Tag: EIR

Third District Court of Appeal Upholds EIR for Chico Walmart Expansion Against Challenge to Urban Decay Analysis

In a partially published decision issued on October 3, 2019, the Third District Court of Appeal affirmed a judgment upholding an EIR for a Walmart expansion project in Chico against challenges to the EIR’s urban decay analysis. (Chico Advocates for a Responsible Economy v. City of Chico (2019) 40 Cal.App.5th 839.)

In 2015, Walmart applied to the city to expand its existing Chico store in a regional retail center that includes the Chico Mall and several national chain retail stores. A FoodMaxx grocery store is also nearby. Walmart planned to expand its existing store by approximately 64,000 square feet, add an eight-pump gas station, and create two new outparcels for future commercial development. Approximately 49,000 square feet of the new space would be used for grocery-related sales.

The city prepared an EIR for the project that included, among other things, a “robust 43-page urban decay analysis.” The urban decay analysis was supported by a 123-page expert study prepared by ALH Urban & Regional Economics. The purpose of the ALH study was to assess the economic impact of the project on retailers in the surrounding area and to evaluate the extent to which the project could contribute to store closures and urban decay. For purposes of the study, “urban decay” was defined as “visible symptoms of physical deterioration . . . that is caused by a downward spiral of business closures and long term vacancies . . . [and]. . . so prevalent, substantial, and lasting for a significant period of time that it impairs the proper utilization of the properties and structures, and the health, safety, and welfare of the surrounding community.”

The ALH study concluded that, on its own, the project would have a negligible impact on sales for competing retailers and that store closures were not expected to follow. Based on these findings, the EIR concluded that the project would not cause the type of severe economic effects that would lead to urban decay. With regard to cumulative impacts, the ALH study concluded that the project, when combined with other planned retail projects in the area, could induce the closure of one full-service grocery store. The city’s retail vacancy rate, however, would only increase by approximately one percent and would remain “well within the range of a robust, healthy commercial retail sector.” The EIR further explained that Chico has a strong history of “backfilling” store vacancies, that existing vacant properties are well-maintained, and that the city has regulations to prevent decay and blight. For these reasons, the EIR concluded that although some economic impacts were expected, cumulative impacts likely would not result in urban decay.

Following the city’s certification of the EIR, Chico Advocates for a Responsible Economy (CARE) challenged the urban decay analysis in an administrative appeal to the city council. CARE supported its challenge with its own “retail expert” report refuting the city’s analysis. The city council denied the appeal.  CARE then filed a petition for writ of mandate seeking to rescind the EIR and project approvals. The trial court denied the petition in full and CARE appealed.

On appeal, CARE challenged the EIR’s urban decay analysis on two grounds. First, CARE argued that the EIR relied on an “unnaturally constrained” definition of “urban decay” and, as a result, failed to treat the loss of “close and convenient shopping” as a significant environmental impact. Second, CARE argued that, due to flaws in the ALH study’s methodology, the EIR’s urban decay findings were not supported by substantial evidence.

Addressing the first issue, the court began its discussion by explaining the applicable standard of review for allegations that an EIR failed to include necessary information. Citing the Supreme Court’s recent decision in Sierra Club v. County of Fresno (2018) 6 Cal.5th 502, the court explained that CARE’s argument presented the predominantly legal question of whether the EIR included enough detail “to enable those who did not participate in its preparation to understand and consider meaningfully the issues raised by the proposed project,” which is subject to independent review. On this issue, the court found “CARE’s argument lacks merit – the City did not violate CEQA because the potential loss of close and convenient shopping is not an environmental issue that must be reviewed under CEQA.” “CEQA is concerned with physical changes in the environment,” the court explained, and “[a]lthough the loss of close and convenient shopping could impact some Chico residents psychologically and socially, such impacts are not, by themselves, environmental impacts.”

Next, the court turned to CARE’s attack on the methodology for the urban decay analysis. CARE alleged three flaws with the urban decay study’s methodology. First, CARE argued that the study relied on incorrect assumptions for calculating the anticipated grocery sales. Second, CARE argued that the study underestimated impacts on Chico stores by incorrectly assuming shoppers from the neighboring Town of Paradise would patronize the Walmart. Lastly, CARE argued that the study incorrectly assumed economic impacts would be spread amongst existing stores, rather than concentrated on the closest competitor – the FoodMaxx grocery.

In rejecting each of CARE’s arguments, the court explained that challenges to the EIR’s methodology are reviewed under the substantial evidence standard. Under this standard, challenges to the EIR’s methodology “must be rejected unless the agency’s reasons for proceeding as it did are clearly inadequate or unsupported.” Moreover, the court explained, when an agency is faced with conflicting evidence on an issue, it is permissible to give more weight to some evidence than others – mere “disagreement among experts” does not render an EIR inadequate.

In this case, the court concluded that CARE’s challenge amounted to “nothing more than differences of opinion about how the Project’s expected grocery sales should be estimated, how the Project’s market area should be defined, and which competitors are most susceptible to impacts from the Project.” These differences in opinion, the court explained, did not render the EIR’s analysis clearly inadequate or unsupported. Therefore, CARE’s challenge failed under the substantial evidence test.

The court further noted that although CARE’s own expert report showed additional store closures would occur, CARE failed to demonstrate how such closures would lead to urban decay. As the court explained, “Store closures, by themselves, do not amount to urban decay.”

Second District Invalidates EIR’s Project Description For Failing to Provide Sufficient Detail and Certainty.

In Stopthemillenniumhollywood.com et al. v. City of Los Angeles et al. (2019) 39 Cal.App.5th 1, the Second District Court of Appeal affirmed the trial court’s conclusion that an EIR for a mixed-use development project proposed by Millennium Hollywood, LLC (Millennium) in the City of Los Angeles (City) violated CEQA as a matter of law, because it failed to provide an accurate, stable, and finite project description.

In 2008, Millennium filed an application—which the Court of Appeal described as detailed—with the City proposing a mixed-use development project (2008 Proposal) on 4.47 acres in multiple parcels straddling two sides of Vine Street, between Yucca Street and Hollywood Boulevard, in the Hollywood Community Plan area of the City. The 2008 Proposal described a mixed-use development with 492 residential units, a 200-unit hotel, 100,000 square feet of office space, a 35,000-square-foot sports club and spa, 11,000 square feet of commercial uses, and 34,000 square feet of food and beverage uses. In total, proposed square footage was 1,163,079. Two historic buildings on site, the Capital Records Tower and Gogerty Building, would be preserved. The development would consist of two low-rise buildings, one on each side of Vine Street, with three towers intended to “frame” the Capital Records Tower. The 2008 Proposal would have required a zone change to allow the sports club, as well as a variance to allow the proposed density. After the City informed Millennium that a variance from the General Plan Floor Area Ratio (FAR) requirement would also be necessary, the project was put on hold.

In 2011, Millennium filed a new application with a new project description for the same site (2011 Project). Millennium still proposed a mixed-use development with residential, hotel, and retail uses totaling 1,166,970 square feet and a FAR of 6:1. Though the same mix of uses were proposed, the 2011 Project was “designed to create an impact ‘envelope’ within which a range of development scenarios can occur.” Thus, the specific shape, size, location, use, and number of buildings to be constructed on the site were not described, other than that the existing historic buildings would be preserved. Instead, Millennium sought to enter into a development agreement with the City that would establish the permitted developable floor area, land uses, design guidelines, and development standards for the site. Additionally, the 2011 Project included a land use equivalency program (LUEP) allowing the transfer of floor area between parcels on the site. The EIR analyzed the maximum level of impacts that could occur under the development agreement, regardless of which of the several development scenarios was actually constructed in the future.

Commenters on the Draft EIR complained that the imprecise project description hindered meaningful public participation. Nevertheless, the City approved the development agreement, certified the EIR, adopted mitigation for the analyzed maximum level of impacts and adopted a statement of overriding considerations. Petitioners, Stopthemillenniumhollywood.com, Communities United for Reasonable Development, and George Abrahams (collectively, Petitioners) petitioned the Los Angeles Superior Court for a writ of mandate setting aside project approval and certification of the EIR. Petitioners alleged three causes of action relating to violations of CEQA. First, they alleged that the EIR failed to include an accurate, stable, and finite project description. The second cause of action asserted that the City abused its discretion by failing to study traffic impacts to the 101 freeway despite Caltran’s direction that the City do so. The third cause of action alleged that the City failed to consult with the California Geological Survey regarding potential seismic hazards on the site. The trial court granted the petition as to the first and second causes of action, but not the third.

On the first cause of action, the trial court found that the project description was not stable or finite, and that the use of the word “or” in a condition of approval allowed Millennium, or future developers, to choose any permitted use listed for the C2 zone in the LAMC for future development, not just the list of proposed uses in the development agreement. The trial court reasoned that, though there may be circumstances where a project description may disclose only the physical parameters and maximum potential environmental impacts, no such circumstances were present here. The trial court distinguished Citizens for a Sustainable Treasure Island v. City and County of San Francisco (2014) 227 Cal.App.4th 1036 (Treasure Island), on the grounds that that case dealt with a site contaminated by hazardous materials, and it was unknown when cleanup of the site would be completed. The trial court noted that the development in Treasure Island included both fixed elements (including the street grid) and conceptual elements that would “likely” be subject to supplemental CEQA review. The trial court concluded that neither element was present here.

The trial court also found that, by including an ambiguous project description, the EIR impermissibly deferred part of the analysis of environmental impacts. Specifically, the trial court found that, because no specific “concept” was analyzed, the EIR did not explain how exceedance of the maximum impacts would be avoided when the project was actually designed and built; nor was additional CEQA review contemplated by either the EIR or the development agreement. The trial court determined that, without knowing the “bona fide subject” of the EIR, it would be impossible for the public and decisionmakers to accurately weigh the “environmental price tag” of the proposal and decide if the benefits outweigh that price.

The City and Millennium appealed the trial court’s decision as to the first and second cause of action, while Petitioners appealed the decision on the third cause of action. The Court of appeal, after ruling on the first cause of action, determined that it need not reach the other issues raised by the parties.

In affirming the trial court, the Court of Appeal looked to County of Inyo v. City of Los Angeles (1977) 71 Cal.App.3d 185 (County of Inyo), and Washoe Meadows Community v. Department of Parks and Recreation (2017) 17 Cal.App.5th 277 (Washoe Meadows). The Court cited County of Inyo for the proposition that, even where an inaccurate project description does not render invalid the analysis of environmental effects, it may nevertheless violate CEQA by interfering with “intelligent public participation.” The Court found further support for this position in Washoe Meadows, where the First District held that a failure to select or identify a specific project in the Draft EIR interfered with the public’s right to participate in CEQA review.

In the case before it, the Court found that the project description “fail[ed] to describe the siting, size, mass, or appearance of any building proposed to be built at the project site” and that the proposed development regulations imposed only vague and ambiguous limits on future construction choices. The Court held that, even if the analysis of maximum impacts were adequate—despite the project description, “CEQA’s purposes go beyond an evaluation of theoretical environmental impacts.” The Court determined that the project description violated CEQA as a matter of law.

In reaching its decision, the Court distinguished South of Market Community Action Network v. City and County of San Francisco (2019) 33 Cal.App.5th 321 (South of Market), on two grounds. First, the Court found that the only “uncertainty” at issue in South of Market was that the project description presented a choice of either a predominately office use or a predominately residential use, but the EIR did not select one or the other. Second, the Court found that the EIR in South of Market “included ‘site plans, illustrative massing, building elevations, cross-sections and representative floor plans for both options.”’ Because the EIR before it did not include these “technical characteristics” of the project, the Court concluded that it failed to comply with CEQA’s mandates. The Court also largely agreed with basis for the trial court’s distinguishing of Treasure Island, supra, 227 Cal.App.4th 1036, finding that no unusual circumstances were present in this case, and that future planning and development of the project would not be subject to additional environmental review. Lastly, the Court found the violation to be prejudicial because it interfered with public participation.

As stated above, the Court determined that it need not address the other issues raised by the parties. The Court dismissed an argument that Public Resources Code section 21168.9 required them to rule on each issue raised in a CEQA appeal. The Court found that section applied only to the trial court’s order on remand, which is to address only those mandates from the Court of Appeal that are necessary to comply with CEQA. The Court found that the trial court’s judgment was correct on at least one ground, so it was affirmed.

Nathan George

First District Court of Appeal Upholds EIR for Mixed-Use Development Project

In the first published decision to apply the standard of review articulated by the Supreme Court in Sierra Club v. County of Fresno (Friant Ranch), the First District Court of Appeal affirmed the trial court’s decision upholding an EIR for a mixed-use development project in South of Market Community Action Network v. City and County of San Francisco (2019) 33 Cal.App.5th 321.

The project at issue is a mixed-use development that covers four acres of downtown San Francisco and seeks to provide office, retail, cultural, educational, and open-space uses for the property, to support the region’s technology industry and offer spaces for coworking, media, arts, and small-scale urban manufacturing. The city certified an EIR, which described two options for the project—an “office scheme” and a “residential scheme.” The office scheme had a larger building envelope and higher density than the residential scheme but all other project components were the same and the overall square footage was substantially similar. Several community organizations raised a variety of claims challenging the environmental review. The trial court denied relief and the petitioners appealed.

Applying the three “basic principles” set forth by the Supreme Court in Friant Ranch regarding the standard of review for the adequacy of an EIR, the First District held the EIR was legally adequate.

The court rejected the petitioners’ argument that the project description was inadequate because it presented multiple possible projects. The court found that the EIR described one project—a mixed use development involving retention or demolition of existing buildings and construction of new buildings—with two options for different allocations of residential and office units. The court also rejected petitioners’ argument that the final EIR adopted a “revised” project that was a variant of another alternative identified in the draft EIR—emphasizing that the CEQA reporting process is not designed to freeze the ultimate proposal in the precise mold of the initial project, but to allow consideration of other options that may be less harmful to the environment.

Petitioners alleged that the cumulative impacts analysis was flawed because the EIR used an outdated 2012 project list, developed during the “Great Recession,” which did not reflect a more recent increase in development. The court noted the petitioners did not point to any evidence to establish that the project list was defective or misleading or that the city had ignored foreseeable projects. Accordingly, the court held that the petitioners had not met their burden of proving the EIR’s cumulative impacts analysis was not supported by substantial evidence.

With respect to traffic, the petitioners argued the EIR was inadequate because it failed to (1) include all impacted intersections, (2) consider the impact of the Safer Market Street Plan (SMSP), and (3) adequately evaluate community-proposed mitigation measures and alternatives. The court rejected each argument in turn. First, the court found that the EIR’s explanation for selecting certain intersections and excluding others and the related analysis was supported by substantial evidence. The court further held that the city did not need to include the SMSP in the EIR because it was not reasonably foreseeable when the city initiated the EIR, nor was there evidence that the SMSP would have an adverse impact on traffic and circulation related to the project. Lastly, the court deferred to the city’s selection of alternatives because the petitioners had failed to meet their burden to show the nine alternatives evaluated in the EIR were “manifestly unreasonable.” Similarly, the court found the petitioners had failed to meet their burden to demonstrate their proposed alternatives were feasible and met most of the project objectives.

In addressing wind impacts, an argument petitioners failed to exhaust, the court found such impacts were appropriately addressed in the EIR. The court reasoned an alternative configuration was not required under the city’s comfort criterion for wind speed impacts because the exceedance of the comfort criterion did not establish significant impacts for CEQA purposes.

The court also rejected an argument that the project failed to provide onsite open space because the EIR explained that the project provided more space than the city code required and the impact related to demand on existing parks and open spaces would be less than significant.

The court further upheld the EIR’s shade and shadow analysis, finding no evidence in the record to support that sunlight on a park is not a “special and rare resource” warranting “special emphasis” under CEQA Guidelines section 15125.

The court also held that the city had made a good faith effort to discuss inconsistencies with the applicable general plans, noting that CEQA does not “mandate perfection.”

Finally, the petitioners claimed that the statement of overriding considerations was invalid because the city improperly considered the benefits of the project before considering feasible mitigation measures or alternatives. The court disagreed, emphasizing that the project was modified to substantially conform to the identified environmentally superior alternative and stating that the revised project would not have been adopted if there had been no consideration of mitigation measures or alternatives.

Second District Finds that CEQA’s Supplemental Review Provisions Applied to Modification of Commercial Development Project adding a Specific Plan Amendment and that the Amendment was not Impermissible “Spot Zoning”

In Citizens Coalition Los Angeles v. City of Los Angeles (2018) 26 Cal.App.5th 561, the Second District Court of Appeal overturned the trial court’s decision that revisions to a commercial development project to include a specific plan amendment constituted a “new project” under CEQA, and found that supplemental review under Public Resources Code section 21166 applied instead. Additionally, the Court determined that, while the specific plan amendment created a “spot zone,” substantial evidence supported the City’s determination that the amendment was in the public interest, and thus not impermissible under the test announced in Foothill Communities Coalition v. County of Orange (2014) 222 Cal.App.4th 1302.

Target Corporation (Target) applied to build a Super Target retail store at the intersection of Sunset Boulevard and Western Avenue in Hollywood. The project contemplated a nearly 75-foot tall, three-story building with the Target store occupying the third floor, parking on the second, and the first floor containing several smaller retail stores, a transit kiosk, and a pedestrian plaza. The City of Los Angeles certified the environmental impact report (EIR) prepared for the project, and granted eight variances from the Vermont/Western Transit Oriented District Specific Plan (SNAP) allowing the project to be built as proposed. Target began construction of the project. Several community associations (plaintiffs) filed separate petitions for writ of mandate challenging the City’s approval of the project, alleging violations of CEQA, and that the grant of the variances were not supported by substantial evidence in violation of the Los Angeles Municipal Code. The trial court upheld the EIR, but found that six of the eight variances were not supported by substantial evidence and ordered construction to cease.

While that case was pending on appeal, the City amended the SNAP to create a new subarea (Subarea F) that would allow projects similar to Target’s to be built in certain parts of the specific plan area without the need for variances, and designated the project site as Subarea F. There were two other locations in the specific plan area that could qualify for the Subarea F designation, but no projects meeting the requirements of Subarea F were proposed to the City at those locations. The appellate court dismissed the appeal as moot, leaving the trial court’s decision intact. The City prepared and approved an addendum to the Target project EIR, defining the revised project as the SNAP amendment and the completion of construction for the Target project. The same plaintiffs challenged the revised project approval, alleging that the City violated CEQA by relying on an addendum rather than a new, subsequent, or supplemental EIR, and that the City impermissibly “spot-zoned” by amending the SNAP for the project. The trial court found that the SNAP amendment was a new project, making the addendum improper but did not reach the “spot zoning” issue. The City and Target appealed.

The court of appeal, in analyzing whether the addendum violated CEQA asked three questions: what did the SNAP amendment do? Do CEQA’s supplemental or initial project review provisions apply? And, did the City comply with the applicable CEQA provisions? The court answered each question in turn. First, the court found that SNAP amendment, though it created a new subarea, only placed the project location into that subarea. While two other locations in the SNAP area could meet the proximity to transit and acreage requirements, they did not meet the commercial square footage requirement and no projects meeting that requirement had been proposed to the City. The court also rejected plaintiffs’ “haphazard” development argument, finding that the amendment was consistent with the SNAP’s policies and that the City could rationally take planning and development “one step at a time.”

In determining whether CEQA’s supplemental review provisions applied, the court found that there had been prior CEQA review of the Target project. Thus, the question was “whether the previous environmental document retains any relevance in light of the proposed changes.” (Citing Friends of College of San Mateo Gardens v. San Mateo County Community College Dist. (2016) 1 Cal.5th 937, 944.) The court found that substantial evidence supported the City’s determination that the previous EIR retained relevance for the revised project. The court rejected the argument that, because the previous EIR was limited to a specific development “project” and the SNAP amendment involved more general policy considerations, the “project” EIR was insufficient. The court found that the label placed on the EIR said little about its sufficiency as an informational document. The proper question is whether the EIR retains any value in addressing the impacts associated with the revised project.

Next, the court asked whether the City complied with CEQA’s supplemental review requirements, and found that substantial evidence supported the City’s decision to rely on an addendum for the revised project. Plaintiffs made four arguments, all of which the court rejected. First, petitioners argued that the addendum did not discuss the SNAP amendment, which the court stated was factually inaccurate. Second, they argued that the City intended further development in the SNAP area through the new subarea because of some of the language the City used in describing the requirements of the new subarea. The court found that the cited language did not negate the substantial evidence supporting the City’s finding that no additional development was foreseeable. Third, plaintiffs argued that additional development projects at the two locations that could qualify for the new subarea, and any other locations that could be “cobbled together” were reasonably foreseeable consequences of the SNAP amendment that required a subsequent or supplemental EIR. The court found that whatever incentive for development the amendment created, evidence of that incentive did not overcome the substantial evidence supporting the City’s determination. Lastly, plaintiffs argued that de novo review should apply because the challenge to the amendment required the court to construe its meaning. The court found that the issue before it involved the amendment’s environmental impact, not its meaning, and thus review was for substantial evidence.

Though the trial court did not address the “spot zoning” issue, the court of appeal did, finding that it was important enough to resolve the fully briefed, longstanding issue. Under the analysis in Foothill Communities, the court found that the SNAP amendment did create a zoning “island,” though it was unclear whether the zoning was less or more stringent than the surrounding parcels because of the specific requirements for the new subarea. Regardless, the question was whether the zoning decision creating the “island” was arbitrary, irrational or unreasonable. The court found that, under that standard, the spot zone was valid. Further, the City’s determination that the amendment was in the public interest was supported by substantial evidence, and the SNAP, as amended, remained compatible with the City’s general plan. The court rejected plaintiffs’ challenge to the City’s alleged motive in amending the SNAP, and plaintiffs’ questioning of whether the SNAP amendment represented good policy, as neither issue was appropriate for the court’s inquiry. The court also found that even if future projects proposed to use the new subarea, the City retained its power to determine whether each project is in the public interest. Lastly, the court rejected plaintiffs’ argument that the amendment to the SNAP was “incompatible” with it because the amendment would “alter” the SNAP.  The court found that the law unambiguously allows specific plan amendments.

Nathan O. George

First District Court of Appeal Upholds Judicial Council of California’s Determination That Closure of Downtown Placerville Courthouse Would Not Lead to Significant Urban Decay Impacts

On October 16, 2017, the First District Court of Appeal published its decision in Placerville Historic Preservation League v. Judicial Council of California (2017) 16 Cal.App.5th 187, upholding the San Francisco County Superior Court’s denial of a petition for writ of mandate challenging the Judicial Council of California’s decision to certify a Final EIR and approve the New Placerville Courthouse Project.

Background

El Dorado County’s court facilities are currently divided between the Main Street Courthouse, a historic building in downtown Placerville, and the County administrative complex. The Judicial Council proposed to consolidate all court activities in a new three-story building to be built on undeveloped land adjacent to the County jail, less than two miles away from the existing Main Street Courthouse.

In October 2014, the Judicial Council published a draft EIR for the proposed new courthouse. The draft EIR acknowledged that retiring the downtown courthouse could have an impact on downtown Placerville. The EIR also recognized that the Judicial Council was required address neighborhood deterioration as a significant environmental effect under CEQA if urban decay was a reasonably foreseeable impact of the project. The draft EIR defined “urban decay” as “physical deterioration of properties or structures that is so prevalent, substantial, and lasting a significant period of time that it impairs the proper utilization of the properties and structures, and the health, safety, and welfare of the surrounding community.” The draft EIR concluded that urban decay, so defined, was not a reasonably foreseeable consequence of the new courthouse project.

Comments received both during and after the public review period on the draft EIR voiced the concern that closing the historic Main Street Courthouse could negatively affect businesses in downtown Placerville. In response to such concerns, the Judicial Council reiterated the draft EIR’s conclusion that the project was not likely to lead to urban decay. In support of this conclusion, the Judicial Council observed that it was working with both the city and county to develop a re-use strategy for the building that would support the downtown businesses and local residences. The Judicial Council also cited evidence of the City and County’s efforts to find a new use for the historic courthouse building.

Following the Judicial Council’s certification of the final EIR, the Placerville Historic Preservation League (League) filed a petition for writ of mandate, which the trial court denied. The Court of Appeal affirmed.

The Court of Appeal’s Decision

On appeal, the League argued that the Judicial Council erred in concluding that urban decay is not a reasonably foreseeable indirect effect of relocating the courthouse activities from downtown Placerville to their new location. The court held that substantial evidence in the record supported the Judicial Council’s conclusion that the type of physical deterioration contemplated in the term “urban decay” is not reasonably foreseeable. The court explained that there is no presumption that urban decay would result from the project. To the contrary, as defined by CEQA—which focuses on the physical environment—urban decay “is a relatively extreme economic condition.” Evidence in the record, including comments submitted by the public, suggested that downtown Placerville was an economically stable area, and could withstand business closures without falling into urban decay.

The League also characterized the likelihood of the re-use of the historic courthouse building as an “‘unenforceable and illusory”’ commitment. The court explained, however, that the lack of a binding requirement for the re-use of the building does not undermine the EIR’s reasoning. Specifically, the issue before the Judicial Council was whether urban decay was a reasonably foreseeable effect of the project, not whether its occurrence was a certainty. It would be the best interest of the City of Placerville and the County of El Dorado to re-use the historic courthouse building, suggesting that the building was likely to be put to a new use. While the re-use was by no means guaranteed, it was reasonably likely. Therefore, the Judicial Council did not err in relying on the possibility of re-using the building as one basis for concluding that urban decay was not reasonably foreseeable.

The League also argued that the administrative record contained evidence, in the form of comments submitted by local residents and businesses, of the impact of moving the courtroom activities outside of downtown Placerville. The court held that although these letters and comments provided credible grounds to conclude that relocating the courthouse activities would constitute a hardship for some local businesses, it was not substantial evidence to support the conclusion that such economic effects would lead to substantial physical deterioration of the downtown.

The League further argued that the Judicial Council should have prepared an economic study evaluating the effects of removing the courthouse functions from downtown. The court disagreed, noting that in “any endeavor of this type, financial resources are limited, and the lead agency has the discretion to direct resources toward the most pressing concerns.” Just because a financial impact study might have been helpful does not make it necessary.

The Judicial Council was represented by RMM attorneys Andrea Leisy and Laura Harris in the trial court and on appeal.

Fourth District Holds that Land Acquisition Agreement Did Not Trigger Duty to Prepare an EIR

In Bridges v. Mt. San Jacinto Community College District (2017) 14 Cal.App.5th 104, the Fourth District Court of Appeals held that a land acquisition agreement entered into by the Mt. San Jacinto Community College District to purchase property from the Riverside County Regional Park & Open-Space District for potential future use as the site of new campus did not trigger the duty to prepare an EIR.

As a threshold issue, the court held that the appellants were barred from raising objections to the college’s decision because they had failed to exhaust their administrative remedies. The appellants argued that they were excused from objecting to the purchase agreement because the college did not give notice of the meeting at which it approved the agreement. Because the appellants could not establish that the no-notice exception applied—the court relied on the presumption afforded by Evidence Code section 664 to presume that the college had posted the agenda in accordance with the Brown Act requirements because the record contained no evidence to the contrary.

Nonetheless, the court went on to discuss the merits and determined that appellants’ claims were meritless because the purchase agreement required completion of an EIR before the sale could even be finalized. The court found that the purchase agreement complied with CEQA’s land acquisition agreement rule. Unlike the circumstances in the definitive California Supreme Court decision, Save Tara v. City of West Hollywood (2008) 45 Cal.4th 116, here, no funds had been committed to the project and a developer had yet to be identified. The court found nothing in the administrative record to indicate that the college had committed itself to a definitive use of the property.

Finally, the court held the college did not violate CEQA by failing to formally adopt local implementing guidelines. Public Resources Code section 21082 provides an exemption for school districts, if they “utilize” the guidelines of another public agency. Here, the college had chosen to use the local guidelines adopted by Riverside County.

 

Christina Berglund

Fourth District Upholds EIR for Master-Planned Community and Concludes That County Not Required to Recirculate

On March 15, 2017 the Fourth District certified for publication its February 4, 2017 decision in Residents Against Specific Plan 380 v. County of Riverside (2017) 9 Cal.App.5th 941, upholding the EIR for a master- planned community (project). A citizens group challenged the sufficiency of the EIR and the county’s approval process on six grounds. The court found for the county and real party in interest, Hanna Marital Trust (applicant), on every count.

The project proposes a master-planned community with seven planning areas containing medium-density residential housing, mixed uses, commercial retail, and dedicated open space on 200 acres of undeveloped land in Riverside County. Planning area 6, the mixed use area, was analyzed as potentially providing for the development of a Continuing Care Retirement Community (CCRC) for seniors.

On July 28, 2011, the County Planning Department released a Draft EIR (DEIR). The DEIR stated that mitigation measures would reduce the environmental impacts to a below significant level, except for air quality and noise. During the public comment period, the South Coast Air Quality Management District (SCAQMD) and the City of Temecula raised concerns about the project’s air quality impacts. The final EIR (FEIR) was released in January 2012 and included responses to SCAQMD’s and Temecula’s comments. The FEIR reflected changes in the location of some project elements, but was “in its basics identical” with the project as described in the DEIR.

The Planning Commission reviewed the FEIR in April 2012 and suggested revisions, which were subsequently presented to the Commission in October 2012. The Commission recommended approval of the FEIR and the Project to the Board of Supervisors. The Board reviewed the FEIR at its December 11, 2012 meeting, where it considered some modifications to the project and Residents Against Specific Plan 380 (petitioners) suggested additional noise mitigation measures. At its December 18, 2012 meeting, the Board tentatively approved the FEIR, contingent on finalization of the modifications. On November 5, 2013, the Board approved the finalized FEIR, general plan amendment, zone change, and Specific Plan 380. The EIR resolution included findings of fact, a mitigation monitoring and reporting plan, and a statement of overriding considerations. The same day, the county clerk posted a Notice of Determination (NOD) that erroneously used an out-of-date project description.

On November 18, 2013, petitioners filed a petition for a writ of mandate, which was denied by the trial court. This appeal followed.

First, the Fourth District concluded that the Board did not substantially modify the EIR after approving it. Because the Board only tentatively approved the project in December 2012, the final approval in November 2013 reflected the Plan’s modifications. Similarly, the court disagreed with the petitioners’ argument that the findings, statement of overriding considerations, and mitigation plan were not timely and concurrently approved.

Second, the court concluded that the NOD substantially complied with the informational requirements of CEQA, despite its project description errors. The court also noted that the petitioners could not show that the errors were prejudicial because they filed the suit well before the statute of limitations had run.

Third, the court held that the changes made by the Commission and Board were not significant enough to require recirculation of the EIR. In reaching its determination, the court relied on CEQA Guidelines § 15088.5, subd. (a), stating that a lead agency must recirculate an EIR when significant new information is added that reveals a substantially new or increased impact. The court rejected the petitioners’ argument of increased traffic impacts, holding that only traffic patterns would be affected, not intensity. The court also rejected the petitioners’ contention that increased biological impacts would result from moving the mixed-use area further north, as the open space region was already adjacent to it. Petitioners’ argument of increased noise impacts was contradicted by the county’s expert. Finally, the petitioners failed to substantiate their claim of potential land use inconsistencies. Therefore, the County had an adequate basis for not recirculating the EIR. Petitioners’ reliance on Vineyard Area Citizens for Responsible Growth v. City of Rancho Cordova (2007) 40 Cal.4th 412 and Save our Peninsula Committee v. Monterey County Board of Supervisors (2001) 87 Cal.App.4th 99 were inapposite, as the EIR did not reveal facially significant new impacts nor areas necessitating further factual development.

Fourth, the court concluded that the EIR adequately analyzed the impacts of the mixed-use area under the rubric of a proposed CCRC. Petitioners alleged that by analyzing only a CCRC, and not other potentially higher impact uses, the EIR’s analysis of the mixed-use planning area was improperly narrow in scope. The court rejected this argument because substantial evidence supported the County’s decision to limit the scope of the analysis to a CCRC. Even if the applicant did not build a CCRC, the project plan restricted the applicant to other permitted uses in the planning area, and only if they would not incur additional environmental impacts. Nor, the court stated, does CEQA require the county to analyze what are merely possible development schemes.

Finally, the court ruled that the EIR adequately considered the specific suggestions for mitigating the project’s air quality and noise impacts from SCAQMD, Temecula, and the petitioners. Regarding mitigation for air emission impacts proposed by SCAQMD and Temecula, the county could justify why the measures were not adopted, why they were infeasible given the project’s timeline and parameters, or why they were duplicative with measures already adopted. SCAQMD’s proposal to utilize lower emission vehicles did not reflect the construction equipment anticipated to be reasonably available. Temecula’s suggestion of applying the 2010 Energy Code was duplicative of the requirement to exceed the 2008 Code emission standards by 15%, and the code in force at the time of construction would control in any event. Furthermore, the county was not required to adopt the specific prescriptive emission reduction measures in the Green Building Standards Code, but could opt for performance-based standards that are less likely to incur enforcement and enforceability issues. With respect to the additional noise mitigation measures proposed by the petitioners, these were found to be untimely raised more than a year after the comment period had closed. Therefore, the county was not obligated to respond. Moreover, the county was justified in not adopting these noise mitigation measures because they require electric construction equipment that may not be available or may duplicate existing requirements.

 

First District Court of Appeal Upholds EIR for Plan Bay Area that Correctly Excluded Statewide Emissions Reductions in Developing Strategies to Meet SB 375’s Emissions Targets

In Bay Area Citizens v. Association of Bay Area Governments (2016) 248 Cal.App.4th 966, the First District Court of Appeal interpreted SB 375 as requiring the California Air Resources Board (Board) and regional agencies to set and meet the emissions reductions targets through regionally-developed land use and transportation strategies that are independent of existing statewide clean technology mandates. Therefore, the court of appeal upheld the Bay Area Metropolitan Transportation Commission and the Association of Bay Area Government’s (collectively, the Agencies) “Plan Bay Area” and its EIR, finding the opponent’s arguments failed because they were based on a misinterpretation of SB 375’s requirements.

SB 375 requires the Board to provide greenhouse gas emissions reduction targets to each region while taking into account statewide mandates such as the Low Carbon Fuel Standard and the New Vehicle Emissions Standards. Then, each regional metropolitan planning organization (MPO) must prepare a sustainable communities strategy to meet those targets. The Agencies prepared Plan Bay Area. The petitioners commented on the Plan’s EIR stating that the Agencies should have counted reductions expected from preexisting statewide mandates. When the Board’s staff conducted a technical review of the Plan, however, they stated that the Agencies had appropriately excluded greenhouse gas emissions reductions from other technology and fuel programs. The Board then issued an executive order with the staff’s technical report attached, accepting that Plan Bay Area, if implemented, would achieve the targets.

The petitioners alleged that the Agencies failed to comply with CEQA by incorrectly assuming that SB 375 compelled them to exclude compliance with statewide mandates when assessing strategies to meet emissions reductions targets. First, the court looked to the plain meaning and purpose of the statute and found that because the emissions reductions from the statewide mandates are projected to dwarf those achieved by SB 375, the whole statute would be superfluous if the MPOs were simply allowed to cite the expected reductions from preexisting initiatives. Further, the Board’s AB 32 Scoping Plan repeatedly emphasized that the regional land use and transportation strategies were distinct from the statewide mandates. Although the Board was required to take the statewide mandates into account when setting targets under SB 375, the statute did not require any specific approach and the board had discretion to instruct MPOs to exclude consideration of reductions expected from statewide mandates. The Board made this instruction clear when it approved of Plan Bay Area with the exclusion of reductions from statewide mandates.

On the alleged inadequacy of the Plan’s EIR, the court stated that the petitioner’s arguments were based on their misinterpretation of SB 375 and found the EIR adequate. The Agencies were not required to consider the appellants proposed alternative that relied on statewide mandates because, as discussed above, it did not comply with SB 375 and was therefore infeasible. Contrary to the appellants’ contentions, the EIR did not ignore statewide mandates. Consideration of the New Vehicle Emissions Standards and the Low Carbon Fuel standard were included when determining whether implementation of the Plan would result in a net increase in emissions and whether it would impede the goals of AB 32. Further, the court found that in light of the Agencies’ sufficient disclosures throughout the EIR, including when they did and did not consider statewide mandates, the appellant’s arguments amounted to an impermissible substantive attack on the plan.

Written by Sabrina S. Eshaghi

Fourth District Court of Appeal Upholds Supplemental EIR for Jail Facility Upgrade Project

City of Irvine v. County of Orange (July 6, 2015) __ Cal.App.4th __, Case No. G049527

The court upheld a Supplemental EIR prepared by the County of Orange for a jail upgrade project over a decade after the original EIR had been certified. The court found the project was not substantially different than the project analyzed in the original EIR and that the Supplemental EIR adequately addressed the minor project changes and changed circumstances. And after a hearty dissertation on CEQA’s responses to comments requirement, the court determined that the county’s responses to comments on the Supplemental EIR were adequate.

The county prepared an EIR in the 1990s for the expansion of the James A. Musick Jail Facility. The City of Irvine challenged that EIR and lost; however, project construction was delayed indefinitely by a lack of funding. In 2012, the county decided to move forward with the project and prepared a Supplemental EIR to account for project changes and changed circumstances. Irvine filed a petition challenging the Supplemental EIR on various CEQA grounds. The trial court rejected the challenge and Irvine appealed.

On appeal, Irvine first claimed that the County was required to prepare a “Subsequent EIR” rather than a “Supplemental EIR.” Regarding the Supplemental EIR, Irvine’s contentions focused primarily on traffic impacts during construction and the loss of agricultural land. Irvine’s main argument, however, was that the county’s responses to Irvine’s comments on the Supplemental EIR were inadequate. The court rejected each of these claims in turn.

Irvine’s first claim was that the County was obligated to prepare a Subsequent EIR as opposed to a Supplemental EIR for their analysis of the impacts of the expansion. The court rejected this claim, explaining that courts should look to the substance of the EIR, not its nominal title.

Irvine’s next argument concerned the Supplemental EIR’s analysis of traffic impacts during project construction. Due to delays, there were discrepancies in the county’s construction timeline. Irvine claimed that these discrepancies amounted to an unstable project description that prevented the Supplemental EIR from adequately assessing project impacts. The court disagreed, finding that the project description was distinct from the interim impacts of construction. Specifically, Irvine claimed the county had failed to provide a stable project description because it could not account for the traffic impacts caused by construction in a given year. The court found that CEQA does not require a continuous update of traffic impacts as a result of construction delays and that, regardless of the delay, the impacts would not be substantially different from those disclosed in the Supplemental EIR even if traffic data was updated, and therefore, there was no prejudice.

The third claim concerned mitigation for the loss of agricultural land that would occur as a result of the expansion. The Supplemental EIR discussed seven possible mitigation measures, but none were found to be feasible. Irvine challenged the county’s feasibility findings for three of the measures: (1) the purchase of conservation easements on existing agricultural land to prevent it from being used in the future for nonagricultural purposes, (2) a transfer of development rights program, and (3) a “right to farm” ordinance.

The court held that the county’s findings rejecting these measures as infeasible were supported by substantial evidence. Conservation easements were found infeasible because there was no additional land for agriculture in the county that would be profitable and putting a conservation easement for agricultural use on land that is already used for agriculture would do nothing to mitigate the loss of other agricultural lands. The court also noted that the county’s zoning laws did not support the feasibility of conservation easements. Transfers of development rights were found to be even less feasible because the county did not have land laying fallow for which they could transfer rights in the preservation of agricultural land use. Lastly, the court concluded that a right to farm ordinance was the least viable option of all. The Supplemental EIR recognized that the conversion of current non-agricultural land to agricultural land would itself entail significant environmental effects, including nuisance suits. Beyond that, the court noted, a right-to-farm ordinance is meaningless where no land owner wants to farm. The court held that it is a reasonable inference that no one would want to convert land that is currently non-agricultural and put it to agricultural use even if they have the ostensible legal right to do so.

Lastly, the court addressed Irvine’s claim that the county failed to adequately respond to comments. The court began with a thorough discussion of CEQA’s responses to comment requirement and a detailed assessment of the state of case law on the subject. The court noted several oft-repeated principles by which courts may evaluate the sufficiency of responses, including (1) a general comment can be adequately met with a general response; (2) responses need not be exhaustive; and (3) the sufficiency of responses should be “viewed in light of what is reasonably feasible.” From the cases, the court divined a few more basic standards for the adequacy of responses: (1) when a comment raises a “significant” environmental issue, there must be some genuine confrontation with the issue, it can’t be swept under the rug; (2) responses that leave big gaps in the analysis of environmental impacts are obviously inadequate; (3) comments that bring some new issue to the table need genuine confrontation; and (4) comments that are only objections to the merits of the project itself may be addressed with cursory responses. Based on these guiding principles, the court found that the county had adequately responded to each of Irvine’s comments that merited a response.