Tag: Mitigated Negative Declaration

Third District Holds Order Requiring a Limited EIR Is Not an Appropriate Remedy Where a Project May Have Significant Impacts

In the published portions of Farmland Protection Alliance v. County of Yolo (2021) 71 Cal.App.5th 300, the Third District Court of Appeal held that a limited environmental impact report (“EIR”) is not an appropriate remedy where a court finds that substantial evidence supports a fair argument that the project might have a significant environmental impact.

Background

The Yolo County Board of Supervisors adopted a mitigated negative declaration and issued a conditional use permit for a bed and breakfast and commercial event facility on agriculturally-zoned property. Project opponents filed a lawsuit alleging, among other claims, that the MND was inadequate under CEQA. The trial court rejected most of petitioners’ claims but found substantial evidence supported a fair argument that the project may have a significant impact on three special-status species, and as the remedy, (1) ordered the County to prepare a limited EIR addressing only the project’s impacts on the three species, and (2) allowed the project to continue operations pending further environmental review.

Petitioners appealed the trial court’s decision, arguing that the court violated CEQA by ordering preparation of a limited EIR after its finding of potentially significant impacts, and allowing the project to continue operating while further environmental review was pending.

The Court of Appeal’s Decision

The Court of Appeal held that Public Resources Code section 21168.9 does not authorize a court to split a project’s environmental review across two types of documents, such as a negative declaration or mitigated negative declaration and an EIR. The court noted that while section 21168.9 is designed to provide a trial court with flexibility in crafting remedies to ensure compliance with CEQA, it does not authorize a court to circumvent CEQA’s mandatory provisions. According to the court, CEQA requires an agency to prepare a full EIR when substantial evidence supports a fair argument that any aspect of the project may have a significant effect on the environment. The Court of Appeal therefore found that the trial court erred by ordering preparation of a limited EIR after finding the fair argument test had been met as to impacts to the three species.

The Court of Appeal declined to consider petitioners’ argument that the trial court erred in allowing the project to operate while the limited EIR was being prepared. While the appeal was pending, the County filed a return to the peremptory writ of mandate stating the limited EIR ordered by the trial court had been certified.  As a result, the Court of Appeal determined the portion of the judgment allowing the project to continue to operate no longer had any effect, and therefore, the issue was moot.

Fourth District Court of Appeal upholds determination that one group of utilities undergrounding projects is exempt from CEQA because of petitioner’s failure to exhaust, but remands for further consideration of GHG impacts from second group of utilities undergrounding projects

In a procedurally complicated holding, in McCann v. City of San Diego (2021) 70 Cal.App.5th 51,the Fourth District Court of Appeal upheld the trial court’s ruling on the City of San Diego’s determination that one set of utilities undergrounding districts is exempt from CEQA, but remanded for further analysis of another set of utilities undergrounding districts to determine whether the project’s greenhouse gas (GHG) emissions are consistent with the City’s Climate Action Plan (CAP).

Background

The City of San Diego adopted a Utilities Undergrounding Program Master Plan in 2017, which sets out a process by which the City is converting overhead utility wires to an underground system. Undergrounding includes digging tunnels or trenches, installing underground conduit, filling in the soil, and pulling cable through the conduit. In addition, the City installs new above-ground transformers, three-foot cube-shaped cable boxes, and pedestals. The Master Plan and the City’s Municipal Code divide the larger effort to convert the entire above-ground utility system into smaller “districts,” each of which the City considers and approves separately.

Margaret McCann, a property owner, challenged the City’s approval of two sets of districts. The first set, City staff determined, was exempt from CEQA pursuant to Guidelines section 15302, subdivision (d). For the second set, the City adopted a mitigated negative declaration (MND).

The exempt districts

City staff determined that the first set of districts is exempt from CEQA. The City posted a Notice of Right to Appeal Environmental Determination in its City Development Services Department Office and on its website, and emailed the notice to City Councilmembers and local community planning groups. The notice stated that the exemption determination was appealable to the City Council within ten days. No one appealed. The City Council subsequently mailed notice of a public hearing regarding the districts to affected property owners, including McCann. McCann emailed the City and indicated that she had not seen the Notice of Right to Appeal, and that she believed the environmental review was inadequate. Her attorney also spoke at the Council hearing. The City Council subsequently approved the projects and the City filed a Notice of Exemption.

The MND districts

Separately, the City published a draft MND for another set of undergrounding districts, because some of them included sites with cultural significance. The MND also considered potential aesthetic and GHG effects from the projects. McCann and her attorney submitted written comments disputing the adequacy of the MND, and McCann’s attorney spoke at the public hearing. The City Council adopted the MND and approved the undergrounding districts.

Trial court decision

McCann filed a petition challenging both the exempt districts and the MND districts. The trial court denied the petition in its entirety. With respect to the exempt projects, the trial court found that McCann failed to exhaust administrative remedies, and in the alternative, denied her claims outright. Regarding the MND projects, the trial court found that McCann failed to demonstrate that substantial evidence supported a fair argument that the projects may have a significant effect on the environment.

The Court of Appeal’s Decision

The Court of Appeal agreed with the trial court, with one exception. First, with respect to the exempt projects, the court explained that CEQA does not prescribe a specific appeal process following a determination that a project is exempt. But, the court said, CEQA does require that if a nonelected official or decisionmaking body determines that a project is exempt, the agency must allow for an appeal of that determination to the decisionmaking body. Here, the City provided an administrative appeal process, but McCann did not file a timely appeal pursuant to the City’s procedures. McCann argued that City staff’s exemption determination did not comply with due process principles, but the court disagreed because the determination was not a land use decision and did not deprive McCann of any significant property interest. As a result, the court concluded, McCann failed to exhaust her administrative remedies, barring her claims with respect to the exempt projects.

Second, with respect to the MND projects, the Court of Appeal rejected all but one of McCann’s arguments. McCann argued that the City improperly segmented the projects; the court disagreed because each utility underground district is independently functional and does not rely on other districts to operate, and no set of districts is the “first step” toward any other projects. McCann argued that the project description was inadequate because it did not identify the precise locations of above-ground transformer boxes; the court disagreed because regardless of the precise location of each transformer, the environmental impacts of the project are the same. McCann argued that the MND projects will have significant aesthetic effects on the environment; the court disagreed because McCann failed to meet her burden to identify substantial evidence in the record that the project might have significant impacts. Most of McCann’s arguments, the court said, revolved around her neighborhood, which falls under the exempt projects, not the MND projects. McCann also cited to testimony of a person who commented on the project, but the court concluded that stray comments or expressions of concern related to aesthetic impacts are not enough to constitute substantial evidence.

The Court of Appeal remanded to the trial court on one narrow issue–the City’s determination that GHG impacts are not significant. Interestingly, the court explained that it was not holding that McCann proved that substantial evidence supported a fair argument that the project might have significant GHG impacts, which is usually the standard of review applied by the courts when considering an MND. Instead, the court said that because the City relied on an inapplicable checklist to conclude that the project was consistent with the City’s CAP, the City’s conclusions were not supported by substantial evidence.

To determine whether the project is consistent with the CAP, the City looked to its “Climate Action Plan Consistency Checklist.” The checklist directs staff to first consider whether a project is consistent with the City’s land use and zoning regulations. If yes, staff must then move to step two. But the checklist explains that step two does not apply to projects that, like this one, do not require a certificate of occupancy. Because step two does not apply, the City concluded that the project was consistent with the CAP. The court found, though, that the City could not rely on a checklist which expressly states that it does not apply to projects like this one to make a consistency determination. Thus, the court concluded, the City never considered whether the MND projects are consistent with the CAP. The court clarified that the use of a checklist to determine consistency might still be appropriate; the City could amend the checklist to include a step for assessing infrastructure projects, or it could create a separate checklist entirely. Without such a checklist though, the City was required to consider whether the projects comply with each individual action identified in the CAP if it wished to rely on streamlined review of GHG impacts.

The Court of Appeal reversed the trial court’s judgment on this limited issue, with directions to the trial court to enter a new judgment granting the petition in part, and to issue a peremptory writ of mandate directing the City to set aside its adoption of the MND and approval of the project.

THIRD DISTRICT COURT OF APPEAL DISMISSES PETITIONERS’ CHALLENGE TO A MITIGATED NEGATIVE DECLARATION BECAUSE THE CLAIMS DID NOT ESTABLISH A FAIR ARGUMENT OF SIGNIFICANT ENVIRONMENTAL IMPACTS.

In Newtown Preservation Society v. County of El Dorado (2021) 65 Cal.App.5th 771, the Third District Court of Appeal affirmed the trial court’s decision to uphold El Dorado County’s adoption of a mitigated negative declaration (MND) for a bridge replacement project. In the published portions of the opinion, the court held that Petitioners failed to establish a “fair argument” that the project would have significant environmental impacts. Instead, Petitioners raised concerns regarding existing wildfire hazards that could impact residents near the project, but did not establish that the project may significantly impact the environment by creating or exacerbating wildfire hazards.

Factual and Procedural Background

The County, in preparing the MND, determined that the bridge replacement project could interfere with emergency response or evacuation plans and—as a result—expose people or structures to risk of loss or injury. However, the County also determined that these impacts would not be significant since a temporary evacuation route would be constructed to mitigate the risk. Such a route would only be used for emergency evacuation and, regardless of whether it was in place, any evacuation or emergency orders would be executed as the El Dorado County Sheriff’s Office of Emergency Services saw fit. Additionally, the County consulted with this office as well as the El Dorado County Fire Protection District in preparing the MND and both entities were comfortable with the document’s conclusions and assessments.

The County initially refrained from discussing the temporary evacuation route in detail in its mitigated negative declaration since it was concerned this would “lead people to believe that they should follow a certain evacuation route.” But, as a result of comments raised by one of the petitioners’ counsel and others regarding the possibility of a temporary evacuation route, the County’s responses to comments elucidated its plans and evacuation procedures in greater detail. It outlined several evacuation options given numerous emergency conditions depending on whether the temporary evacuation route was constructed.

After the County adopted the MND, Petitioners filed a writ a mandate, claiming the County failed to 1) properly consider the no-project alternative and 2) “adequately address the impact of closing the bridge without committing to construction of an evacuation route.” Petitioners claimed there was sufficient evidence in the record—including letters, correspondences, and hearing comments—supporting a fair argument that the bridge replacement project would significantly impact public safety. For example, a resident who lived on Newtown Road discussed past fire damage near her home; another resident complained that the County had not determined with finality whether a temporary route would be constructed; and another expressed concern about the effects of wind in the area on fire management; an aerial firefighter argued that recent history of wildfires demonstrated the danger in the County’s temporary evacuation route plans; Ms. Nagel, one of the petitioners, discussed her extensive firefighting experience; and Ms. Nagel’s attorney argued that the County’s MND violated CEQA by deferring important emergency management analysis.

The trial court, however, found that none of the petitioners’ arguments constituted substantial evidence, especially in light of explanatory testimony and responses to comments by the County and its experts, as well as the detailed evacuation options outlined in the MND. Instead, Petitioners’ letters and comments amounted to mere complaints and fears, backed up by speculation and unsubstantiated, non-expert opinion.

The Court of Appeal’s Decision

On appeal, Petitioners argued that the trial court erred in upholding the MND since “substantial evidence supports a fair argument of potentially significant impacts on resident safety and emergency evacuation.” The court noted that evidence supporting a fair argument can be substantial even though other equally compelling evidence may exist to the contrary. Still, the court concluded that Petitioners’ “framing of the fair argument test [was] erroneous. The question is not whether substantial evidence supports a fair argument that the proposed project will have significant impacts on resident safety and emergency evacuation. . . . [T]he question is whether the project may have a significant effect on the environment.” Yet Petitioners failed to identify any potentially significant effects the project might have on the environment and instead merely raised possible increased effects the environment might have on the community as a result of poorer evacuation procedures.

Furthermore, the Court of Appeal, like the trial court, pointed out that substantial evidence must be based on relevant information and facts; or at least reasonable inferences, assumptions, or expert opinion supported by facts. Unsubstantiated opinions, arguments, or speculations generally will not do. The court noted, however, that lay opinion may be considered substantial evidence where expertise is not necessary, which was not the case with the emergency evacuation issues raised by the Petitioners. The Court of Appeal explained again that Petitioners’ cited comments and letters were “mere speculation” and simply “dire predictions by nonexperts” and that they “fail[ed] to identify any factual foundation” for their assertions. Some comments were even directly contradicted by factual evidence in the record. Nowhere did Petitioners establish that any of the individuals whose testimony was cited were experts in evacuation planning. Thus, the court concluded that Petitioners’ claims did not constitute substantial evidence supporting a fair argument that the project may have a significant impact on the environment.

– Blake C. Hyde

Second District Court of Appeal Upholds Ruling that Mitigation Measures are Inadequate and EIR is Required for Mixed-Use Development Project in Agoura Hills

On February 24, 2020, the Second Appellate District in Save the Agoura Cornell Knoll et al. v. City of Agoura Hills et al. (2020) 46 Cal.App.5th 665 affirmed the trial court’s decision to require an EIR instead of an MND for a mixed-use development on 8.2 acres because the adopted mitigation measures deferred action, lacked performance criteria, and/or were otherwise inadequate.

Background

The “Cornerstone Mixed-Use Project,” proposed by Agoura and Cornell Roads, LP, and Doron Gelfand (“Appellants”), consists of 8.2 acres of development, including 35 residential apartment units, retail, a restaurant, and office space on an undeveloped hillside in the City of Agoura Hills. The project site is covered mostly by the Agoura Village Specific Plan (adopted in 2008 after its final EIR was certified) with a small portion located within a Significant Ecological Area. After Appellants submitted applications for a development permit, conditional use permit, oak tree permit, and tentative parcel map, the City prepared and finalized an MND for the project in November 2016. The Planning Commission voted to approve the project and adopt the MND. The local chapter of the California Native Plant Society (CNPS) appealed the Planning Commission’s decision, but the City Council approved the project and adopted the MND. The City Council found “no substantial evidence that the project would have a significant effect on the environment” because the project included feasible mitigation measures, reducing all effects to less than significant.

Save the Agoura Cornell Knoll filed a petition for writ of mandate followed by a first amended petition on August 10, 2017, adding CNPS as a petitioner (“Petitioners”), alleging multiple CEQA violations, a violation of planning and zoning law, and a violation of the City’s oak tree ordinance. The trial court granted the petition as to the CEQA and oak tree ordinance claims, denied the planning and zoning law claim, and issued a peremptory writ of mandate directing the City to set aside its project and permit approvals, and to set aside the MND to make way for preparation of an EIR. The project applicants appealed.

The Court of Appeal’s CEQA Decision

The Court reviewed Appellants’ claims under the “fair argument” standard, which requires finding that a lead agency abused their discretion if substantial evidence in the record supports a fair argument that that the project may have a significant effect on the environment. This standard creates a relatively low threshold for requiring an EIR pursuant to “‘legislative preference for resolving doubts in favor of environmental review.’” Three CEQA resource areas were litigated—cultural, biological, and aesthetic. Appellants asserted, repeatedly, that mitigation was adequate and an EIR was not required, and the Court repeatedly disagreed. Overall, the Court found that certain mitigation measures set forth in the MND were “not feasible,” “improperly defer[] mitigation,” or were “inadequate to mitigate the project’s potentially significant impacts.” Affected resource areas are briefly discussed below.

Cultural Resources

The project site contains an identified prehistoric archaeological site that was previously determined to be eligible for inclusion in the California Register of Historical Resources. Three mitigation measures were included in the MND to address potential impacts to the site: (1) construction monitoring, notification of finds, and preservation in place of any resources (i.e., avoidance); (2) notification if human remains are encountered; and (3) a data-recovery excavation program if the site cannot be avoided. The Court found this mitigation constituted improper deferral because, pursuant to an expert opinion on the record, the site could not be avoided as prescribed in the first measure without a project redesign and therefore the third measure would be necessary. The Court also found that the third measure delayed “formulation of several components of the data recovery plan until some future time.” For example, the third measure called for the preparation of a Mitigation Monitoring and Reporting Plan (MMRP), yet did not explain how this MMRP would actually mitigate impacts, and there was no evidence in the record that inclusion of such information was impractical or infeasible prior to project approval. Appellants challenged the “evidentiary value” of the expert opinion, but the Court noted that any “conflict in the evidence” should be resolved in an EIR and that there was no debate as to whether the project would have a significant effect on a cultural resource, just on how it might be mitigated.

Biological Resources

The project site contains three special-status plant species that could be significantly impacted by project grading, landscaping, and fuel modification activities: Agoura Hills Dudley, Lyon’s pentachaeta, and Ojai navarretia. Again, three mitigation measures were included in the MND to reduce impact significance: (1) avoidance if feasible for two of the species, but if not, preparation of a restoration plan that includes plant surveys, onsite restoration, and offsite preservation; (2) the same measure for the third species; and (3) locating and flagging of all three species within the fuel modification zone and the use of buffers, other protocols, and monitoring for protection. The Court found the first two measures inadequately mitigated impacts and were infeasible, largely because of statements on the record asserting that restoration of “‘rare plants is next to impossible’” and “‘experimental’” and because the City relied on outdated surveys conducted during the drought in adopting the measure. The measures called for updated surveys but the record provided no evidence as to why such surveys could not be conducted prior to project approval. The measures also failed to provide performance criteria for determining the feasibility of avoidance or in the alternative, maintenance plans. The third measure was found to be inadequate because it did not properly consider the full expanse of fuel modification zones nor did it account for ongoing fuel modification activities, as it applied only to construction.

The project site also contains native oak trees, 35 of which would be removed by the project. Two mitigation measures were included in the MND to reduce significant impacts: (1) replacement of oak trees either onsite or via in-lieu fees paid to the City to acquire land for new tress; and (2) submittal of an oak tree survey, report, and preservation program to the City for approval. The Court found the first measure to be inadequate because mass grading required for the project would cause a loss of subsurface water to any onsite replacement trees, which could result in failure; yet this water deficit was not addressed in the measure. Also, substantial evidence existed showing that oak woodlands are “‘impossible to recreate’” or at least “‘often unsuccessful.’” Lastly this measure was inadequate because the in-lieu fees to be paid to the City would not be not part of a program that has undergone its own CEQA review, which is required “‘to provide a lawful substitute for the “traditional” method of mitigating CEQA impacts.’” The second mitigation measure was found to potentially lack effectiveness because that same subsurface water deficit was not considered, thereby calling into question any claims of long-term survival of preserved oak trees.

Aesthetic Resources

The project site contains a “distinct” knoll of oak trees that likely would be removed for project development. The MND acknowledged the potential loss of this scenic resource but claimed mitigation reduced the impact to less than significant. This mitigation included some avoidance measures and also pointed to the oak tree measures (discussed above) for restoration and preservation. The trial court found this mitigation to be inadequate. Although Appellants claimed the Petitioners failed to properly exhaust this issue (discussed below), the Court found that evidence in the record demonstrated that the knoll may not be preserved under project design and that, even if it were, the subsurface water deficit would jeopardize its continued existence, and no in-lieu fee could “reduce the impacts on aesthetic resources” of this loss.

The Court of Appeal’s Decision on Appellants’ Other Claims

Administrative Remedies Were Exhausted

Appellants repeatedly contended that Petitioners did not exhaust their administrative remedies and therefore forfeited their claims. They also contended that Petitioners did not address the issue of exhaustion in their first opening brief, and therefore could not submit supporting evidence. Addressing the second claim first, the Court found that Petitioners did preserve the general issue of exhaustion because there is no requirement that the issue must be argued in an opening brief and, nevertheless, their opening brief cited evidence that was later used in Petitioners’ reply brief to show exhaustion. This evidence demonstrated that exhaustion was “not a new legal theory raised for the first time” on reply. The Court also found that Petitioners expressly alleged exhaustion in their petition and “lodged the complete administrative record” as part of the writ proceedings. Further, the trial court’s rejection of Appellants’ supplemental brief on this issue was warranted because in filing it they had directly violated a court order stating that “the issue of exhaustion was thoroughly argued.”
As to the first contention, appellants raised exhaustion as a defense to each of Petitioners’ CEQA claims. The Court considered “the totality of [the] record” by looking to various portions demonstrating that most of Petitioners’ claims were preserved. It looked specifically to public comments, City Council hearing transcripts, other correspondence from environmental groups and experts, and documentation from the City’s own consultants to find again and again that the City was “‘fairly apprised’” of the “underlying concerns behind Petitioners’’ claims and thereby had the “‘opportunity to decide matters [], respond to objections, and correct any errors before the courts intervene.’”

Court Rejected Standing and Statute of Limitations Defenses

Appellants asserted both that Petitioner Save the Agoura Cornell Knoll lacked standing because Petitioners failed to show that they timely objected to project approval and that Petitioner CNPS was barred from the action because they joined the suit after the statute of limitations had run. The Court declined to consider the merits of either claim. It found that Appellants had forfeited their statute of limitations argument by not properly asserting it “‘in a general demurrer or pleaded in answer’” and, therefore, without a statute of limitation violation, CNPS remained a petitioner with uncontested standing. The Court was quick to point out that Appellants claims on these points were made for the first time in their appellate reply brief “[n]otwithstanding their [own] arguments on forfeiture.”

Attorney’s Fees Are Recoverable and Appellants Are Jointly and Severally Liable

The trial court awarded attorneys’ fees to Petitioners and assigned joint and several liability to both the developer Agoura and Cornell Road and its representative Doron Gelfand. Appellants first argued against the award by asserting that Petitioners did not provide notice of the CEQA action to the Attorney General “in accordance with section 21167.7 [of the Public Resources Code] and Code of Civil Procedure section 388” that requires notice be served within 10 days of filing a pleading. On this point, the Court found that, although Petitioners did not serve the Attorney General notice of the first amended petition, they did properly notice their original petition, which was not materially different than the first amended, thereby giving the Attorney General “ample time to intervene.” The Court further pointed to case law emphasizing that a lack of strict compliance with the 10-day notice rule “was not an absolute bar to attorney’s fees.” It further concluded that a declaration from Petitioners’ attorney attesting to notice could stand as evidence in lieu of formal proofs of service of that notice. Appellants then argued that Gelfand could not be held personally liable because he was neither the applicant nor the property owner. But, in utilizing the test articulated in Connerly v. State Personnel Bd. (2006) 37 Cal.4th 1169, 1181, the Court found that Gelfand was a “real party who pursued a direct interest in the project that gave rise to the CEQA action and actively participated in the litigation” and, therefore, was liable. The record contained ample evidence showing that Gelfand was, at one time, “‘the owner of the property’” and had personally made several requests to the City regarding the project, and was listed “as the sole project applicant” on City resolutions approving project entitlements.

Oak Tree Ordinance Was Violated

The City’s oak tree ordinance allows the cutting of oak trees with a permit but disallows removal of more than 10 percent of a subject property’s total estimated canopy or root structure. The project would result in removal of up to 36 percent of oak trees on site in violation of this ordinance. Appellants did not argue against that fact but did assert Petitioners failed to exhaust their administrative remedies on this claim. The Court addressed both the merits of the claim and exhaustion (see above) and agreed with the trial court in finding that, in approving the oak tree permit for the project, the City violated its own “‘duly adopted law’” and therefore the permit must be vacated.

Casey Shorrock

Third District Holds EIR Is Required When Lay Opinion Supports Fair Argument of Aesthetic Impacts

In Georgetown Preservation Society v. County of El Dorado (2018) 30 Cal.App.5th 358, the Third District Court of Appeal held that the county is required to prepare an EIR when the lay opinions of local community members create a fair argument of potentially significant aesthetic impacts.

The project at issue was a proposed Dollar General store in a designated rural commercial zone in downtown Georgetown, an unincorporated community in El Dorado County. Although the community is not a designated historic resource, it has a historical design overlay zone, and new construction is required to “generally conform” to the county’s Historic Design Guidelines. The county prepared a mitigated negative declaration. The county also determined, through an extensive design review process in which the proposed design was revised and refined to more fully express the “Gold Rush Era” aesthetic, that the project was consistent with the design guidelines, relying in part on peer review by experts in historic architecture. Over the course of the design and environmental review processes, local residents expressed their opinions that the project was visually incompatible with the existing aesthetic character of the community. Nonetheless, the county adopted the MND, and the Georgetown Preservation Society sued. The Society prevailed in the trial court, asserting that local residents’ lay opinions on the compatibility of the proposed store design with the existing aesthetic character of the town provided substantial evidence in support of a fair argument and that an EIR was required. The applicant and the county appealed.

First, the court held that the county’s finding that the project complied with applicable planning and zoning rules via the historic design review process is not entitled to deference in the context of the county’s compliance with CEQA, and the fair argument standard still applies. Although an agency’s planning and design review forms part of the entire body of evidence to consider when determining whether the fair argument standard has been met, application of such design guidelines does not insulate the project from CEQA review at the initial study phase under the fair argument standard.

Second, the court stated that lay commentary can establish a fair argument that the project may cause substantial environmental impacts. The court rejected the appellants’ arguments that here, the county’s design review criteria recommending specific architectural styles and features constituted a technical subject. Therefore the court held that lay commentary on nontechnical matters is admissible and probative. Here, the court cited the large number of local residents who submitted comments on this issue, including some claiming backgrounds in design and planning.

Relatedly, the court held that the county’s position that cited evidence from lay persons was not credible, the county’s decision-makers were first obligated to state, in the record and with particularity, which evidence lacked credibility and why. The appellants asserted that much of the cited testimony lacked basis in facts, but the court held that the county could not discount such evidence in litigation after failing to do so in the administrative record. The court further stated that even if the county had made such determinations here, doing so would have been an abuse of discretion because the court found the testimony constituted substantial evidence supporting a fair argument.

The court noted that it was not offering an opinion as to whether the project would have a substantial impact on aesthetics, but only that an EIR was required in order to fully examine the issue.

Real parties in interest were presented by Sabrina V. Teller, L. Elizabeth Sarine, and Sara F. Dudley.

City’s Decision to Deny Mitigated Negative Declaration Upheld For Small San Diego Subdivision

On May 23, 2017, the Fourth District Court of Appeal court ordered published Kutzke v. City of San Diego (2017) 11 Cal.App.5th 1034. In a succinct opinion, the court upheld the city’s decision to deny a mitigated negative declaration (MND), initially approved by the planning commission, regarding an application to subdivide two hillside lots and build three residences.

The court emphasized that the standard of review was deferential to the city, and limited to determining whether the city’s findings were supported by substantial evidence. The court interpreted this standard by stating that plaintiff could only prevail if she could demonstrate that no reasonable municipality could have reached the same decision as the city.

Under this standard of review, the court determined that the city presented substantial evidence in the record to support its finding that impacts to land use, geology, and public safety would be detrimental and inadequately mitigated. Flaws and omissions in the project’s geotechnical report cast doubt on the report’s conclusion that homes could be built safely on the steep sandstone hillside. Furthermore, the slope of the shared driveway would not permit access by firetrucks and potentially other emergency response vehicles. Proposed mitigation measures (sprinkler systems and standpipes) were inadequate to mitigate all of these risks.

Regarding the project’s consistency with the community plan, the city properly considered the opinions of neighbors, who stated that the project’s dense development with minimal setbacks was incompatible with the large lot, single-family residential character of the area. Finally, the project was properly rejected under city ordinances, which provide for deviations from the development regulations for qualified sustainable building projects, if the deviations result in a more desirable project. For similar reasons as to why the project was rejected under the community plan and CEQA, the deviations requested here (smaller setbacks, no frontage, and higher walls) would not make the project more desirable.

First District Applies Fair Argument Standard of Review to Addendum to Negative Declaration on Remand from Supreme Court in Friends of the College of San Mateo Gardens

On remand from the Supreme Court’s holding in Friends of the College of San Mateo Gardens v. San Mateo County Community College (2016) 1 Cal.5th 926 (San Mateo I ), the First District interpreted the Supreme Court’s direction as requiring the application of the fair argument standard of review to claims challenging an addendum to a negative declaration in Friends of the College of San Mateo Gardens v. San Mateo County Community College District (2017) 11 Cal. App.5th 596.

The Supreme Court’s holding in San Mateo I

The San Mateo cases concern the San Mateo County Community College District’s campus renovation project, approved with a mitigated negative declaration (MND) in 2006. In 2011, the College decided to demolish an area of the campus (the Building 20 Complex) that was planned for renovation under the 2006 plan, and construct a parking lot in its place. The updated plan was analyzed in an addendum to the 2006 MND. The suit in San Mateo I followed, with the petitioner alleging that the updated plan was a “new project” under CEQA, and not a modified project subject to CEQA’s subsequent review provisions (Pub. Resources Code, § 21166; CEQA Guidelines, § 15162.). Both the trial court and the First District held that it was a new project, and therefore, the District was not entitled to rely on an addendum.

The Supreme Court reversed, noting first that the proper inquiry under CEQA was not whether or not a project is new or modified, but whether or not the initial environmental document retains informational value in light of the proposed modifications, or if it had become irrelevant.  This is a factual determination to be made by the agency and reviewed for substantial evidence.

If the agency’s decision to proceed under CEQA’s subsequent review provisions is supported by substantial evidence, a court may consider the type of subsequent document prepared by the agency. The standard of review applied by the court in reviewing that decision turns on the nature of the original documents. The agency must first determine if there are substantial changes to the project that require “major revisions” in the original environmental analysis. This determination is reviewed for substantial evidence. When the project was previously reviewed in an EIR, there are no “major revisions” if the initial EIR has already adequately addressed any additional environmental effects expected to result from the proposed modifications. In contrast, when a project is initially approved with a negative declaration, a “major revision” to the negative declaration will necessarily be required if the proposed modification may produce a new or previously unstudied significant environmental effect. If there is no major revision required, the agency can issue a subsequent mitigated negative declaration, addendum, or no further documentation.

Application in San Mateo II

The court applied the two-part test of San Mateo I to the College’s decision to rely on an addendum to the 2006 MND. First, the court conceded that the agency determination—that the MND retained informational value in light of the revised campus plan—was supported by substantial evidence. It retained informational value because the revised plan considered in the addendum did not affect plans to demolish 14 buildings cited in the original plan. The revised plan added one more building complex to the demolish list, but the College had previously removed two others, deciding to renovate them instead. The mitigation measures adopted with the original plan remained in place.

Applying the second prong of the Supreme Court’s test, however, the court held that the College violated CEQA’s subsequent review provisions by preparing an addendum to the MND, because the removal of gardens in the Building 20 Complex could result in a significant aesthetic impact, under the fair argument standard of review.

Interpreting this second prong of the San Mateo I test, the San Mateo II court stated that when the initial environmental review document is an negative declaration, the court must apply the more exacting standard applicable to negative declarations—whether there is substantial evidence to support a fair argument that the proposed changes to the project might have a significant effect on the environment. The court acknowledged that aesthetic impacts are necessarily subjective, but agreed with the petitioner that substantial evidence of a fair argument could be found in the opinions based on direct observation. The impact is not determined by the size of the area, but measured in light of the context in which it occurs, and this can vary by setting.

Here, the court relied on the opinions of campus employees and students regarding the garden’s aesthetic value and quality. Although not a significant portion of the campus’ open space (less than one-third of one percent), the garden’s vegetation and landscaping were alleged by its admirers to be unique. The garden’s social value as a gathering space was also considered. Because the court determined that this lay testimony qualified as substantial evidence to support a fair argument of a potentially significant aesthetic impact, the College’s decision to rely on an addendum violated CEQA’s subsequent review provisions, as an addendum is only appropriate if there are no new or more severe significant impacts than were previously analyzed.  However, the court declined to order the preparation of an EIR, stating that the College could choose to prepare a subsequent MND if the impacts to the garden could be mitigated to a less-than-significant level.

Friends of the College of San Mateo Gardens v. San Mateo County Community College District

Friends of the College of San Mateo Gardens v. San Mateo County Community College District (2016) 1 Cal.5th 937

In a unanimous decision, the California Supreme Court emphatically rejected the notion that public agencies should get no deference in deciding whether to treat proposed projects as changes to previously reviewed projects or as new projects under CEQA. In doing so, the court strongly disagreed with the reasoning presented in the Third District’s decision in Save Our Neighborhood v. Lishman (2006) 140 Cal.App.4th 1288, which first articulated the “new project” threshold question as a de novo question of law for the courts. The Supreme Court concluded that Division One of the First District Court of Appeal erred in applying Lishman’s “new” project standard to the case at hand, which involved a community college district’s proposed changes to the disposition of a small building complex and landscaped area on a campus for which a campus-wide renovation plan was previously reviewed in an unchallenged mitigated negative declaration (MND). The district considered the subsequent changes in an addendum to the MND and approved the demolition of an existing complex of outdated buildings and their replacement with a new parking lot, concluding that the changes posed no new or more severe environmental impacts than were previously described in the adopted MND.

The Supreme Court granted review to resolve the question of whether Lishman’s “new project” test was the correct approach for courts reviewing subsequent review documents, or whether courts should follow the more deferential, substantial evidence standard explained in Mani Brothers Real Estate Group v. City of Los Angeles (2007) 153 Cal.App.4th 1385. Few appellate courts had followed the Lishman approach after the court in Mani Brothers rejected it. Division One of the First District applied it to the college district’s case in an unpublished decision, but oddly declined to apply it again a few weeks later in its published decision, Latinos Unidos de Napa v. City of Napa (2013) 221 Cal.App.4th 192, 201-202, thereby highlighting the conflict in the law.

The Supreme Court noted that the Lishman court’s focus on the similarities or lack thereof in the features associated with an originally-reviewed project and subsequent proposal as lacking any basis or standards in CEQA. The court further noted that because of the lack of any standards or framework for measuring the “newness” of a given project, a “new project” test applied by the courts “would inevitably invite arbitrary results.” Moreover, the court emphasized that, given the purpose of CEQA to ensure agencies consider the environmental effects of proposed actions, focusing on the characterization of a proposed project as a new project or a modified project misses the point of subsequent review. Rather, the court concluded, the fundamental determination an agency must make is whether an original environmental document retains some informational value, or whether the proposed changes have rendered it wholly irrelevant.

The court affirmed the college district’s view (shared by the Regents of the University of California, League of California Cities, California State Association of Counties, Association of California Water Agencies, California Building Industry Association, Building Industry Association of the Bay Area, and California Business Properties Association, who participated as amicus parties at the Supreme Court) that the question of whether an initial environmental document remains relevant in light of changed plans or circumstances is inherently a factual question for the agency to answer in the first instance and is reviewable under the deferential substantial evidence standard of review.

Following oral argument, the court ordered supplemental briefing on two issues: (1) the standard of review that applies to an agency’s determination not to prepare an EIR for modifications to a project that was previously reviewed by a negative declaration; and (2) whether CEQA Guidelines section 15162, as applied to projects initially approved by negative declarations rather than EIRs, was a valid interpretation of the governing statute, Public Resources Code section 21166, which does not mention negative declarations. Guidelines section 15162, subdivision (a) prohibits agencies from requiring a subsequent or supplemental EIR unless the agency determines “on the basis of substantial evidence in the light of the whole record,” that “substantial changes . . . will require major revisions of the previous EIR or negative declaration due to the involvement of new significant environmental effects or a substantial increase in the severity of previously identified significant effects.” The court rejected the petitioner’s argument that application of this substantial evidence standard in section 15162(a) to projects initially analyzed in negative declarations creates a CEQA loophole that permits agencies to evade their obligation to prepare an EIR under the less deferential fair argument standard. As the court explained, “the substantial evidence test referred to in the Guidelines does not, as plaintiff supposes, refer to substantial evidence that the project, as modified, will necessarily have significant environmental effects. It instead refers to substantial evidence that the proposed modifications will involve ‘[s]ubstantial changes’ that ‘require major revisions of the previous EIR or negative declaration due to the involvement’ of new or significantly more severe environmental effects.” The court held that section 15162 constitutes a valid gap-filling measure as applied to projects initially approved via negative declaration, including the college district’s project at hand.

Lastly, the court rejected the petitioner’s contention that the subsequent review schemes in the statute and Guidelines were inapplicable to the district’s project because the originally-approved campus renovation project was more akin to a plan or program than a specific project. Both the Court of Appeal below and petitioner relied on Sierra Club v. County of Sonoma (1992) 6 Cal.App.4th 1307 to conclude that when an agency initially adopts a broad, large-scale environmental document (such as the college district’s original MND) that addresses the environmental effects of a complex long-term management plan, a court can find that a material alteration to the plan regarding a particular site or activity may be a new project triggering environmental review under Public Resources Code section 21151. The Supreme Court rejected the attempt to frame the original campus renovation plan and subsequent changes to the disputed area in this manner, holding that the tiering provisions, and therefore the Sierra Club decision, had no applicability here. The court noted that unlike the program EIR at issue in Sierra Club, the MND previously adopted by the college district was a project-specific review that could not be characterized as a first-tier document.

The Supreme Court remanded to the Court of Appeal’s consideration the merits of the district’s addendum and approval of the building demolition and parking lot project. The Court of Appeal had not previously reached the merits because of its conclusion that the subsequent project was “new.”

RMM partners Sabrina V. Teller and James G. Moose represented the respondent San Mateo County Community College District in the litigation from the trial court through the Supreme Court.

First District Court of Appeal Applies Substantial Evidence Standard of Review to Subsequent MND and Upholds County’s Decision to Permit Expansion of Buddhist Retreat Center

In Coastal Hills Rural Preservation v. County of Sonoma (2016) (previously published at 2 Cal.App.5th 1234)* the First District Court of Appeal upheld the trial court’s determination that the County of Sonoma did not violate CEQA or the Planning and Zoning law when it adopted a subsequent mitigated negative declaration (MND) and approved a master use permit to expand the existing Ratna Ling Buddhist retreat center and printing facility.

The Tibetan Nyingma Meditation Center (TNMC) has operated a monastery and retreat center in Cazadero since 1975. In 2004, TNMC purchased an additional property, which it designated the Ratna Ling Retreat Center. Since 2004 Ratna Ling has undergone numerous changes and expansions, including growing from a one-printing-press facility to operating six printing presses. In response to applications from Ratna Ling, the county adopted and approved a series of mitigated negative declarations in 2004, 2008 and 2012. In 2014, Ratna Ling applied for a third multiple-use permit, and the county adopted a subsequent MND to the 2004 and 2008 MNDs, superseding the 2012 MND. The 2014 subsequent MND analyzed Ratna Ling’s application to make permanent four storage tents for its printing-press operation, and construct a new six-bedroom residence and up to eight tent cabins.

Coastal Hills Rural Preservation (CHRP) filed suit, arguing that the county should have prepared an EIR because the project greatly expands the printing-press operation. CHRP also argued that the approval violated the county’s general plan and zoning provisions. The trial court denied the petition, and the First District Court of Appeal affirmed.

CHRP argued that the project was inconsistent with the county’s general plan and zoning provisions in violation of Government Code section 65300. The site is designated for “resources and rural development” under the county’s general plan, which is intended to “protect lands used for timber, geothermal and mineral resource production and for natural resource conservation.” Contrary to CHRP’s argument that the printing press included “extraordinary levels of manufacturing productions …, massive storage structures and commercial Internet sales,” the court found that substantial evidence supported the county’s determination that the proposed uses were consistent with the land use regulations. The court explained that an agency’s determination regarding consistency with its own general plan is given great deference because “the body adopting a general plan has unique competence to interpret those policies when applying them to a proposed project.” There was no evidence in the record that the printing activities were undertaken for profit, the printing press use had been permitted since 2004, and the Board fully considered the county’s land use policies and the extent to which the project conforms to those policies.

The Court of Appeal also affirmed the trial court’s determination that the Board did not violate CEQA. Because the court was considering the county’s decision to prepare a subsequent MND where an MND had already been prepared under Public Resources Code section 21166, the court applied the substantial evidence test rather than the fair-argument standard of review. The court noted that the issue of the standard of review is currently before the California Supreme Court in Friends of the College of San Mateo Gardens v. San Mateo Community College Dist. (Sept. 26, 2013, A135892 [nonpub. opn.]), review granted Nov. 5, 2013, S214061).

The court found that substantial evidence supported the Board’s conclusion that any fire risks posed by the storage tents were adequately mitigated: the membranes covering the tents met applicable fire protection standards, there was 200 to 300 feet of defensible space around each tent, and a condition of approval required Ratna Ling to provide and maintain its own onsite fire engine. In addition, the court held that, regardless of whether the county should have included the tents in the baseline for its analysis, substantial evidence in the record indicated that the Board fully considered the potential impacts of the tents.

The court also ruled against arguments put forth by amicus curiae Friends of the Gualala River and Forest Unlimited. Contrary to those arguments, the county’s Hazard Mitigation Plan was not effective until October 25, 2011, well after the storage tents were permitted and constructed, and therefore was inapplicable. In addition, the county did not improperly defer mitigation when it required Ratna Ling to coordinate with the fire district and comply with all fire-related conditions, because the mitigaton simply granted the county the right to impose new, stricter requirements if deemed necessary.

Finally, CHRP argued that the county engaged in impermissible spot zoning. The court explained that because the record and the relevant zoning regulations did not suggest that the authorized use for Ratna Ling is prohibited as to all other parcels in the same zone, this was not impermissible spot zoning in violation of Government Code section 65852.

*On November 22, 2016, the California Supreme Court granted review (210 Cal.Rptr.3d 14), depublished the decision, and transferred the case back to the First District, Division One, for reconsideration in light of Friends of the College of San Mateo Gardens v. San Mateo County Community College District et al. (2016) 1 Cal.5th 937, 957–959. On May 16, 2016, the First District filed an unpublished decision in matter, available at 2017 WL 2118370.