Tag: EIR

FIRST DISTRICT REVERSES DECISION SETTING ASIDE TOWN OF TIBURON’S GENERAL PLAN UPDATE

In The Committee for Tiburon LLC v. Town of Tiburon (Cal. Ct. App., Feb. 2, 2026, No. A171983) 2026 WL 266411, the First District Court of Appeal reversed a trial court decision setting aside the Town of Tiburon’s general plan update and housing element. The court held that a program EIR for a general plan need not include site-specific environmental analysis for housing element sites where no development project has been proposed.

Key Takeaway

  • Identifying housing sites to meet RHNA obligations when no specific housing project has been proposed does not trigger a duty to analyze site-specific impacts in a program EIR.

Background

The Town adopted a general plan update that incorporated its 2023–2031 Housing Element, which identified the Town’s RHNA as 639 units and identified 17 sites for rezoning to accommodate 916 total units.

The Town prepared a program EIR that modeled a full buildout of the 17 sites. Rather than analyzing site-specific impacts, the EIR evaluated the townwide environmental effects of adding 916 housing units. The Town certified the EIR, adopted the general plan update, and later implemented rezonings through amendments to the municipal code.

The Committee for Tiburon LLC (“Committee”) challenged the EIR, asserting the Town violated CEQA by failing to analyze the site-specific impacts of rezoning Site H for very high-density residential use. The trial court granted the petition. The Town appealed.

Appellate Decision

The appellate court reversed, holding that the Town properly used a program EIR to analyze the broad environmental effects of increased housing under the general plan update, and that CEQA did not require site-specific analysis of Site H in the absence of a proposed development project.

The court rejected the Committee’s reliance on Vineyard Area Citizens for Responsible Growth, Inc. v. City of Rancho Cordova (2007) 40 Cal.4th 412 (Vineyard), distinguishing Vineyard as involving a concrete, multi-phase development project with foreseeable long-term impacts requiring project-specific analysis. The court observed that the Town’s identified housing sites were not phases of a single project but rather components of a planning document adopted to satisfy RHNA obligations, and there was no certainty that any particular site would be developed. The court emphasized that CEQA’s core purposes cannot be fulfilled without a concrete project, making deferral appropriate when no site-specific proposal exists.

The court also disagreed with the Committee’s argument that reports submitted to HCD during housing element review demonstrated the feasibility of a site-specific CEQA analysis of Site H. The court explained that while the reports described existing conditions, they did not analyze environmental impacts or mitigation measures associated with any proposed project and therefore did not support a requirement for a site-specific CEQA review.

Moreover, the court was not persuaded that deferring site-specific environmental review does not eliminate future CEQA review. Rather, the court explained that if development on Site H would result in impacts not addressed in the program EIR, CEQA would require additional project-level review tiered from that EIR.

Finally, the court remanded the matter to the trial court to determine whether rezoning of Site H is exempt under SB 131 for rezonings that implement actions contained in an approved housing element, and, if not, whether substantial evidence supports the Town’s determination that the EIR adequately analyzed the zoning amendments and that no supplemental or subsequent EIR is required.

Adam D. Nir

THIRD DISTRICT AFFIRMS EIR AND WATER SUPPLY ANALYSIS FOR GIOVANNONI LOGISTICS CENTER PROJECT

In City of Vallejo v. City of American Canyon (Cal. Ct. App., Jan. 14, 2026, No. C102070) 2026 WL 100754, the Third District Court of Appeal affirmed the denial of a CEQA and Water Code challenge to the City of American Canyon’s certification of an environmental impact report (EIR) for the Giovannioni Logistics Center.

This published decision represents a strong result for RMM client, Buzz Oates LLC, confirming that the project’s environmental review and water supply analysis were legally sound and allowing the Giovannioni Logistics Center to move forward. The outcome reflects the effective defense of the EIR by RMM attorneys James Moose and Christina Berglund.

Key Takeaways

  • Once incorporated into and certified with EIR, a water supply assessment is justiciable.
  • Lower historical water purchases do not make EIR speculative absent evidence of actual supply or deliverability constraints.

Background

The project involves developing a 2.4-million-square-foot warehouse complex on industrially zoned land in American Canyon. Once operational, the project is expected to require approximately 23.9 acre-feet per year of potable water—an amount the EIR characterized as modest relative to citywide demand. American Canyon relies primarily on the State Water Project, supplemented by water purchased from the City of Vallejo pursuant to a 1996 agreement. Vallejo also holds an appropriative water right under License 7848.

Vallejo challenged the EIR’s water supply assessment under CEQA and Water Code sections 10910 and 10911, arguing that the analysis overstated water availability and failed to address several asserted constraints. The trial court denied the petition. Vallejo appealed.

Appellate Decision

CEQA Claims

The Court of Appeal rejected each of Vallejo’s CEQA claims, emphasizing that CEQA requires a reasoned analysis of water availability—not certainty, perfection, or exhaustive detail.

  • Authorized vs. actual water purchases. Vallejo argued that the EIR was misleading because it relied on American Canyon’s contractual entitlement to purchase water rather than the lesser amount it historically purchased. The court disagreed, explaining that the record contained no evidence showing that the difference reflected supply constraints, rather than economic decisions by American Canyon. Critically, the court noted that the EIR properly relied on American Canyon’s urban water management plan, which explained that while Vallejo treated water is a reliable source, American Canyon typically purchases less than its full contractual allotment because of its higher costs, not because the water is unavailable.
  • Place of use restrictions. Vallejo also contended the EIR was deficient for failing to discuss place-of-use restrictions associated with License 7848 water. The court acknowledged that such restrictions could, in a narrow sense, affect where the water may be used, but emphasized that they did not reduce the overall volume of water available to the citywide system. Even assuming disclosure might have been appropriate, the court held Vallejo failed to show prejudice—because the EIR evaluated water supply and demand on a citywide basis and substantial evidence supported its conclusion that supplies were sufficient under all modeled scenarios.
  • Curtailment analysis. Vallejo argued the EIR should have analyzed water availability on a monthly basis and addressed the risk of “simultaneous curtailment” affecting multiple imported sources. The court rejected both arguments. CEQA Guidelines section 15155 requires consideration of drought and curtailment risks but does not mandate monthly projections. The court also found the EIR adequately disclosed that American Canyon’s imported supplies share common infrastructure and hydrologic constraints and described contingency planning for dry years.
  • Alternative water sources. Vallejo’s argument that the EIR was required to analyze alternative water sources failed for two reasons. First, the issue was not preserved in the trial court. Second, an alternative analysis is required only when a lead agency cannot determine that sufficient water will be available—a finding American Canyon never made.
  • Related contract litigation. Finally, Vallejo argued the EIR should have disclosed separate litigation over the 1996 agreement. The court declined to find error, noting that the record contained no information about the litigation’s substance or potential effect on water availability. Without such evidence, Vallejo could not demonstrate that the omission was material or prejudicial.

Water Code Claims

The court also rejected Vallejo’s claims under Water Code sections 10910 and 10911. Although water supply assessments are often treated as preliminary informational documents, the court held Vallejo’s claims were justiciable because the assessment had been incorporated into and certified in the EIR.

On the merits, the court concluded the assessment adequately identified relevant water supply contracts and relied on American Canyon’s urban water management plan to describe historical deliveries. The Water Code does not require the level of detail Vallejo sought, nor does it require a contingency plan unless the agency determines supplies will be insufficient—which American Canyon did not.

Adam Nir

California Supreme Court Holds that CEQA is Not Preempted by the Federal Power Act When Used to Make Decisions that are Outside Federal Jurisdiction or Compatible with the Federal Government’s Licensing Authority

In County of Butte v. Department of Water Resources (2022) 13 Cal.5th 612, the California Supreme Court partially reversed an opinion from the Third District Court of Appeal that CEQA is completely preempted by the Federal Power Act (FPA), finding instead that CEQA is only partly preempted. Specifically, the Supreme Court held the FPA preempts an agency’s application of CEQA to the extent that it interferes with the federally established licensing process, but not when CEQA is used to make decisions concerning matters outside federal jurisdiction or those compatible with the federal government’s exclusive licensing authority.

Background

This consolidated litigation addresses a license renewal for the Oroville Facilities, a collection of public works projects, including hydroelectric facilities, in Butte County. As part of the renewal process, the California Department of Water Resources (DWR) engaged the alternative licensing process (ALP) authorized by the Federal Energy Regulatory Commission (FERC) prior to applying for relicensing. The ALP process allowed DWR to engage with stakeholders and develop a settlement agreement addressing their concerns, which effectively functions as a first draft of the FERC license. Following five years of negotiations, all but two of the stakeholders signed on to the settlement agreement, which DWR submitted to FERC. The Counties of Butte and Plumas did not sign the agreement. Following submission of the settlement agreement and licensing application by DWR, FERC prepared an Environmental Impact Statement (EIS) pursuant to NEPA, which considered several alternatives, including a “staff alternative” with modifications from the FERC staff. The EIS concluded the “staff alternative” was the preferred alternative.

Also following submittal of the relicensing application, DWR prepared an EIR pursuant to CEQA, analyzing implementation of the settlement agreement and continued operation of the Oroville Facilities as the “project” under CEQA and the same alternatives considered by FERC. DWR prepared the EIR to comply with additional permitting requirements under the Clean Water Act, for which the State Water Resources Control Board was the lead agency, and to help DWR determine whether to accept a license containing the original terms or the “staff alternative.”

Procedural History

Butte County and Plumas County separately filed petitions for writ of mandate, each challenging DWR’s compliance with CEQA in connection with the relicensing of Oroville Facilities. The cases were later consolidated.

The trial court found DWR’s EIR adequate, and the Counties appealed. On appeal, the Third District declined to reach the merits of the case, holding that the Counties’ CEQA claims were entirely preempted by the FPA, the purpose of which is to “facilitate the development of the nation’s hydropower resources” by centralizing regulatory authority over dams, reservoirs, and hydroelectric power plants in the federal government. The California Supreme Court granted the Counties’ petition for review but subsequently transferred the matter back to the Court of Appeal for reconsideration in light of Friends of the Eel River v. North Coast Railroad Authority (2017) 3 Cal.5th 677 (Friends), which held that the Interstate Commerce Commission Termination Act (ICCTA) does not necessarily preempt a State agency’ compliance with CEQA for a new railroad project, and that State, as a railroad operator, could voluntarily subject itself to compliance with CEQA without conflicting with the ICCTA. On remand, the Third District affirmed its earlier holding that CEQA was preempted by the FPA.

The California Supreme Court again granted the Counties’ petition for review to determine whether the FPA preempts CEQA when the state is acting on its own behalf and exercising discretion in relicensing a hydroelectric dam.

The California Supreme Court’s Decision on Preemption

A five justice majority of the California Supreme Court held that CEQA claims are preempted insofar as they conflict with the FPA’s licensing scheme, but not where CEQA is used to make decisions concerning matters outside federal jurisdiction or those compatible with the federal government’s exclusive licensing authority. Specifically, the court determined that any CEQA challenge to the ALP and the terms of the settlement agreement and license being considered by FERC were preempted by the FPA. However, because DWR’s compliance with CEQA was not limited to the FERC relicensing, the Counties’ broader challenges to the adequacy of DWR’s EIR were not preempted. The Court concluded that DWR could use the environmental conclusions reached through the CEQA process to aid its decision whether to accept FERC’s “staff alternative” or request modification to the terms of the license issued by FERC, which the FPA allows.

The Court discussed the federal and state law principles applicable to the case before it, including the presumption against preemption for a state-owned, or state-operated project. The FPA does not include an “express” preemption clause, so the issue was whether “conflict” or “field” preemption applied. The Court concluded that the distinction between the two types of preemption was not meaningful here, particularly considering the presumption that, absent a clear statement of Congressional intent that state regulation is preempted, federal law will not be interpreted as interfering with state-owned or state-operated projects. The Court also found federal caselaw applying “field” preemption to state regulatory schemes related to the FPA distinguishable because those cases addressed state attempts to regulate private actors seeking licensing under the FPA. The Court stated that CEQA, in the context of a state agency applying for a federal license, constitutes “self-governance” rather than traditional state regulation of private actors that has been held preempted in the past.

The Court acknowledged that state courts could not require a CEQA remedy inconsistent with federal law, including the FPA, but noted that the Counties had dropped their previous request to enjoin FERC’s licensing process pending DWR’s compliance with CEQA. The Court reasoned, however, that DWR’s compliance with both CEQA and the FPA was possible without creating any conflict. Specifically, DWR used CEQA analysis, in part, to determine whether it should accept a license from FERC containing the proposed terms or those modified by FERC staff. Similarly, the FPA allows applicants to amend their licensing applications or request that FERC modify the terms of the license. DWR could thus use the environmental conclusions reached in the CEQA process to make its own decisions and then make appropriate requests to FERC without intruding on FERC’s jurisdiction. Just as FERC was not required to issue a license wholly consistent with the terms of the settlement agreement, FERC retained jurisdiction to consider, but in no way be bound by, any subsequent requests from DWR. For these reason, environmental review at both levels of government did not overlap to invoke conflict preemption.

The Court also concluded that any preemption issues related to DWR’s adoption of specific mitigation measures demanded by the Counties were premature, as no court had ruled that any additional mitigation was required. The question before the Court was whether any CEQA challenge to DWR’s EIR was preempted by the FPA, the Court ruled such a challenge, in the abstract, was not inherently preempted. Additionally, the Court noted that it may be possible for DWR to adopt mitigation measures that are either outside of FERC’s jurisdiction or compatible with FERC’s licensing authority. Again, FERC could simply deny any request from DWR that conflicted with the FPA or FERC’s licensing authority.

In sum, where the Counties’ CEQA challenges seek to undermine a FERC license or associated terms, they are preempted by the federal government’s exclusive licensing authority under the FPA. However, Counties’ CEQA claims which implicate the sufficiency of an EIR to inform state self-governance and decision-making are not preempted.

The Concurring and Dissenting Opinion

Notably, the Chief Justice, and author of the Friends decision, filed a concurring and dissenting opinion. The Chief Justice agreed that any CEQA challenge to FERC’s licensing process including the settlement agreement was preempted but disagreed that broader CEQA challenges were not similarly preempted. The dissent reasoned that, in addition to “field” and “conflict” preemption, state law that constitutes an “obstacle” to the purposes and objectives of federal law would be similarly preempted. Here, given the history of federal caselaw concluding that state regulation of hydroelectric facilities is preempted by the FPA, and the express “savings clause” in the FPA reserving regulation of water rights to the states, the Chief Justice concluded that CEQA is an “obstacle” to the objectives and purpose of the FPA, particularly where the FPA licensing process included multiple equivalents of CEQA through the ALP and FERC’s compliance with NEPA and does not contemplate delays caused by state court review of CEQA compliance.

The dissent also concluded that CEQA was subject to “field” preemption because CEQA did not involve state regulation of water rights. The Chief Justice also noted that, while none of the federal FPA preemption cases addressed state-operated projects, the concept of “field” preemption (i.e., where Congress truly intends to “occupy the field”) is broad enough to preempt all state regulation, regardless of who the operator is.

Turning to Friends, the Chief Justice characterized her decision in that case as concluding that CEQA is exempt from preemption under the ICCTA as an example of “self-governance” by the State. Given the purpose of the ICCTA was to deregulate railroads, and thereby allow greater “self-governance” by railroad operators, the State’s voluntary compliance with CEQA was not preempted. In contrast, the dissent concluded that the FPA’s purpose and objectives is to vest exclusive regulation of hydroelectric facilities in FERC and to exclude all state regulation, with the exception of water rights. The Chief Justice concluded that, unlike the ICCTA, the FPA (including the federal caselaw interpreting the FPA) made it “unmistakably clear” that all state regulation of hydroelectricity facilities, except regulation of water rights, is preempted.

Lastly, the dissent concluded that finding CEQA only partially preempted was unworkable because a ruling that DWR’s CEQA compliance deficient would not impact FERC’s decision on whether to issue the license. Forcing DWR to perform additional analysis or consider additional mitigation or alternatives would be an exercise in generating paper, without any practical effect. As the Majority Opinion acknowledges, FERC has complete discretion to deny any request to alter the terms of the license, regardless of whether DWR believes such changes to be necessary to comply with CEQA. The dissent also found that requiring CEQA compliance in this case, where multiple environmental studies have been prepared for FERC’s consideration during the licensing process, would be redundant and have little practical benefit.

By Jordan Wright and Nathan George

SECOND DISTRICT FINDS QUANTIFICATION OF EXISTING WATER RIGHTS NOT REQUIRED UNDER CEQA FOR WATER DIVERSION AND STORAGE PROJECT

On March 3, 2022, the Second District Court of Appeal ordered published its decision in Buena Vista Water Storage District v. Kern Water Bank Authority (2022) 76 Cal.App.5th 576, in which the court held that an EIR for a project to divert and store unappropriated flood flows need not quantify all existing water rights. The court also held that CEQA does not require the project description to specify the exact amount of water that would be diverted, since that amount will vary from year to year based on the weather. Additionally, the court held that substantial evidence supported the EIR’s conclusion that the project would not adversely affect the long-term recovery of the groundwater basin in which it is located, as the project would cause a net benefit to the aquifer.

Factual & Procedural Background

Although the Kern River had been designated a fully appropriated stream for many years—such that only those who held an appropriative right could divert from it—in 2010, the State Water Resources Control Board (SWRCB) found that in certain wet years, Kern River water was available in excess of the amount appropriated. In particular, following construction of the Kern River-California Aqueduct Intertie in 1977, the Kern River water master began occasionally releasing reservoir water into the intertie to alleviate flooding. This release only occurs when flows are in excess of those held by existing water rights holders. The SWRCB concluded that this flood-released water was unappropriated and stated that it would allow applications to appropriate that water.

Respondent, the Kern Water Bank Authority, thereafter filed an application with the SWRCB seeking a permit for a water right to divert and store up to 500,000 acre-feet-per-year of the unappropriated water. The Authority also certified an EIR for the project. Buena Vista Water Storage District filed a petition for writ of mandate, seeking to set aside the Authority’s certification of the EIR and its approval of the project.

The trial court granted Buena Vista Water Storage District’s writ petition, holding: (1) the EIR’s project description was inadequate because it did not quantify existing water rights and it was unstable; (2) the EIR’s discussion of the existing baseline was inadequate because it did not quantify competing existing rights to Kern River water; and (3) the EIR’s impact analysis was inadequate because it did not adequately assess impacts on senior rights holders and impacts on groundwater during long-term recovery operations. The Court of Appeal reversed, concluding that the EIR complied with CEQA.

The Court of Appeal’s Opinion

The EIR’s Project Description is Accurate and Stable

Unlike the trial court, the Second District Court of Appeal held that the EIR’s project description is adequate under CEQA. As explained by the court, the EIR consistently and adequately describes the project as “‘high flow Kern River water, only available under certain hydrologic conditions and after the rights of senior Kern River water right holders have been met, that otherwise would have (1) been diverted to the Intertie, (2) flooded farmlands, or (3) left Kern County.’”

Buena Vista Water Storage District argued that the EIR’s project description is unstable because it relies on an “open-ended limit of ‘up to 500,000 [acre-feet] of water.” The court rejected this argument, explaining that a precise amount of water to be diverted by the project cannot be determined because water availability will fluctuate from year to year. As stated by the court: “A project description may use a flexible parameter when subject to future changing conditions.” Furthermore, the proposed 500,000 acre-foot-per-year is a finite maximum amount based on historical conditions, thus providing an adequate upper-end of the proposed diversion.

EIR Not Required to Quantify Existing Water Rights

The appellate court also rejected the District’s contention that the EIR’s project description must include a quantification of existing Kern River rights. That amount of detail is not necessary under CEQA Guidelines section 15124, subdivision (c), which requires a “general description” of the project’s technical and environmental characteristics. Moreover, a stream-wide quantification is a complex proceeding conducted by the SWRCB or a court and can take several years (or even decades) to complete. CEQA does not require this type of exhaustive detail.

Similarly, the EIR’s description of the existing environmental setting is not required to include a quantification of the existing Kern River water rights. The EIR satisfies CEQA’s informational requirements by providing measurements of Kern River water historically diverted into the Kern Water Basin and estimating, based on these historic records, how much water the Kern River Bank Authority could have diverted from the basin under baseline conditions. A complete quantification of existing water rights was not necessary to provide these estimates.

Finally, the court found it was clear that existing rights would not be impacted because the SWRCB cannot issue a new permit to divert water that is already subject to existing water rights. Further, the SWRCB expressly allowed processing of water rights applications, like the one at issue, in its Order finding that the water diverted to the Intertie was not fully appropriated. Quantification of the existing water rights was not necessary to evaluate the project’s impacts.

Substantial Evidence Supports the EIR’s Conclusions Regarding Groundwater Impacts

According to the trial court, the project would alter groundwater recovery by making groundwater available for long-term pumping for additional months or years during drought conditions, which, in the trial court’s view, would likely deplete groundwater during a drought. The Second District rejected the lower court’s analysis as factually inaccurate. The purpose of the project is to add to groundwater supplies and increase the availability of groundwater storage. The EIR concludes that the project would raise the local groundwater, resulting in a net increase in aquifer volume. Additionally, the Kern Water Bank Authority’s existing groundwater and monitoring policies will ensure that banking additional groundwater will not lower groundwater tables or affect the production rate of existing wells. Thus, substantial evidence supports the EIR’s conclusion that the project’s groundwater impacts will not be significant.

Conclusions & Implications

The Second District’s decision addresses whether an EIR for a water diversion and storage project must quantify the existing water rights to the underlying waterbody. In holding that such quantification is not required for the Kern Water Bank Authority’s proposed water diversion project, the Court of Appeal adhered to the principle that CEQA does not require an exhaustive analysis, but rather a good faith and reasonable effort at full disclosure. The decision also recognizes that for certain types of projects, particularly those involving water supplies, a project description must be somewhat flexible. The decision illustrates how a court reviewing an EIR must defer to the lead agency’s factual analyses and conclusions—deference that the trial court had failed to give to the Kern Water Bank Authority’s determinations.

– Laura Harris Middleton

THIRD DISTRICT PARTIALLY AFFIRMS JUDGMENTS SETTING ASIDE EIR FOR SPECIFIC PLAN LAND SWAP IN EASTERN PLACER COUNTY

In a 123-page decision, League to Save Lake Tahoe Mountain Area Preservation Foundation v. County of Placer (2022) 75 Cal.App.5th 63, the Third District partially affirmed the trial court’s judgment in two cases granting a petition for writ of mandate, finding that the EIR for the Martis Valley West Parcel Specific Plan (Project) failed to adequately describe the environmental setting of Lake Tahoe regarding water quality, failed to adequately analyze impacts to Lake Tahoe water quality resulting from automobile trips, impermissibly deferred the formulation of mitigation for GHG impacts, failed to analyze proposed mitigation for the Project’s significant and unavoidable traffic impacts on SR 267, and failed to analyze whether renewable energy features could be incorporated into the Project. The Court of Appeal upheld the EIR’s analysis of impacts to forest resources and air quality, including the County’s reliance on the Placer County Air Pollution Control District’s (PCAPCD) thresholds of significance. The court also upheld the County’s decision not to recirculate the Draft EIR and to immediately rezone the subject property out of Timberland Productivity Zone (TPZ). Lastly, the Court of Appeal reversed the trial court’s decision that the EIR did not adequately analyze emergency evacuation impacts.

Background

Real Party in Interest, Sierra Pacific Industries (SPI), owns two undeveloped parcels on either side of SR 267, between Truckee and Lake Tahoe. The West Parcel is southeast of the Northstar Resort and has 1,052 acres. The East Parcel has 6,376 acres.  The existing zoning and land use designation in the Martis Valley Community Plan (MVCP) allows up to 1,360 residential units and 6.6 acres of commercial uses in a 670-acre area of the larger east parcel. Otherwise, both parcels are zoned TPZ and designated as forest in the MVCP. Starting in 2013, SPI and its partners (collectively, Real Parties in Interest or RPI) proposed that the County adopt a specific plan for the two parcels that would amend the MVCP and zoning to move the residential and commercial uses from the East Parcel to the West Parcel, reduce the residential capacity from 1,360 units to 760 units, immediately rezone 662 acres on the West Parcel out of TPZ, and rezone the entire East Parcel as TPZ. Following adoption of the specific plan, the applicants would sell the East Parcel for conservation purposes or place the land in a conservation easement. The effect of the land swap would be to allow development on the West Parcel, adjacent to Northstar and existing residential development, while permanently conserving all 6,376 acres of the East Parcel, connecting some 50,000 acres of open space east of SR 267. Two small areas of both parcels are within the Lake Tahoe Basin, and thus subject to the jurisdiction of the Tahoe Regional Planning Agency (TRPA), but neither area would be included in the specific plan.

The County circulated a draft EIR for the Project in 2015. In 2016, the County certified the final EIR, immediately rezoned the 662-acre project area of the West Parcel out of TPZ, rezoned the East Parcel to TPZ, and adopted the specific plan.

Sierra Watch, Mountain Area Preservation, and the League to Save Lake Tahoe (collectively, Sierra Watch) filed a lawsuit challenging the EIR and the County’s finding that immediately rezoning the project area on the West Parcel was consistent with the purposes of the Timberland Productivity Act (TPA). The California Clean Energy Committee (CCEC) filed a separate petition, also challenging the EIR. The trial court issued judgments in April and June 2018, rejecting all the challenges to the EIR, with the exception of the EIR’s analysis of impacts to emergency evacuations, and upholding the County’s findings on the immediate rezone out of TPZ. Sierra Watch and CCEC filed separate appeals, and the County and RPI cross-appealed on the emergency evacuation issue.

Court of Appeal’s Decision

On appeal, Sierra Watch argued that the EIR failed to adequately describe the Lake Tahoe Basin’s existing air and water quality, that the County should have adopted the TRPA’s threshold of significance for vehicle miles traveled (VMT) with respect to basin air and water quality, and that the EIR failed to adequately analyze the impacts of project traffic on air and water quality in the basin. Sierra Watch also challenged the County’s decision not to recirculate the EIR following changes to the analysis of GHG impacts, and argued that the adopted GHG mitigation measure was invalid. Lastly, Sierra Watch argued that the County violated the TPA by failing to make required findings. In their cross-appeal, the County and RPI argued that the EIR’s analysis of impacts to emergency evacuations was adequate, and that substantial evidence supported the EIR’s conclusion that the impacts would be less than significant.

CCEC’s appeal argued that the EIR did not adequately describe existing forest resources or analyze cumulative impacts to forest resources, failed to analyze feasible traffic mitigation measures proposed in comments, failed to disclose significant impacts from widening SR 267, and failed to discuss the use of renewable energy sources to meet Project energy demand. CCEC also argued that the adopted GHG mitigation measure was infeasible and unenforceable.

Lake Tahoe

The Court of Appeal found the County was not legally required to use TRPA’s thresholds of significance for measuring the Project’s impacts because, although the two parcels did include land within TRPA’s jurisdiction, the Project was revised to not include those areas. Instead, the County, as the lead agency, had discretion to rely on TRPA’s thresholds or those of another agency, or use their own thresholds, including thresholds unique to the Project. The court also concluded that, while TRPA had “jurisdiction by law” over resources that could be affected by the Project, and was thus, a “Trustee agency” under CEQA, they were not a “Responsible agency” because they had no permitting authority over the Project.
The court also found that the County did not abuse its discretion in adopting the PCAPCD’s thresholds of significance for the project’s air emissions impacts because, contrary to Sierra Watch’s claims, the PCAPCD’s significance thresholds were adopted to address air and water quality (resulting from air emissions) within the Tahoe Basin. However, the EIR failed to adequately describe the existing water quality of Lake Tahoe, which could be impacted by “crushed abrasives and sediment” from project traffic within the basin. According top the court, the EIR did not include a threshold of significance (though several were discussed in post-EIR responses to comments) for such impacts, even though there was substantial evidence that the project-generated traffic would travel within the basin, which the court found to be an abuse of discretion.

Recirculation

Sierra Watch argued that the revisions to the draft EIR’s GHG analysis included in the Final EIR triggered the need to recirculate. The draft EIR included a tiered analysis of GHG impacts. First, annual Project GHG emissions were calculated and compared to PCAPCD’s numeric threshold of 1,100 MTC2E for residential development. Second, although the draft EIR acknowledged that little, if any, of the Project would be constructed by 2020, the EIR compared a completed Project in 2020 with the GHG reduction measures, including those required by law, in place with a “no action” or “business as usual” scenario to determine the Project’s GHG efficiency, pursuant to the California Air Resources Board’s revised Scoping Plan. The draft EIR concluded that, because the Project would generate GHG emissions substantially greater than the numeric threshold, and because it was uncertain what regulatory GHG measures would be in place after 2020, when the Project was likely to begin operating, the impact was significant and unavoidable.

Before the final EIR was published, however, the California Supreme Court issued its decision in Center for Biological Diversity v. California Department of Fish and Wildlife (2015) 62 Cal.4th 204 (Newhall Ranch). Newhall Ranch ruled that an efficiency metric comparing a proposed project to a hypothetical “business as usual” scenario was a permissible way to analyze GHG impacts, but the Scoping Plan’s statewide efficiency threshold required additional evidence and analysis to apply to individual projects, and the EIR in that case did not include the required connection. In response to Newhall Ranch, the final EIR dropped the efficiency analysis, but affirmed the draft EIR’s conclusion that impacts would be significant and unavoidable because the Project would generate emissions exceeding the numeric threshold, and because of the uncertainty around future regulatory GHG reduction measures. The County concluded that, because the significance conclusion did not change, recirculation was not required. The Court agreed recirculation was not required because the final EIR did not show new or substantially more significant effects, and merely clarified or amplified the information provided in the draft EIR.

GHG Mitigation

The court agreed with the appellants that the GHG mitigation measure impermissibly deferred determining the significance of GHG impacts, because the measure required future tentative maps to establish consistency with future efficiency targets adopted in compliance with the Newhall Ranch decision, even though the EIR acknowledged that no such targets existed and may not ever exist. The measure provided a suite of proposed mitigation tools that future maps could use to meet the efficiency targets. The court reasoned that, if no efficiency target consistent with Newhall Ranch became available, mitigation would never be triggered. RPI and the County argued that, if no efficiency targets were available, the 1,100 MTC2E threshold would apply to future maps, but the court found that the language of the measure itself did not include the numeric threshold.

Emergency Evacuations

The court agreed with the County and RPI that the EIR’s analysis of impacts to emergency evacuation plans was adequate and the EIR’s conclusion that impacts would be less than significant was supported by substantial evidence. The court upheld the EIR’s reliance on the questions in Appendix G to the CEQA Guidelines to set a threshold of significance. The EIR acknowledged that adding people and development to the area could exacerbate cumulative impacts to evacuation but concluded that the impact was less than significant because the project would not cut off or modify any evacuation routes and would not prevent an evacuation from occurring or otherwise interfere with the implementation of the County’s evacuation plans. The court found that the conclusion was supported by substantial evidence, including the EIR’s analysis of how long it would take to evacuate the project site, the number of emergency access/evacuation roads included in the project, the requirement that RPI develop a “shelter in place” feature, and the analysis of impacts to fire department response times.

The court acknowledged that evacuation planning involved multiple unknown factors and a host of potential circumstances which made it difficult to predict how an evacuation might play out or how a project could impact such an evacuation. The court reasoned that because the County had discretion as the lead agency to decide how to analyze an impact, the court would defer to the County’s methodology decision provided it was reasonable and supported by substantial evidence. The court found that it was. The court concluded that many of Sierra Watch’s challenges to the EIR’s analysis amounted to requests for further analysis, additional modeling, and speculative hypothetical scenarios. The court cited Guidelines sections 15145 and 15151 for the propositions that the EIR need not speculate and need not be exhaustive. While some of the evidence, relating to fire prevention and fire department response times, did not directly relate to emergency evacuation planning, the evidence indirectly supported the County’s conclusions by demonstrating that the project was reducing the likelihood of wildfire on the site and reducing the need for an evacuation.

Sierra Watch also argued that the EIR was internally inconsistent because the traffic analysis reached the opposite conclusion of the emergency evacuation analysis regarding project traffic on SR 267. The court found that the EIR’s conclusion that project generated traffic would have a significant impact on vehicle delay was not inconsistent with the conclusion that project generated traffic would not substantially interfere with emergency evacuation plans. The court reasoned that the two analyses focused on different types of impacts, with time (as measured by vehicle delay) being the focus of the traffic analysis and public safety being the focus of the emergency evacuation analysis.

Forest Resources

The court upheld the EIR’s conclusions that cumulative impacts to forest resources were less than significant. The EIR discussed the County’s 1994 General Plan EIR’s analysis of impacts to forest resources based on projected growth and development in the County and concluded that the Project’s impacts were consistent with and would not exceed the impacts disclosed in 1994 General Plan EIR. The Final EIR concluded that analyzing climate-related forest impacts, such as drought, wildfire, and tree mortality cause by bark beetles, would be speculative, and the court agreed. The court concluded that climate-driven tree mortality was not within the scope of a CEQA cumulative impacts analysis, which required the County to analyze impacts from the Project combined with past, present, and reasonably foreseeable future projects. Tree mortality is not a “project” under CEQA. The court acknowledged that climate-caused tree mortality could be exacerbated by a project, but such impacts would be best analyzed as part of the climate change and GHG analysis. The court concluded that aspect of the GHG analysis was not challenged in this case.

Traffic Mitigation

The EIR concluded that the Project’s traffic impacts on SR 267, measured in terms of delay and using the level of service (LOS) metric, would be significant and unavoidable. The EIR reached this conclusion in part because while the California Department of Transportation had plans to widen SR 267 from two to four lanes, the plan did not cover the portion of SR 267 within the Tahoe Basin, and it was uncertain when the widening would occur. Several commenters suggested that the EIR analyze transportation demand management (TDM) options to reduce traffic on SR 267. The EIR included similar measures for the Project’s impact on public transit but did not analyze whether TDM measures could further reduce the significant traffic impacts. The court, without acknowledging previous rulings by the Third District Court of Appeal finding LOS impacts to be moot given the Legislature’s directive that vehicle delay is not a significant environmental impact, ruled that the EIR failed to analyze facially feasible mitigation proposed in comments and therefore violated CEQA. The Court also found that, while the EIR did not analyze the impacts of widening SR 267, that lack of analysis was not prejudicial error because widening SR 267 was previously approved by the County in the MVCP, which concluded at the time that impacts of such a project would be analyzed in a separate EIR once the improvements were designed.

Energy Resources

Lastly, the court found fault in the EIR’s analysis of impacts to energy resources. The EIR concluded that the Project’s energy consumption impacts would be less than significant because the Project would not result in “wasteful, inefficient, or unnecessary use of energy, or wasteful use of energy resources.” The court, however, ruled that the EIR was required to analyze the Project’s potential use of renewable energy both in determining whether the Project may have a significant impact and how to mitigate that impact. Citing California Clean Energy Com. v. City of Woodland (2014) 225 Cal.App.4th 173, 209, the court concluded that the requirement to analyze renewable energy as part of a project’s impact analysis was a procedural requirement of CEQA, which the EIR failed to comply with.

– Nathan George

*RMM Attorneys Whit Manley, Chip Wilkins, and Nate George served as counsel to Real Parties in Interest in the above litigation.

FOURTH DISTRICT UPHOLDS EIR FOR MULTI-FAMILY HOUSING PROJECT AND FINDS CITY PROPERLY USED A PLANNED DEVELOPMENT PERMIT TO ALLOW A VARIATION FROM CONVENTIONAL ZONING REGULATIONS

In Ocean Street Extension Neighborhood Association v. City of Santa Cruz (2022) 73 Cal.App.5th 985, the Fourth District Court of Appeal held that an EIR for a multi-family housing project properly relied on the biological resources analysis and mitigation measures identified in the initial study for the project, and sufficiently addressed the project objectives, alternatives, and cumulative impacts to water supply and traffic. Reversing the trial court, the Court of Appeal also held that the City complied with its municipal code by using a planned development permit as a variation from its conventional slope regulations.

Background

The proposed project consisted of a 40-unit residential complex on a vacant lot in the City of Santa Cruz. The City prepared an initial study that discussed, among other topics, biological impacts that would be reduced to less-than-significant with mitigation, and later circulated a draft EIR and recirculated draft EIR before certifying the final EIR. The City Council approved a reduced-housing alternative with 32 units.

Along with a general plan amendment, rezone, and other entitlements, the City approved a planned development permit (PDP) to allow a variation from the conventional slope regulations in the City’s zoning code.

The Ocean Street Extension Neighborhood Association (OSENA) filed a petition for writ of mandate challenging the EIR and the City’s approval of the PDP. The trial court ruled that the City complied with CEQA, but found the City violated its municipal code by not requiring compliance with the conventional slope regulations. OSENA appealed and the City and Real Parties in Interest cross-appealed.

The Court of Appeal’s Decision

CEQA and Adequacy of the EIR

Upholding the trail court’s ruling on the CEQA claims, the Court of Appeal concluded that the EIR was adequate. The court held that impacts that are less than significant with mitigation may be discussed in an initial study rather than in the EIR as long as the EIR fulfills its purpose as an informational document. The court noted that the EIR summarized the impacts and mitigation measures, and the EIR’s reference to the initial study—which was attached to the EIR as appendix—sufficiently alerted the public to the environmental issues and provided readers with adequate information. Accordingly, the court determined that it was appropriate for the EIR to rely on the biological resources analysis and mitigation measures identified in the initial study.

The court also rejected OSENA’s argument that the mitigation measures were vague and improperly deferred because OSENA failed to exhaust its administrative remedies as to this issue and did not raise it in the trial court proceedings. The court nonetheless explained that even if it considered this issue on the merits, it would reject OSENA’s arguments because the question of effectiveness of a mitigation measure is a factual one, which, in this case, was supported by substantial evidence in the record.

The court further concluded that the project’s objectives and alternatives analyses were adequate, and that OSENA’s arguments amounted to mere disagreement with the City’s conclusions. The court explained that rejecting or approving an alternative is a decision only for the decisionmakers, and they may reject alternatives that are undesirable for policy reasons or fail to meet project objectives. While the project objectives included specific targets, those objectives did not improperly restrict the range of alternatives analyzed in the EIR, and the City justified its reasons for rejecting alternatives with even less housing than the 32-unit alternative.

Additionally, the court determined that the EIR sufficiently analyzed the project’s cumulative impacts on water supply and traffic. Regarding water supply, the court explained that the EIR’s analysis properly considered the water supply impact in light of city-wide needs and future demand, and properly relied on the City’s Urban Water Management Plan. Regarding traffic, the court held that OSENA’s arguments challenging the EIR’s analysis of LOS impacts were moot because CEQA Guidelines section 15064.3, which took effect after the case was initiated, provides that a project’s effects on automobile delay shall not constitute a significant environmental impact.

Therefore, the Court affirmed the portion of the trial court’s order and judgment concluding that the City complied with CEQA.

Santa Cruz Municipal Code

Reversing the trial court’s ruling on OSENA’s municipal code claims, the Court of Appeal held that the City did not violate its municipal code by granting a PDP without also requiring compliance with the conventional slope modification regulation procedures in its zoning code. The City’s PDP ordinance allows a variation from certain zoning regulations including “Slope Regulations Modifications, pursuant to procedures set forth in Chapter 24.08, Part 9 (Slope Regulations Modifications).” Rejecting OSENA’s claim that the City was required to comply with the conventional regulations in Chapter 24.08, Part 9, in addition to the requirements for a PDP, the court explained that the City should be afforded deference in the interpretation of its own municipal code. The court upheld the City’s determination that the granting of a PDP does not require compliance with the conventional slope regulations, as this interpretation was consistent with the text and purpose of the ordinance and interpreting the PDP ordinance as requiring compliance with both the PDP ordinance and the slope regulations would have served no readily apparent purpose.

RMM Partners Christopher L. Stiles and Tiffany K. Wright represented the Real Parties in Interest in this case.  Chris Stiles argued the case in Court of Appeal on behalf of the City and Real Parties.

-Veronika S. Morrison

SIXTH DISTRICT HOLDS COASTAL COMMISSION VIOLATED CEQA BY FAILING TO COMPLETE ENVIRONMENTAL REVIEW OF COASTAL DEVELOPMENT PERMIT PRIOR TO PROJECT APPROVAL

In Friends, Artists, and Neighbors of Elkhorn Slough v. California Coastal Commission (2021) 72 Cal.App.5th 666, the Sixth District Court of Appeal held that the California Coastal Commission (CCC) violated CEQA by analyzing a coastal development permit’s environmental impacts and adopting findings in support thereof after it had approved the permit and underlying project. Although the CCC is authorized to issue “revised findings” when the Commission’s action differs from what was proposed in the staff report, the court held that the revised findings in this case went too far and were an improper pot-hoc rationalization.

Background

In 2000, Real Party in Interest Heritage/Western Communities, Ltd., applied to the County of Monterey for a combined development permit and coastal development permit (CDP) for the Rancho Los robles Subdivision. The project proposed more than 100 residential units on a commercial parcel. Monterey County prepared an EIR containing several alternatives, including one with a reduced number of units.

In 2008, the County Planning Commission recommended denying the project due to water supply and traffic congestion issues. Heritage/Western appealed the denial to the County Board of Supervisors. The Board disagreed with the Planning Commission and approved the project. The Board also certified the EIR and adopted a statement of overriding considerations regarding significant and avoidable impacts to traffic, groundwater, and seawater intrusion.

In 2009, Friends, Artists, and Neighbors of Elkhorn Slough (FANS) appealed the Board’s decision to the CCC, alongside two Coastal Commissioners. CCC staff issued a staff report recommending denial of the CDP primarily due to lack of adequate water supply. The staff report concluded further analysis for certain issues was unwarranted in light of staff’s recommendation to deny the permit.

On November 8, 2017, the CCC held a de novo hearing and voted to approve the CDP, despite staff recommending denial.

In August 2018, CCC staff issued a subsequent report, containing revised findings in support of the CCC’s approval of the CDP. The 2018 report concluded that water supply was no longer an issue that necessitated denying the project. The 2018 staff report also considered other impacts previously identified in the 2017 report and determined they were no longer relevant or significant, and that staff’s prior conditions of approval would still apply to the project but be adjusted where necessary and implemented in a manner consistent with the project as approved by the Commission. Finally, the report concluded that the project was consistent with CEQA because it adequately addressed any potential adverse impacts to coastal resources, and there were no additional feasible alternatives or mitigation measures that would substantially lessen adverse impacts. The CCC approved the revised findings at a public hearing on September 13, 2018, approximately ten months after the CDP was approved.

FANS filed a petition for writ of mandate challenging the CCC’s approval of the CDP. The trial court denied the petition, rejecting FANS’ assertion that the CCC violated CEQA by approving the project without conducting environmental review before making findings. FANS appealed.

Court of Appeal’s Decision

On appeal, FANS asserted that the CCC failed to employ the proper procedures required by CEQA and the Coastal Act because its “revised findings” were a post-hoc rationalization for the CCC’s prior decision to approve the project and went beyond what was permitted by the CCC’s regulations. The Court of Appeal agreed and reversed the trial court.

The Court of Appeal outlined the steps for seeking CCC review of an approved CDP application and noted that the Commission’s de novo review of a permit application mimics CEQA’s environmental review process. The analysis and recommendation in a staff report must be accompanied by specific findings regarding—among other factors—the project’s conformity with the Coastal Act and CEQA. If the CCC’s action on the project substantially differs from staff’s recommendation, the prevailing Commissioners must separately state the basis to allow staff to prepare a revised staff report with proposed revised findings that reflect the action taken by the Commissioners. Under section 13096 of the CCC’s regulations, a public hearing must be held before the revised findings are adopted. (Cal. Code Regs., tit. 13, § 13096, subd. (c).) After the hearing, the CCC must vote on whether to adopt the revised findings.

Based on the facts of the case, the court held that the CCC’s environmental review for the CDP was incomplete at the time of approval, and the revised finding did not make up for the shortcoming. The court determined that the CCC’s decision to approve the project relied on a staff report that failed to contain elements required by CEQA (and the Commission’s certified regulatory program), including project alternatives, feasible mitigation measures to substantially lessen significant adverse effects, and conditions of approval.

In reaching its conclusion, the court explained the importance of these factors: “Requiring specific findings about alternatives and mitigation measures ‘ensures there is evidence of the public agency’s actual consideration of alternatives and mitigation measures, and reveals to citizens the analytical process by which the public agency arrived at its decision.’ [Citation.]” (Opinion, p. 32.) Through this lens, the court clarified that section 13096 “requires commissioners to set forth the analytic route between the evidence and the action at the hearing before approval.” The court further observed that no prior case law involved facts similar to this one, where the CCC’s environmental analysis was this incomplete at the time a CDP was approved. Accordingly, the court found that the CCC abused its discretion because it was required to conduct the analysis before it approved the project.

– Bridget McDonald

FOURTH DISTRICT UPHOLDS EIR FOR ROADWAY CONNECTION PROJECT AND HOLDS CITY’S QUASI-LEGISLATIVE APPROVALS WERE NOT SUBJECT TO PROCEDURAL DUE PROCESS REQUIREMENTS

In Save Civita Because Sudberry Won’t v. City of San Diego (2021) 72 Cal.App.5th 957, a partially published opinion, the Fourth District Court of Appeal held that the City of San Diego did not violate CEQA by failing to summarize revisions made in its recirculated draft EIR, and that the City’s certification of the Final EIR and approval of the project were quasi-legislative acts not subject to procedural due process requirements.

Background

In 2008, as part of an alternative to a proposed mixed-use development project, the City of San Diego proposed a four-lane major roadway in Mission Valley that would directly connect the development to local roadways. This connector roadway required an amendment to the Serra Mesa Community Plan (SMCP) and the City’s General Plan.

In April 2016, the City issued examined this connector roadway as its own project and prepared a programmatic draft EIR (PDEIR) for the SMCP and General Plan amendments. In March 2017, when roadway construction became foreseeable and upon a large volume of public comment, the City issued a revised and recirculated draft EIR (RE-DEIR) that looked at both the programmatic portion of the project, the adoption of amendments, as well as the actual construction of the roadway. In August 2017, the City issued the Final EIR for the project. Also in August 2017, the Planning Commission voted unanimously, with one member recusing, to recommend approval of the project and certification of the FEIR, with the City Council’s Smart Growth & Land Use Committee voting the same a month later. The City Council certified the Final EIR and approved the project in October 2017.

Save Civita Because Sudberry Won’t (Save Civita) filed a petition for writ of mandate and complaint for declaratory and injunctive relief challenging the City’s certification of the Final EIR and approval of the project on several grounds, namely here that it violated the requirement in CEQA Guidelines section 15088.5, subdivision (g) that a recirculated EIR summarize the revisions made to the prior EIR, and also that it violated procedural due process rights. The trial court denied the petition and complaint. Save Civita appealed.

The Court of Appeal’s Decision

Save Civita argued that the City violated CEQA Guidelines section 15088.5, subdivision (g), because it failed to summarize the changes in the RE-DEIR from the PDEIR, thereby forcing readers to “‘leaf through thousands of pages,’” and cause them “‘to have the mistaken belief’” that the two EIRs address the same project. The Court of Appeal disagreed, holding that statements in the RE-DEIR adequately summarized the changes to the PDEIR, and that these summary provisions informed the public that the revisions to the PDEIR were extensive and the PDEIR had been effectively “replaced” by the RE-DEIR. To make its determination, the court also looked to section 15088.5, subdivision (f), which requires that an agency inform the public that, when an EIR is so substantially revised that the document is recirculated, then comments on the prior EIR will not receive a response. The City fulfilled this criteria.

Furthermore, the court concluded that even if the City had failed to comply with the summation requirements of section 15088.5, any such failure was not prejudicial because it did not deprive the public of a meaningful opportunity to discuss and critique the project. Specifically, the court noted that the administrative record contained “ample and vigorous” public discussion of the RE-DEIR, proof that there were not fatal obstacles to public discourse created by any absence of a revision summary.

Save Civita also argued that the City’s certification of the Final EIR and project approval violated the public’s procedural right to due process and a fair hearing because a member of the City Council, who voted to approve the project was, according to Save Civita, “‘a cheerleader for the Project’” who had predetermined his vote. The court foreclosed this claim by explaining that procedural due process requirements are applicable only to quasi-adjudicatory hearings. Here, the City’s actions were quasi-legislative because they involved the adoption of generally applicable rules on the basis of broad public policy. The project approved by the City and analyzed in its EIR—construction of the roadway and amendment of planning documents—were, as the court determined, matters of public policy that required it to assess a broad spectrum of community costs and benefits. Therefore, procedural due process did not apply.

– Veronika S. Morrison

THIRD DISTRICT FINDS EIR FOR OLYMPIC VALLEY RESORT PROJECT FAILED TO ADEQUATELY CONSIDER IMPACTS TO LAKE TAHOE’S UNIQUE ENVIRONMENTAL RESOURCES

In Sierra Watch v. County of Placer (2021) 69 Cal.App.5th 86, the Third District Court of Appeal found that the EIR for a resort development project in Olympic Valley violated CEQA because it contained an inadequate description of the environmental setting and failed to adequately consider the project’s potential air quality, water quality, and noise impacts on Lake Tahoe and the surrounding Basin.

FACTUAL & PROCEDURAL BACKGROUND

In 1983, Placer County adopted the Squaw Valley General Plan and Land Use Ordinance to guide development and growth within the Olympic Valley (formerly Squaw Valley) area. The 4,700-acre area lies a few miles northwest of Lake Tahoe in the Sierra Nevada mountains.

In 2011, Real Party in Interest Squaw Valley Real Estate LLC proposed the first project under the general plan and ordinance—the Village at Squaw Valley Specific Plan—which included two components to be built over a 25-year timeframe: (1) an 85-acre parcel that included 850 lodging units, approximately 300,000 square feet of commercial space, and 3,000 parking spaces (“the Village”); and (2) an 8.8-acre parcel that included housing for up to 300 employees (“the East Parcel”).

The County approved the project and certified its associated EIR in 2016. Following the County’s approval, Sierra Watch filed a petition for writ of mandate, alleging the County violated CEQA in numerous ways. The trial court rejected Sierra Watch’s claims. Sierra Watch appealed.

COURT OF APPEAL’S DECISION

In the published portion of the opinion, the Third District considered whether the EIR sufficiently described the project’s environmental setting and adequately considered water quality, air quality, and noise impacts.

EIR’s Description of the Environmental Setting

The court first considered whether the EIR’s discussion of the environmental setting adequately addressed Lake Tahoe and the Lake Tahoe Basin, particularly with respect to the settings for water and air quality.

Water Quality Setting

As to water quality, the Court of Appeal agreed with Sierra Watch’s assertion that the EIR’s hydrology and water quality analysis failed to adequately describe the regional setting specific to Lake Tahoe. Though the Draft EIR explained that the project would be “located within the low elevation portion of the approximately eight square mile Squaw Creek watershed, a tributary to the middle reach of the Truckee River (downstream of Lake Tahoe),” it concluded that VMT generated by the project would not exceed TRPA’s cumulative VMT threshold, and thus, would not affect the Lake’s water quality. The court rejected this rationale by noting that the EIR’s description failed to discuss the importance of the Lake’s current condition or the relationship between VMT and the Lake’s water clarity and quality, thereby depriving the public of an ability to evaluate and assess impacts on the Lake.

Air Quality Setting

As to air quality, the court found that the EIR’s description of the air quality setting and baseline was more substantial, and thus, adequate. The EIR properly explained the applicable air quality standards and presented data on the current concentrations and sources of criteria air pollutants in the area.

EIR’s Analysis of Impacts

Air Quality Impacts

The court agreed with Sierra Watch’s assertion that the EIR failed to meaningfully assess the project’s traffic impacts on Lake Tahoe’s air quality. The EIR concluded the project would not exceed TRPA’s cumulative VMT threshold but acknowledged it would likely exceed TRPA’s project-level VMT threshold for basin traffic. Nevertheless, the EIR ultimately concluded that TRPA’s VMT significance thresholds did not apply because the project was not located in the Tahoe Basin. The court found this rationale “provided mixed messages.” Rather than summarizing and declaring TRPA’s VMT thresholds as inapplicable, the court held that the EIR should have determined whether the Project’s impacts on Lake Tahoe and the Basin were potentially significant.

The court also agreed that the EIR underestimated the Project’s expected cumulative VMT in the Basin by failing to consider expected VMT from other anticipated projects. Even though the County addressed this issue in post-FEIR responses to comments, the court held that the public was denied an opportunity to “test, assess, and evaluate the newly revealed information and make an informed judgment as to the validity of the conclusions to be drawn therefrom.”

Construction Noise Impacts

The court rejected Sierra Watch’s initial assertion that the EIR failed to adequately disclose the duration of construction noise at any specific location, particularly at the Village parcel. The EIR properly explained that that portion of the Project would be constructed over 25 years based on market conditions, and thus, it would be too speculative to identify specific noise levels for every single receptor.

The court agreed, however, with Sierra Watch’s assertion that the EIR failed to analyze the project’s full geographic range of noises by ignoring activities occurring farther than 50 feet from sensitive receptors. The court reasoned that a “lead agency cannot ignore a project’s expected impacts merely because they occur…’outside an arbitrary radius.’” The EIR only considered impacts to sensitive receptors within 50 feet of construction—yet, according to the court, “ignore[d] potential impacts to a receptor sitting an inch more distant[,] even though the noise levels at these two distances would presumably be the same.” Though the County explained this analysis was standard practice, the court contended that an agency “cannot employ a methodological approach in a manner that entirely forecloses consideration of evidence showing impacts to the neighboring region [and] beyond a project’s boundaries.”

Finally, the court agreed that mitigation requiring “operations and techniques … be replaced with quieter procedures where feasible and consistent with building codes and other applicable laws and regulations” was too vague because “in effect, [it] only tells construction contractors to be quieter than normal when they can.” The court concluded that the measure improperly deferred which construction procedures can later be modified to be quiet but did not explain how these determinations are to be made.

– Bridget McDonald

*RMM Attorneys Whit Manley, Andee Leisy, Chip Wilkins, and Nathan George represented Real Party in Interest Squaw Valley Real Estate LLC in this litigation.