Tag: Endangered Species Act

Petition for Writ of Certiorari Submitted to the U.S. Supreme Court Contesting the Ninth Circuit’s Decision Upholding USFWS’s Biological Opinion on Delta Smelt

Under the Endangered Species Act (ESA), if the Secretary of the Interior concludes that a federal agency action will jeopardize a species listed as threatened or endangered, then the Secretary must use the best scientific and commercial data available to identify reasonable and prudent alternatives that are economically and technologically feasible. Petitioners in State Water Contractors v. Jewell presented the U.S. Supreme Court with the following questions related to the Act’s directive: 1) Must the Secretary address in the administrative record the economic and technical feasibility of proposed “reasonable and prudent alternative,” including the effects of the proposed alternatives on third parties? 2) May the Secretary disregard the “best scientific data” on the ground that considering the data would lead to a less “conservative” result, because scientific certainty is impossible, or because the Secretary has considered a range of data in reaching a conclusion?

This case arose after the U.S. Fish and Wildlife Service (FWS) issued a Biological Opinion (BiOp) in 2005 which found that operation of the state’s two largest water projects, the State Water Project and the Central Valley Project, threatened the delta smelt, and thereby curtailed those projects’ operations. The district court found major flaws with the BiOp and ordered FWS to reconsider it, but the Ninth Circuit reversed. The appellate court held that FWS was precluded as a matter of law from considering the economic effects of its proposed restrictions on project operations on Californians. The court also excused FWS’s failure to use the best available scientific data in formulating its opinion. Petitioners argued that the Ninth Circuit’s decision exacerbated the harmful effects of California’s drought, created circuit splits, and contravened the Supreme Court’s precedents.

The BiOp, which the appellate court described as “a big bit of a mess,” concluded that unless the quality and quantity of the delta smelt habitat improved, the smelt would not recover from their downward population trend. The BiOp specified various actions as reasonable and prudent alternatives (RPAs) to the status quo, including limiting the amount of water the projects could pump for certain uses. Petitioners claimed that the amount of water sacrificed to implement the RPAs could have met the needs of over one million households for a year, or irrigated two hundred thousand acres of farmland.

District Court decision

Petitioners brought suit alleging the BiOp violated NEPA, the ESA, and the Administrative Procedure Act. The district court held the BiOp invalid. First, it found FWS had failed to establish that its RPAs met the requirements for a reasonable and prudent alternative under 50 C.F.R. section 402.02, including the requirement that the proposed restrictions be economically and technologically feasible. The court also held that the analyses supporting the specific flow prescriptions set forth in the RPA were fatally flawed and predominantly unsupported, given that 1) FWS failed to use the best available science in calculating flow rates to reduce the number of fish drawn into the pumping stations and 2) the BiOp adopted a flawed methodology to set limits on salinity in the Delta in the autumn of years categorized as above-normal or wet. The court found the agency’s decision “was arbitrary and capricious and ignored the best available science showing that a bias was present.”

Ninth Circuit decision

In a divided panel, the Ninth Circuit reversed. The majority agreed with FWS that the agency was not required to explain why its proposed RPAs met the feasibility standard set forth in the agency’s own regulations. The court also upheld FWS’s decision to use raw salvage data, concluding that normalized data was not tailored to protect the maximum absolute number of individual smelt, as the BiOp’s approach was. The court noted that although ideally FWS would have discussed its reasoning in using that data, the agency’s choice was entitled to deference. One judge sitting by designation from the Eighth Circuit dissented, arguing that because the concerns relating to the RPAs’ feasibility had been raised, FWS was required to at least address those concerns in the BiOp or in the administrative record. The dissent also argued that FWS had failed to use the best available science. The dissent also concluded that the agency’s means of determining where in the Delta the salinity reaches two parts per thousand was arbitrary and capricious, and disagreed with the majority’s decision to ignore the expert witnesses.

Argument for granting the writ

Petitioners described the issues presented as ones of “exceptional national importance.” They argued cert is warranted to resolve a circuit conflict over whether a consulting agency must consider the effects on third parties when proposing reasonable and prudent alternatives to agency action. Furthermore, petitioners noted, whether the ESA requires or precludes an agency from considering the economic impact of its proposed restrictions on agency activity on third parties is a question of recurring importance, given the fact that the federal government conducts thousands of ESA consultations every year. Petitioners argued, that, contrary to the Ninth Circuit’s interpretation, the presence of the feasibility requirement in the definition section of the regulations made the requirement more central to the agency’s obligation of reasoned explanation than it would if the requirement appeared elsewhere. By failing to consider feasibility, petitioners stated, FWS entirely failed to consider an important aspect of the problem, and therefore acted arbitrarily and capriciously. This would not mean that an RPA requirement authorizes FWS to balance the life of delta smelt against the impact of restrictions on project operations; but in choosing among possible alternatives that would avoid jeopardy, an agency would be required to consider the impact of the various effective alternatives on third parties, “in order to avoid unnecessary harm to humans in the course of protecting plants and animals.”

Second District Court of Appeal Holds EIR/EIS for the Newhall Ranch Resource Management and Development Plan and Spineflower Conservation Plan Complies with CEQA

In Center for Biological Diversity v. Department of Fish and Wildlife (Mar. 20, 2014) ___ Cal.App. ___, Case No. B245131, the Second Appellate District reversed the trial court judgment granting a petition for writ of mandate challenging the California Department of Fish and Wildlife’s (Department) approval of the Newhall Ranch Resource Management and Development Plan and Spineflower Conservation Plan. In the published portion of its opinion, the court held that the provisions of the Fish and Game Code supported a determination that live trapping and transplantation of a protected species of fish does not constitute an unlawful taking when undertaken by the Department for conservation purposes. The court also found the Environmental Impact Report’s analysis of cultural resources, alternatives, impacts to Steelhead smolt, and impacts to spineflower complied with CEQA.

The Newhall Land and Farming Company proposed an almost 12,000-acre Specific Plan area approved by Los Angeles County in 2003 and to be built out over a number of years. After the local county approved an environmental impact statement for the proposed development, the Department prepared and certified an EIR for the project—a Resource Management and Development Plan and Spineflower Conservation Plan. The EIR analyzed the potential environmental effects of issuing incidental take permits and a streambed alteration agreement under the project. The construction of the project would impact, among other things, the stickleback, a fish protected under Fish & Game Code §5515(a)(1) as a “fully protected species.”

The Center for Biological Diversity filed a petition for writ of mandate challenging the Department’s actions. The trial court granted the writ petition, finding, among other things, that the department failed to prevent the taking of the stickleback. The Department and the developer appealed. The court of appeal reversed, holding that the trial court erred in granting the petition.

The court found substantial evidence supported the Department’s conclusion that no take of the stickleback would occur. The court found that the EIR contained mitigation measures to exclude stickleback from any construction areas in the river and to trap and relocate any stranded stickleback to other parts of the river in temporary containers. The court found substantial evidence supported a determination that no mortality would occur given the extraordinary measures taken by the Department to ensure the sticklebacks’ safety, including undertaking surveys of stickleback habitat prior to developing its plan, preparation of ten different studies, and employing the expertise of one of the leading authorities on stickleback preservation. The extensive mitigation measures, coupled with the expert’s discussion, constituted substantial evidence no deaths would result.

The court also rejected CBD’s contention that the mitigation measures themselves would constitute a taking prohibited by Fish and Game Code §§86 and 5515(a)(1). Those sections defined a prohibited take as the “catch, capture, or kill” of protected fish. After a thorough review of pertinent sections of the code, along with their legislative histories, the court agreed with the Department and developer that the use of live trapping and transplantation techniques approved in Fish and Game Code §2061 would not constitute a prohibited take or possession. The court reasoned the entire statutory scheme must be construed together and section 2061 allows for live trapping and transplantation when performed for conservation purposes. Such techniques, as explained by the Department’s expert, can involve the possession and movement of the stickleback in containers to parts of the river that would not be impacted by construction. Therefore, the court concluded the mitigation measures would not result in an unlawful take or possession of stickleback.

The court also rejected CBD’s claims that the EIR failed to adequately address the cultural resources impacts of the project. As an initial matter, the court found CBD had forfeited its cultural resources claims by failing to raise such issues during the public comment period. As a result, the court held CBD failed to exhaust administrative remedies and Department had no obligation to respond to untimely comments. Though finding the claims waived, the court addressed these claims on the merits and rejected them, finding the cultural resource analysis was supported by substantial evidence. The analysis in the EIR was based on extensive research, surveys, and studies performed by consultants with expertise in the field. The consultants undertook excavations of areas that the research and studies indicated resources might be present. Furthermore, the court found there was no evidence that the consultant have failed to uncover any human remains. Though human remains had been found near the project site, the court found that those earlier, off-site discoveries did not require the Department to conduct additional plug tests on site to confirm the consultant’s conclusion. The court also upheld the cultural resources mitigation measures set forth in the EIR as adequate and in full compliance with CEQA Guidelines §15126.4(b)(3)(A).

The court rejected CBD’s claim that the Department’s determination regarding the feasibility of one of the alternatives was not supported by substantial evidence. The court found that, in general, the alternatives were appropriate because they were required to follow the Newhall Ranch Specific Plan. In considering the objectives of the specific plan, the alternative in question would not meet the project objectives to provide a new major community with industrial, commercial, and residential uses because the alternative lacked commercial uses in one planning area and had no connectivity to the easternmost portion of the project area. Furthermore, the alternative was economically infeasible based on application of an industry metric of the cost per developable acre compared to the proposed project. The court upheld this methodology and found substantial evidence supported the Department’s determination regarding the infeasibility of the alternative.

The court rejected CBD’s claims that the EIR failed to address the potential effects on steelhead smolt downstream of the project area due to dissolved copper discharges.  Again, the court found CBD had forfeited its claims for failing to raise them during the public comment period. Though waived, the court addressed the claims and found that there were no steelhead smolt in the project area because the habitat would be below the dry gap where the river goes underground. Furthermore, the dissolved copper discharged to the river would be below the California Toxics Rule Threshold with compliance with regulatory requirements and implementation of mitigation measures and design features. The court found substantial evidence supported the Department’s determination that the project’s impacts on steelhead smolt would be less than significant.

The court rejected CBD’s claims of flaws in the EIR’s analysis of impacts to the San Fernando Valley spineflower, which is listed as endangered under the California Endangered Species Act (CESA) and is known to occur only in the project area and one other location in Ventura County.  The Department issued an incidental take permit for spineflower, allowing take of 24% of the habitat within the Specific Plan area. The court found substantial evidence supported the mitigation plan for the spineflower. The Department had employed 43 biologists who conducted 21 surveys to identify the potential spineflower habitat. The Conservation Plan would dramatically expand the area for potential growth of the spineflower: from 13.88 acres of growth to 56.79 acres of core growth, 110.77 acres of buffer and 42.90 acres of expansion areas. The Plan would ultimately increase the preserve areas from two to five. The court also found that Department’s comprehensive monitoring plan did not constitute impermissible deferral of mitigation, but rather called for future research, which represented “sound ecological management.”

In an unpublished portion of the opinion, the court upheld the EIR’s greenhouse gas analysis. The Department employed a significance threshold for greenhouse gas emissions premised on the reduction target established under the California Global Warming Solutions Act (AB 32) where GHG emissions would be significant if the project would impede achievement of a reduction in statewide GHG emissions to 1990 levels by 2020.  The court held the Department had discretion to employ this threshold and concluded the threshold was appropriate.  The court found the GHG analysis complied with CEQA because it was consistent with the requirements for such analysis set forth in CEQA Guidelines §15064.4(b)(1)-(3) and was supported by substantial evidence.

USFWS Extends Eagle Take Permits to 30 Years

The U.S. Fish and Wildlife Service extended the maximum term for programmatic “take” permits under the Bald and Golden Eagle Protection Act to 30 years. This means that renewable energy project developers – particularly wind project developers – can apply for permits that authorize recurring “take” (i.e., disturbance or killing) of eagles that is unavoidable even with mitigation. The rule eclipses the five-year limit on programmatic take permits instituted in 2009.

The act prohibits the “take” of bald and golden eagles, their nests, or eggs, unless allowed by permit; specifically, one cannot “pursue, shoot at, poison, wound, kill, capture, trap, collect, molest or disturb” the eagles without permission. Wind energy projects can result in accidental takes when eagles fly into the windmill blades. While most project developers implement measures to direct eagles away from the blades, such as by attracting the birds to reflective material above the blades and locating the projects in less-populated zones, some takes are unavoidable even with such mitigation.

Until now, many developers opted not to apply for programmatic take permits, given the inefficiency of the permit’s five-year duration compared to the decades-long timeframe of renewable energy project operations. Instead, developers would either apply for standard permits, which authorize individual takes, or not apply for any permits. The new regulations do not change the fact that project developers are not legally required to apply for take permits before proceeding with their projects. The downside to this approach, however, is that a developer faces civil and criminal penalties for unpermitted takes done “knowingly” or with “wanton disregard.”

Although the permits can now extend up to 30 years, the length of each permit will depend on the characteristics of the projects, such as the project’s duration and the projected impacts to eagles. Additionally, permits issued for longer than a five-year period will undergo evaluations every five years to assess fatality rates, conservation and mitigation effectiveness, and eagle population levels. Applicants for these longer permits are also required to commit to adaptive management, which involves system monitoring with the goal of continually understanding and improving a project’s effect on eagles.

The issuance of a take permit is a federal action requiring compliance with the National Environmental Policy Act, meaning applicants must prepare an environmental assessment or an environmental impact statement in order to obtain a permit. The rule went into effect on January 8, 2014.

Decision to List Polar Bear as Threatened Species under the Endangered Species Act Affirmed.

On March 1, 2013, the D.C. Circuit Court of Appeals upheld the listing of the polar bear as a threatened species under the federal Endangered Species Act.

The U.S. Fish and Wildlife Service listed the polar bear as threatened in 2008 because of shrinking sea-ice habitat. Industry groups challenged the listing determination under the Administrative Procedure Act’s “arbitrary and capricious” standard, arguing that the agency failed to establish a foreseeable extinction risk.  Environmental groups challenged the listing as insufficiently protective, arguing that the polar bear should be listed as endangered.

The District Court rejected all challenges on summary judgment, finding that the claims “amount to nothing more than competing views about policy and science” and therefore the agency receives deference.

The Court of Appeals emphasized that “a court is not to substitute its judgment for that of the agency”. The Court further noted, “The Listing Rule is the product of FWS’s careful and comprehensive study and analysis. Its scientific conclusions are amply supported by data and well within the mainstream on climate science and polar bear biology.”

The opinion is a win for both federal and state agencies that routinely base administrative decisions on scientific modeling and other complex data.