQA Issues on the Merits

On November 11, 2017, the Fourth District, Division One in Cleveland National Forest Foundation v. San Diego Association of Governments (2017) 17 Cal.App.5th 413 (Cleveland II), resolved the remaining issues on remand from California Supreme Court’s decision earlier this year.

SANDAG certified a programmatic EIR for its 2050 Regional Transportation Plan/Sustainable Communities Strategy in 2011. Petitioners challenged that EIR, alleging multiple deficiencies under CEQA, including the EIR’s analysis of greenhouse gas (GHG) impacts, mitigation measures, alternatives, and impacts to air quality and agricultural land. The Court of Appeal held that the EIR failed to comply with CEQA in all identified respects.  The Supreme Court granted review on the sole issue of whether SANDAG was required to use the GHG emission reduction goals in Governor Schwarzenegger’s Executive Order S-3-05 as a threshold of significance. Finding for SANDAG, the Court left all other issues to be resolved on remand.

First, the Court of Appeal ruled that the case was not moot, although the 2011 EIR had been superseded by a new EIR certified in 2015, because the 2011 version had never been decertified and thus could be relied upon. The court also found that petitioners did not forfeit arguments from their original cross-appeal by not seeking a ruling on them. And, even if failing to raise the arguments was a basis for forfeiture, the rule is not automatic, and the court has discretion to resolve important legal issues, including compliance with CEQA.

Second, the court reiterated the Supreme Court’s holding, that SANDAG’s choice of GHG thresholds of significance was adequate for this EIR, but may not be sufficient going forward. Turning to SANDAG’s selection of GHG mitigation measures, the court found that SANDAG’s analysis was not supported by substantial evidence, because the measures selected were either ineffective (“assuring little to no concrete steps toward emissions reductions”) or infeasible and thus “illusory.”

Third, also under the substantial evidence standard of review, the court determined that the EIR failed to describe a reasonable range of alternatives that would plan for the region’s transportation needs, while lessening the plan’s impacts to climate change. The EIR was deficient because none of the alternatives would have reduced regional vehicles miles traveled (VMT). This deficiency was particularly inexplicable given that SANDAG’s Climate Action Strategy expressly calls for VMT reduction. The measures, policies, and strategies in the Climate Action Strategy could have formed an acceptable basis for identifying project alternatives in this EIR.

Fourth, the EIR’s description of the environmental baseline, description of adverse health impacts, and analysis of mitigation measures for air quality, improperly deferred analysis from the programmatic EIR to later environmental review, and were not based on substantial evidence.  Despite acknowledging potential impacts from particulate matter and toxic air contaminants on sensitive receptors (children, the elderly, and certain communities), the EIR did not provide a “reasoned estimate” of pollutant levels or the location and population of sensitive receptors. The EIR’s discussion of the project’s adverse health impacts was impermissibly generalized. The court explained that a programmatic EIR improperly defers mitigation measures when it does not formulate them or fails to specify the performance criteria to be met in the later environmental review. Because this issue was at least partially moot given the court’s conclusions regarding defects in the EIR’s air quality analysis, the court simply concurred with the petitioners’ contention that all but one of EIR’s mitigation measures had been improperly deferred.

The court made two rulings regarding impacts to agricultural land. In finding for the petitioners, the court held that SANDAG impermissibly relied on a methodology with “known data gaps” to describe the agricultural baseline, as the database did not contain records of agricultural parcels of less than 10 acres nor was there any record of agricultural land that was taken out of production in the last twenty years.  This resulted in unreliable estimates of both the baseline and impacts. However, under de novo review, the court found that the petitioners had failed to exhaust their remedies as to impacts on small farms and the EIR’s assumption that land converted to rural residential zoning would remain farmland. While the petitioners’ comment letter generally discussed impacts to agriculture, it was not sufficiently specific so as to “fairly apprise” SANDAG of their concerns.

Justice Benke made a detailed dissent. Under Benke’s view, the superseded 2011 EIR is “most likely moot” and in any event, that determination should have been left to the trial court on remand. This conclusion is strengthened, when, as here, the remaining issues concern factual contentions. As a court of review, their record is insufficient to resolve those issues.

OPR Proposes First Comprehensive Update to the CEQA Guidelines in Twenty Years, Affecting Several Areas of Analysis

On November 27, 2017, the Governor’s Office of Planning and Research (OPR) presented the California Natural Resources Agency with proposed amendments to the CEQA Guidelines (hyperlink to: http://opr.ca.gov/docs/20171127_Comprehensive_CEQA_Guidelines_Package_Nov_2017.pdf). As Director Ken Alex noted in his transmittal letter (hyperlink to: http://opr.ca.gov/docs/20171127_Transmittal_Letter_OPR_to_Resources_Nov_2017.pdf), this is the most comprehensive update to the Guidelines since the late 1990s. Among other changes, OPR’s amendments affect the analysis of energy impacts, promote the use of vehicle miles traveled (VMT) as the primary metric for transportation impacts, and clarify Guidelines section 15126.2 to specify that an agency must analyze hazards that a project may risk exacerbating.

The amendments to the CEQA Guidelines have been shaped by several years of discussion and public comment. OPR began discussions with stakeholders in 2013 and released a preliminary discussion draft of the comprehensive changes to the Guidelines in August 2015. OPR received hundreds of comments on the proposed updates and has provided a document with Thematic Responses to Comments (hyperlink to: http://opr.ca.gov/docs/20171127_OPR_Thematic_Responses_to_Comments_Nov_2017.pdf).

One of the most highly-anticipated and impactful changes is the switch from the level of service (LOS) to VMT as the primary metric in analysis of transportation impacts. These updates were required by Senate Bill 743, which directed OPR to develop alternative methods for measuring transportation impacts. Due to the complexity of these changes, OPR has provided a Technical Advisory on Evaluating Transportation Impacts in CEQA (hyperlink to: http://opr.ca.gov/docs/20171127_Transportation_Analysis_TA_Nov_2017.pdf) to assist public agencies.

Some highlights from the proposed updates include:

  1. Appendix G: adds new questions related to Energy, VMT, and Wildfire;
  2. Guidelines section 15064.3 (SB 743): establishes VMT as the primary metric for analyzing transportation impacts, with agencies having a two-year opt-in period to make the transition easier;
  3. Energy impacts: includes changes to Appendix G and makes clear that analysis must include energy use for all project phases and include transportation-related energy;
  4. Guidelines section 15126.2, subdivision (a): adds the phrase “or risks exacerbating” to implement the California Supreme Court’s holding in California Building Industry Association v. Bay Area Air Quality Management District (2015) 62 Cal.4th 369, requiring an EIR to analyze existing hazards that a project may make worse; and
  5. Guidelines section 15064.4: includes clarifications related to the analysis of greenhouse gas (GHG) emissions to reflect the Supreme Court’s decisions in Cleveland National Forest Foundation v. San Diego Association of Governments (2017) 3 Cal.5th 497 and Center for Biological Diversity v. Department of Fish & Wildlife (2015) 62 Cal.4th 204 (“Newhall Ranch”)

As of December 2017, the Natural Resources Agency has not initiated the formal administrative rulemaking process under the Administrative Procedure Act. When formal rulemaking is initiated, there will be additional opportunities for public review, with the possibility of further revisions. The Secretary for the Natural Resources Agency could then adopt OPR’s proposed changes. The Office of Administrative Law would need to approve the changes before they could go into effect.

See http://opr.ca.gov/ceqa/updates/guidelines/ for more details, including information about how to register to receive updates from OPR on the status of the rulemaking process.

Sixth District Court of Appeal Holds Breach of Public Trust Doctrine Claim Not Ripe for Adjudication in the Absence of Petitioner’s Exhaustion of its Administrative Remedies

In Monterey Coastkeeper v. Monterey Water Resources Agency (2017) ___ Cal.App.5th ___ (Case No. H042623), the Sixth District Court of Appeal reversed the trial court’s judgment granting Monterey Coastkeeper’s petition for writ of mandate for violation of section 13260 of the Porter-Cologne Act (failure to file a report of waste discharge), holding that the petitioner had failed to exhaust its administrative remedies.

The Monterey County Water Resources Agency (MCWRA) is a flood control and water agency responsible for operation of the Reclamation Ditch and the Blanco Drain, which collects agricultural wastewater and eventually discharges into surface waters that are subject to the Porter-Cologne Act. Petitioner Monterey Coastkeeper alleged that the MCWRA was in violation of section 13260 of the Porter-Cologne Act for failing to submit a report of waste discharge to the Regional Water Quality Control Board (RWQCB) as required under Porter-Cologne.

Petitioner claimed that it did not have an administrative remedy because the Porter-Cologne Act did not have a defined procedure to administratively pursue grievances for failure to file a report of waste discharge. The court disagreed. It stated that the Porter-Cologne Act expressly gives the RWQCB the authority to require a report of waste discharge, and to hold a discharger civilly liable for failure to do so. The Porter-Cologne Act further provides that the RWQCB may be requested to act, and their decision is appealable to the State Water Resources Control Board. The State Water Resources Control Board decision or order is then subject to judicial review by a writ of mandate. The court found that petitioner could have followed these statutory procedures—but it had not done so. The court held that petitioner had failed to exhaust its administrative remedies.

Due to its failure to exhaust, the court further found that petitioner’s claim for breach of duty under the public trust doctrine was unripe. The court held that because petitioner had not initiated the administrative review process, there was no administrative record upon which to base a decision as to whether the public trust doctrine had been violated.

Fifth District Court of Appeal Approves of Oil Refinery EIR’s Use of Cap-and-Trade Program to Mitigate GHG Emissions, But Disapproves of Kern County’s Reliance on Federal Preemption in Failing to Analyze Off-Site Rail Activities

On November 21, 2017, the Fifth District partially published its decision in Association of Irritated Residents v. Kern County Board of Supervisors (2017) 17 Cal.App.5th 708. The published sections covered arguments about the baseline used for the oil refinery modification project, the mitigation of greenhouse gas (GHG) emissions, and the extent to which federal preemption precludes aspects of CEQA review of project impacts. In reversing the trial court’s judgment denying the petition for writ of mandate, the Court of Appeal upheld the EIR’s treatment of the project baseline and GHG emissions but determined that the county erred in relying on federal preemption to avoid analyzing and mitigating impacts from off-site rail activities.

The project involved modifications proposed by Alon USA to an existing petroleum refinery northwest of the City of Bakersfield. The refinery had undergone several ownership changes since 1932, with Alon USA purchasing it from Flying J and its subsidiary during the latter’s 2008 bankruptcy proceedings. Alon USA sought to expand existing rail, transfer and storage facilities, including the construction of a double rail loop connected to the BNSF railway. The expanded train facilities would allow the transport of crude oil from the Bakken formation in North Dakota to the refinery for processing. The Association of Irritated Residents, Center for Biological Diversity, and Sierra Club filed suit after the County certified an EIR and approved the project.

First, the court dealt with plaintiffs’ arguments about the use of year 2007 as the baseline for air pollution emissions instead of using year 2013 – the year that the County published the notice of preparation. In discussing Neighbors for Smart Rail v. Exposition Metro Line Const. Authority (2013) 57 Cal.4th 439, 457 (“Neighbors”), the court established that it was interpreting Neighbors to only require heightened scrutiny of baselines that use hypothetical future conditions and not of those that use data from past, fluctuating conditions. Based on this interpretation, the court found no error in the County’s use of data from year 2007 because substantial evidence supported this deviation from the “normal” baseline. The court concluded that it was reasonable to include an operating refinery in the baseline because: (a) existing permits and entitlements allow for the processing of up to 70,000 barrels per day; (b) Flying J’s bankruptcy filing in 2008 only temporarily halted processing of hydrocarbons; (c) refinery operations have been subject to prior CEQA review; and (d) the processing of crude oil could begin again without the currently proposed project. The court then turned to whether the County’s choice of year 2007 was supported by substantial evidence, and found that it was because 2007 was the last full year of refinery operations, and was not some hypothetical, maximum authorized amount. The court even included its own calculations of the average barrels per day for the period of 2001 through 2008 to show that the year-2007 figure of 60,389 barrels-per-day was less than the average of 60,994 barrels-per-day.

Second, the court addressed GHG emissions arguments. The court started by analyzing under the de novo review standard a question of first impression: can the volume of a project’s estimated GHG emissions be decreased to reflect the use of allowances and offset credits under the state’s cap-and-trade program? The court concluded that this use of the cap-and-trade program did not violate CEQA because Section 15064.4, subd. (b)(3), effectively directed the County to consider the project’s compliance with the state’s cap-and-trade program as a “regulation[] or requirement[] adopted to implement a statewide . . . plan for the reduction of mitigation of greenhouse gas emissions.” And the court concluded that the project’s compliance with the cap-and-trade program could be part of the substantial evidence supporting a finding of less-than-significant impacts from GHG emissions even though surrender of allowances would not result in the project emitting fewer GHG molecules than if the allowance had not been surrendered. The court explained that the cap-and-trade program was designed so that the “limited allocation and use of allowances means they are not available for use elsewhere” in the state.

In the final published section, the court dealt with federal preemption and off-site rail impacts. Claiming that the Interstate Commerce Commission Termination Act of 1995 (ICCTA) preempted CEQA review, the County had excluded analysis of some of the impacts from off-site main line rail operations that will deliver crude oil to the refinery. The court disagreed. Interpreting the California Supreme Court’s direction in Friends of Eel River v. North Coast Railroad Authority (2017) 3 Cal.5th 677, 722, the court of appeal concluded that the development of information pursuant to CEQA is not categorically preempted but may be preempted on an as-applied basis. Then, as an alternative to that broad legal conclusion, the court considered whether categorical preemption applied to the specific circumstances in this case. It concluded that no categorical preemption applied because analysis of indirect environmental effects “would impose no permitting or preclearance by a state or local agency upon the delivery of crude oil to the project site by a rail carrier,” and “would not control or influence matters directly regulated under federal law.” The court also concluded that there was no as-applied preemption because the environmental analysis of off-site rail activities “would not prevent, burden, or interfere with BNSF Railway’s operation.” Finally, the court directed the County on remand to use the tests stated in this opinion to determine whether particular mitigation measures may be preempted by the ICCTA.

 

 

In a Case of First Impression, First District Court of Appeal Holds That Presentation of Five Alternatives in EIR, Without Designation of One as the ‘Project,’ Does Not Satisfy CEQA’s Requirement for a Stable Project Description

In Washoe Meadows Community v. Department of Parks and Recreation (2017) 17 Cal.App.5th 277, the First District Court of Appeal upheld the trial court’s decision directing the Department of Parks and Recreation and the State Park and Recreation Commission to set aside project approvals where the draft EIR analyzed five alternative projects in detail, but did not identify one preferred alternative.

In 1984, the Department of Parks and Recreation acquired 777 acres of land in the Lake Tahoe Basin—608 acres of the property were designated as Washoe Meadows State Park and the remainder contained an existing golf course. Studies conducted in the early 2000s indicated that the layout of the golf course was contributing to sediment running into Lake Tahoe, which contributed to deterioration of habitat and water quality in the lake.

In 2010, the Department circulated a draft EIR to address the concerns about the golf course. The draft EIR analyzed five alternatives in equal detail, with the stated purpose of “improv[ing] geomorphic processes, ecological functions, and habitat values of the Upper Truckee River within the study area, helping to reduce the river’s discharge of nutrients and sediment that diminish Lake Tahoe’s clarity while providing access to public recreation opportunities ….” The draft EIR did not identify one preferred alternative. In the final EIR, the Department identified the preferred alternative as a refined version of the original alternative 2, which provided for river restoration and reconfiguration of the golf course. In 2012, the Department certified the EIR and approved the preferred alternative.

Framing the issue as a question of law, the court found that the draft EIR did not “provide the public with an accurate, stable and finite description of the project,” because it did not identify a preferred alternative. The court found that by describing a range of possible projects, the Department had presented the public with “a moving target,” which required the public to comment on all of the alternatives rather than just one project. The court determined that this presented an undue burden on the public.

The court compared the draft EIR to County of Inyo v. City of Los Angeles (1977) 71 Cal.App.3d 185, where the court found an EIR insufficient because the project description described a much smaller project than was analyzed in other sections of the EIR. The court in Washoe Meadows found that rather than providing inconsistent descriptions like in County of Inyo, the draft EIR had not described a project at all. Thus, the court directed the Department to set aside the project approvals.

Fourth District Rejects Challenge to the City of Huntington Beach’s Housing Element, Applying Charter City Exemption

On October 31, 2017 in Kennedy Commission v. City of Huntington Beach  (2017) 16 Cal.App.5th 841, the Fourth Appellate District reversed the lower court,  finding for defendants on the first cause of action under state housing element, zoning, and planning laws. The court of appeal allowed plaintiffs leave to refile their third to sixth causes of actions, which had been dismissed without prejudice in the court below. A separate ruling on plaintiffs’ fee award from the court below is pending.

Background

The California Department of Housing and Community Development (HCD) determines each region’s Regional Housing Need Allocation (RHNA), including each region’s share of lower income housing. HCD then determines if the housing element of a general plan is compliant and reflects the agency’s share of the RHNA. HCD approved Huntington Beach’s general plan housing element in 2013. At the time, the majority of lower income housing was zoned for the Beach Edinger Corridor Specific Plan area (BECSP). Residents complained about the rapid pace of development in this area. In response, in 2015, the city amended the BECSP, cutting the amount of housing in this area by half. This resulted in a 350-unit shortfall of lower income housing for Huntington Beach. The city then sought to amend the housing element of the general plan to provide for lower-income housing in other areas of the city.

Plaintiffs, a fair housing advocacy organization and two lower-income Huntington Beach renters, filed a writ of mandate with six causes of action. The first cause of action was under state housing element law, for adopting a specific plan that was inconsistent with an approved general plan. The second cause of action was for failure to implement the general plan. The third and fourth causes of action were based on Article XI, section 7 of the California Constitution, alleging that the amended BECSP was preempted by state law. The fifth and sixth causes of action were allegations of housing discrimination, for adverse impacts to racial and ethnic minorities.

In an expedited trial, the trial court found that the amended BECSP violated state housing law because it no longer complied with the general plan (plaintiffs’ first cause of action). The trial court found that under Government Code section 65454, a municipality may not amend a specific plan unless the amendment is consistent with the general plan. The city, in violation of this provision, amended the specific plan without first amending the housing element to find other areas where lower income housing could be built. The BECSP amendment was void when passed and could not be enforced. The third through sixth causes of action were dismissed without prejudice. The second cause of action was not pursued on appeal.

Appellate Court Ruling

For the first time on appeal, the city raised the defense that as a charter city, Huntington Beach was exempt from requirements under Government Code sections 65860 and 65454, requiring that zoning ordinances and specific plans be consistent with the general plan. Charter cities with less than two million residents are exempt from these requirements, per Government Code 65803 (zoning) and 65700 (local planning). An exception to this exemption is when the charter city expressly states, in either its charter or by ordinance, that it intends to adopt the consistency requirement, which Huntington Beach alleged that it had not done. Therefore, the defendants argued, while they were required to provide for their share of lower income housing as determined by the RHNA, the city was permitted to amend the general plan to be compliant. To support this argument, the city moved for the appellate court to take judicial notice of the city’s charter and population, providing the factual basis for the city’s charter city exemption.

First, as a threshold matter, the court of appeal exercised its discretion to take judicial notice of documents that were not before the trial court, that are of substantial consequence in the determination of the action. The court chose to exercise its discretion here, because the trial court had not restricted the issues in its expedited hearing. Although this was not a justification for defendants’ failure to raise the issue, this decision afforded the defendants some latitude in this regard.

As to the merits, the court found that Huntington Beach met the requirements for the charter city exemption, and that the exception to this exemption was inapplicable. First, the court found that the consistency requirement was not adopted by the city in its charter. The court then examined Huntington Beach’s zoning ordinance concerning specific plans and determined that the city did not intend to adopt a consistency requirement there, either. In making this determination, the court heavily relied on its decision in Garat v. City of Riverside (1991) 2 Cal.App.4th 259. In Garat, Riverside, also a charter city, enacted two voter initiatives which changed the zoning to favor agricultural uses in specified areas, creating an inconsistency with the general plan.

In Garat, the court rejected the argument that the adoption of any specific plans, even if they were intended to be consistent with the general plan, creates either a presumption that all specific plans in the general plan area must also be consistent, or that a city has generally adopted the consistency requirement in its land use planning.

More importantly, Garat established that Government Code section 67000 exempts charter cities from local planning requirements, in virtually the same way that section 65803 exempts charter cities from the provisions requiring consistency with to specific plans, and these exemptions are strictly construed.

Turning to Huntington Beach’s zoning ordinance, the city did not explicitly state that any specific plan that was not consistent with the general plan was void. The ordinance did use language concerning consistency, but fell short of expressly adopting the language of Government Code section 65454. To adopt the consistency requirement, a zoning ordinance must state that “[n]o specific plan may be adopted or amended” unless it is consistent with the general plan, or else it is void. Absent this, plaintiffs’ attempt to imbue a consistency requirement in the zoning ordinance must fail, as it did in Garat.

The court also rejected plaintiffs’ argument that even if the charter city exemption applied, the amended BECSP should be considered void, as violating state law. Even if the court were to accept that the BECSP violated state law, the remedy would not be to render the BECSP void. Rather, the remedy would be to grant the city time to amend its housing element. The city is already implementing this remedy. The amendment process can proceed, while leaving the amended BECSP in force.

 The court noted while one may question the wisdom of creating the charter city exemption for certain aspects of land use planning, this was clearly the legislative intent.

The ruling is notable for several reasons. It set a high bar for plaintiffs in the Fourth District who are seeking to establish that a charter city has adopted specific plan consistency requirements, absent express adoption of the language of Government Code section 65454. Additionally, the city’s victory may be pyrrhic. As the city conceded, and the court concurred, the general plan’s housing element will ultimately require amendment to provide the city’s designated share of the RHNA. While the city achieved its goal of slowing down the pace of development, plaintiffs may yet refile and potentially prevail on their claims of housing discrimination, incurring liability for the city. Finally, although the court did decide to exercise its discretion and take judicial notice of the city’s charter, if it had not, the court would have had no basis for finding merit in the city’s defense under the charter city exemption. By not raising this defense in trial, the city came close to forfeiting this ultimately successful defense. Therefore, municipalities would do well to note if they are a charter city, and be prepared to argue that defense where applicable in the first instance.