Tag: mitigation measures

Third District Holds EIR’s Project Objectives Were Too Narrow and Recirculation Was Required Due to Increase in Significant and Unavoidable GHG Emissions

In We Advocate Through Environmental Review v. County of Siskiyou (2022) 78 Cal. App.5th 683, the Third District Court of Appeal held that Siskiyou County’s environmental analysis of a bottling plant was deficient because the project objectives were too narrow, and because the County failed to recirculate the EIR despite a discrepancy in the estimated carbon dioxide emissions from the draft EIR to the final EIR (FEIR). Though the discrepancy did not change the EIR’s ultimate conclusions, recirculation was necessary to provide the public with meaningful opportunity to review and comment on the project’s environmental impacts. In We Advocate Through Environmental Review v. City of Mount Shasta (April 12, 2022, No. C091012) ___ Cal.App.5th___ [2022 WL 1487832], petitioners challenged city’s approval of wastewater permit for the same project.

Background

Real Party in Interest, Crystal Geyser, purchased a non-operational bottling facility in Siskiyou County in 2013, seeking to revive the plant for beverage production. To initiate the project, Crystal Geyser requested permits from the County to build a caretaker’s residence, and the City of Mount Shasta for discharging wastewater into the City’s sewer system. Both permits were approved.

We Advocate Through Environmental Review and the Winnehem Wintu Tribe sued the County alleging the EIR violated CEQA because it (1) provided an inaccurate description of the project, (2) defined the project’s objectives in an impermissibly narrow manner, (3) improperly evaluated several of the project’s impacts, and (4) approved the project though it would be inconsistent with the County’s and City’s general plans.

The trial court rejected all of petitioners’ claims. This appeal followed.

The Court of Appeal’s Decision

The Court of Appeal reversed the trial court in part, holding in the published portions of the decision that the project objectives were too narrow and that recirculation was required because the FEIR estimated that the project would generate significantly more carbon dioxide emissions than disclosed in the DEIR. The fact that the DEIR concluded that this impact was significant and unavoidable did not mean the increase in greenhouse gas emissions was “insignificant” under CEQA.

Project Objectives

The Court agreed with Appellant’s contention that the EIR defined the project objectives too narrowly, because the County defined the project objectives in a manner that precluded all alternatives other than the proposed project. For example, one objective was to “site the proposed facility at the Plant . . . to take advantage of the existing building, production well, and availability and high quality of existing spring water on the property.” Another objective aimed to “utilize the full production capacity of the existing plant based on its current size.” According to the Court, this narrow approach was unacceptable because it transformed the alternatives section of the EIR into an “empty formality,” rather than served the purpose of enabling meaningful environmental review of a project. The Court concluded the County’s error was prejudicial because it foreclosed viable alternatives.

Climate Change Impacts Analysis

Appellants challenged the EIR’s discussion and mitigation of climate change impacts, arguing (1) the County failed to recirculate the EIR to address the discrepancy in carbon dioxide emissions estimations between the DEIR and the FEIR, (2) the County failed to analyze foreseeable emissions from “preform” bottles, and (3) the EIR’s mitigation measures were not properly amended to reflect the emissions change from the DEIR to the FEIR.

The Court agreed that the County violated CEQA by failing to recirculate the EIR after changing the greenhouse gas emissions estimate from 35,486 metric tons of carbon dioxide per year in the DEIR, to 61,281 metric tons in the FEIR. The County argued recirculation was unnecessary because the impact remained above the “significant and unavoidable” threshold in both versions of the EIR. The Court held that the estimated increase of over 25,000 metric tons of carbon dioxide per year between the versions was significant enough to require recirculation, though it did not change the EIR’s ultimate conclusions. Failing to recirculate “wrongly deprived the public of a meaningful opportunity to comment on a project’s substantial environmental impacts.”

The Court rejected Appellants’ other arguments regarding climate change impacts. On the subject of “preforms,” the Court rejected Appellants’ argument because they failed to concretely show that “each preform that Crystal Geyser purchases for the project would necessarily be a preform that would not otherwise have been produced.” Additionally, the Court held that the mitigation measures were valid and enforceable because the County revised and reevaluated mitigation measures to reflect increased emissions in the FEIR.

— Jordan Wright

First District Holds Stipulated Federal Court Judgments Do Not Preclude Independent Review Under CEQA

In Tiburon Open Space Committee v. County of Marin (2022) 78 Cal.App.5th 700, the First District Court of Appeal held that Marin County properly limited the scope of its environmental review to comport with its legal obligations pursuant to two stipulated federal judgments. In the same vein, the Court rejected appellants’ claim challenging the scope of the EIR’s project description, which incorporated the constraints imposed by the judgments. The Court also rejected appellants’ claims that the County abused its discretion by rejecting a scaled down project alternative, and making several mitigation findings for impacts to traffic safety and density, a threatened species, and water supply and fire flow.

Background

Real Party in Interest, the Martha Company (Martha), owns a 110-acre property on a mountaintop in Marin County that overlooks the Town of Tiburon. For several decades, Martha attempted to develop single family homes on the property, yet all proposed projects befell to forceful opposition from residents of the Town of Tiburon and the County.

The current dispute is predated by two stints in federal court that resulted in stipulated judgements.

The first federal case occurred in 1975, when the County adopted a re-zoning measure that drastically reduced the number of residences Martha could build on the property from a minimum of 300 to a maximum of 34. Martha sued the County in federal district court, alleging the re-zoning constituted a regulatory taking of property. The case resolved in 1976 by stipulated settlement that (1) Martha could develop no fewer than 43 single family homes on a minimum of half-acre lots; (2) Martha could place some homes on portions of the property named the Ridge and the Upland Greenbelt; and (3) 43 single family homes on half-acre lots is consistent with the goals of the County’s general plan while allowing owners a feasible economic use of their property.

Between federal cases, Martha submitted a project proposal to the County, which directed Martha to file an application with the Town of Tiburon for approval. The Town conducted years of environmental study without rendering a decision, and eventually Martha withdrew its application. In 2005, Martha submitted a new project proposal. The County refused to process Martha’s second application just as it refused to process the first.

The County returned to federal court, seeking relief from the 1976 stipulated settlement. It alleged that California environmental laws had changed in the 30 years since 1976, such that it would be against public policy of the state to “allow a development of this magnitude, on environmentally sensitive and constrained land to proceed without the development and density being subject to CEQA review.” The district court dismissed the County’s complaint and granted the 2007 stipulated settlement, which set a timeline and procedures for enforcing the 1976 judgement.

Martha submitted a third development application for a 43-unit residential development project (the Project). The County circulated a draft EIR for the project in 2011.

In 2017, after years of administrative proceedings, further environmental review, and litigation concerning the project, Martha submitted a modified Master Plan of the development project to comply with the County Board of Supervisors’ request for a “more specific proposal.” Additionally, Martha agreed to a phased review of its development application. The Marin County Board of Supervisors certified the EIR by a 3-2 vote.

Tiburon Open Space Committee and the Town of Tiburon (collectively, the Town) each filed petitions for a Writ of Mandate against the County, alleging the EIR was legally inadequate in numerous respects, and the County’s review process was legally deficient. The trial court denied both petitions. The Town appealed.

The Court of Appeal’s Decision

Implications of the Stipulated Judgments

The Town’s principal allegation was that the County violated CEQA by failing to exercise the full measure of its statutory discretion when it complied with the stipulated judgements. In essence, the Town claimed the County illegally “contracted away its police powers.”

The Court of Appeal rejected these claims, explaining that the Board proceeded “along lines that are in fact expressly embedded in CEQA,” and did not circumvent its obligations under the statute.

First, the Court concluded that the EIR was not a “pro forma” exercise, nor had a preordained outcome as the Town contends. The Court underscored the fact that the EIR underwent several revisions, spanned 850 pages, involved consultation with other agencies, provided meaningful opportunity for public review and comment, and cost considerable time and money. Furthermore, the County retained discretion to shape the contours of the Project during the later phases of approval. Specifically, the Court noted, the EIR proceedings were not “rushed, perfunctory, or short circuited” and were “utterly at odds with the conduct of a public entity that believed itself free to blow off CEQA.”

Second, the County appropriately limited its CEQA analysis to the scope of its discretionary authority. The Court cited Sequoyah Hills Homeowners Association v. City of Oakland (1993) 23 Cal.App.4th 704 for the holding that an agency’s discretion under CEQA is limited by its own legal obligations. For example, the Court remarked that CEQA imposes a duty to mitigate environmental impacts only to the extent feasible. Applied here, the County had a legal obligation to comply with the conditions imposed by the stipulated judgements. Since the stipulated judgments limit the scope of the County’s discretion by requiring certain conditions for the project be met, they also limited the scope of its environmental review. Thus, while legally feasible alternatives and mitigation measures had to be examined by the County, alternatives or mitigation measures that contradicted its obligations under the stipulated judgements were legally infeasible and did not need to be examined. Accordingly, the Court held that the County’s approval of a project that complied with the conditions set by the stipulated settlements was proper.

The Town also raised a corollary argument that the stipulated judgements deprived the members of the County Board of Supervisors from exercising their “independent judgement.” The Court refuted this argument by highlighting its logical flaw; that is, if it can be said that federal judgements are not binding on a public official’s independent discretion, then it can equally be said that inconvenient provisions of state law, namely CEQA, are not binding on independent discretion either.

The Court therefore concluded that the EIR fulfilled the central purpose of CEQA to “disclose to the public the reasons why a governmental agency approved the project in the manner the agency chose,” and the County’s review process appropriately limited the scope of its environmental review to match its discretionary authority.

Project Description

The Court also rejected the Town’s claim that Final EIR’s 34-page project description was “artificially narrow” because it incorporated the legal constraints imposed by the stipulated judgments. The Court explained that the project description provided more detail than CEQA requires, and this argument was a mere variation of the claim that the County “abdicated” its responsibilities under CEQA by complying with the judgments—which it already rejected.

Alternatives

The Court held that the County did not abuse its discretion by rejecting a 32-unit alternative because that alternative was legally infeasible due to the legal requirements imposed by the stipulated judgments. It emphasized that an EIR is not required to review infeasible alternatives “even when such alternatives might be imagined to be environmentally superior.”

Environmental Impacts and Mitigation Findings

The Court of Appeal held that substantial evidence supported the County’s findings that several of the Project’s impacts would be mitigated to a less than significant level.

First, the Court upheld the County’s finding that traffic safety impacts could be mitigated by measures that required the Town to implement them—including removing traffic obstacles such as trash receptacles and enforcing speed limits on narrow winding road. The Court explained that CEQA only requires a “reasonable plan” for mitigation and allows for the approval of a project with a finding that mitigation should be adopted by another entity that has exclusive jurisdiction.

The Court also concluded that substantial evidence supported the EIR’s “level of service” (LOS) methodology for calculating the Project’s traffic density impacts, noting that LOS was an established standard required in the County. Quoting the trial court, the Court of Appeal held that the traffic analyst was entitled to rely on this methodology because it “had the prerogative to resolve conflicting factual conclusions” about the traffic congestion impacts of the Project.

The Court upheld the EIR’s use of best management practices (BMPs) for the mitigation of impacts on the threatened California red-legged frog. It explained that the BMPs did not defer mitigation, but rather qualified as “revisions in the project plans” agreed to by Martha because they were accepted as conditions of approval. Further, the Court noted, the BMPs were already in existence because they were included in the Project’s Stormwater Control Plan. Accordingly, the Court determined that the BMPs were incorporated by reference in the EIR.

The Town’s claims regarding the County’s water supply and fire flow mitigation measures were barred due to its failure to exhaust the issues during the County’s administrative process. The Court nonetheless concluded that the measures requiring Martha to work with local water and fire authorities were sufficient and would not allow Martha to do “nothing” because failing to comply would result in the County not issuing the permits required to proceed with the Project. The Court also concluded that the Town’s demand for more detail in the water supply plan went beyond what CEQA requires.

Lastly, the Court concluded that substantial evidence—specifically, construction and traffic experts’ opinions—supported the County’s determination that mitigation would reduce the Project’s safety impacts resulting from a temporary on-site construction road to less than significant. The Court explained that alternative evidence does not negate the substantial evidence that the County relied on, and that it is within the agency’s discretion to evaluate the credibility of such evidence. It also emphasized that the safety risks were limited to the workers building the Project, and CEQA only requires review of safety risks posed to the public in general.

The Court’s Closing Remarks

The Court of Appeal concluded its opinion by expressing its inclination to afford the trial court’s decision great weight in counties with designated CEQA judges. The Court also generally criticized the use of CEQA lawsuits as “tool[s] of obstruction,” especially for housing developments.

— Jordan Wright & Veronika Morrison

First District Holds Petitioner Exhausted Its Remedies by Raising General Objections That the Project Site Should Be Preserved as Open Space, Finds “No Project” Alternative Analysis Defective

In the published portions of Save the Hill Group v. City of Livermore (2022) 76 Cal.App.5th 1092, the First District Court of Appeal held that Petitioner Save the Hill’s failure to specifically reference the recirculated EIR or the no-project alternative in its comments to the City Council did not bar its CEQA claims regarding preservation of the Project site.

Background

This case involves the City of Livermore’s approval of a development application for a housing development in the Garaventa Hills. The Project underwent multiple revisions, and the Project at issue is a scaled-down version of the original 76-unit residential development. The final Project is a 44-unit development with pedestrian across Altamont creek that also serves as a secondary emergency vehicle access road. The City published a Recirculated Final EIR (RFEIR) for this final revised Project.

Save the Hill filed a petition for writ of mandate challenging the City’s approval of the Project and certification of the RFEIR for failure to consider significant environmental impacts, adequately investigate and evaluate the no-project alternative, and mitigate significant environmental impacts. The trial court denied the petition, determining that Save the Hill failed to exhaust its administrative remedies in challenging the RFEIR. Save the Hill appealed.

The Court of Appeal’s Decision

Exhaustion

The Court of Appeal held that Save the Hill did not fail to exhaust its administrative remedies before challenging the City’s failure to evaluate the no-project alternative. While Save the Hill did not mention the environmental documents or the lack of a no-project alternative specifically, it did express its desire to preserve the Project site as open space. The Court emphasized that CEQA does not require public interest groups such as Save the Hill—which are often unrepresented by counsel at administrative hearings—to do more than “fairly apprise” the agency of their complaints to preserve them for appeal.

Several Save the Hill representatives voiced support for preserving the Project site as open space in perpetuity at the City Council hearing for the RFEIR’s certification. These comments sparked questions from city councilmembers regarding the possibility of preserving the Project site and a discussion of available funding to purchase Garaventa Hills for conservation. This option was shut down by the City Attorney, who advised the City Council that its evaluation should be limited to the Project as set before them, and that if it were to change the zoning to permanent open space on the property, the City would likely face a takings lawsuit.

The Court determined that these comments and the ensuing discussion reflected the City Council’s consideration of a no-project alternative as a result of Save the Hill’s objections. It concluded that Save the Hill’s failure to specifically refer to the RFEIR’s Project alternatives evaluation was immaterial to the fact that it fairly appraised the City of its position. The court further explained that even if Save the Hill framed its arguments in the context of the RFEIR’s no-project alternative, “the evidence is overwhelmingly that, had it done so, the result would have been the same: [t]he City would have rejected the group’s proposal and certified the RFEIR” because it was improperly instructed to limit its focus to the presented Project.

Accordingly, the Court held that an exception to the exhaustion requirement applied because the aggrieved party—Save the Hill—could “positively state” what the lead agency’s decision would be in its particular case.

No Project Alternative Analysis

On the merits of Save the Hill’s alternative analysis claim, the Court held that the RFEIR failed to disclose and analyze information regarding the availability of funding sources that could have been used to purchase and permanently conserve the Project site. The Court explained that zoning changes are within the City’s police power, and the RFEIR accordingly should have discussed the feasibility of rezoning the site as permanent open space.

Mitigation Measures Adequacy

Save the Hill asserted that the mitigation measures for impacts to vernal pool fairy shrimp were inadequate because they would only be implemented if the fairy shrimp were detected at the site. The Court explained that CEQA allows deferred mitigation where the agency commits to achieving specific performance standards, which it did here, and that the mitigation measures were adequate because the RFEIR assumed that the fairy shrimp were present.

The Court also held that the preservation of an 85-acre compensatory mitigation site was adequate, despite Save the Hill’s contention that the City’s General Plan required the location to be preserved as open space. The Court concluded that the General Plan is “merely aspirational,” while the RFEIR’s mitigation measure created a “perpetual legal restraint on development” at the site, including requiring funding for upkeep and enforcement. Moreover, distinguishing this case from King & Gardiner Farms, LLC v. County of Kern (2020) 45 Cal.App.5th 814 (“King”), the Court explained that this Project involved the loss of only 32 acres—as opposed to the loss of 6,450 acres in King—and CEQA does not require mitigation measures to “completely eliminate the environmental impacts of a project.”

Hydrological Impacts Adequacy

The Court held that the City’s finding of no significant hydrological impacts was supported by substantial evidence because Save the Hill failed to refute the City’s points in its reply brief. The Court refused to afford any weight to Save the Hill’s argument that the Project would degrade downstream water quality because a larger development project (which originally included this Project) would have a significant downstream water quality impact. The Court determined that impacts from a project almost 200 acres larger than this Project were not relevant.

Settlement Agreement Obligation Claims

Lastly, the Court held that that Save the Hill forfeited its claim that the City violated CEQA by failing to preserve the Project site to satisfy its obligations under two settlement agreements by failing to raise the issue prior to appeal. Moreover, Save the Hill was not a party to either settlement agreement and thus lacked standing to enforce those obligations.

First District Holds Regional Water Quality Control Board’s Failure to Impose Mitigation Requirements Through CEQA Process Did Not Preclude it from Later Imposing Those Requirements Pursuant to Its Authority Under the Porter-Cologne Act

The First District Court of Appeal in Santa Clara Valley Water District v. San Francisco Bay Regional Water Quality Control Board (2020) 59 Cal.App.5th 199, held that CEQA did not preclude the San Francisco Bay Regional Water Quality Control Board, acting as a responsible agency under CEQA, from imposing additional waste discharge requirements via the Porter-Cologne Water Quality Control Act, beyond the mitigation measures imposed during the CEQA process.

Background

Every 10-20 years, the Upper Berryessa Creek—which drains from the Diablo Range Hills to the Coyote Creek tributary, and ultimately into the San Francisco Bay—floods the nearby areas of Milpitas and San Jose. In the 1980s, the U.S. Army Corps of Engineers began working on plans to build a flood control project on the creek, but the project did not move forward until 2013, when construction of a nearby BART station that could be impacted by flooding was proposed.

In 2015, the Santa Clara Valley Water District (District), acting as the lead agency under CEQA, issued a Draft EIR for the project. That same month, the Corps applied to the San Francisco Bay Regional Water Quality Control Board (RWQCB) for a section 401 Clean Water Act certification for the project.

The District later issued the Final EIR for the project, and the RWQCB’s executive officer issued the section 401 certification. As a CEQA responsible agency, the RWQCB found that all impacts within its jurisdiction would be mitigated to less-than-significant levels but clarified that it would later consider waste discharge requirements (WDRs) pursuant to its authority under the Porter-Cologne Act to address impacts to waters and wetlands that were not handled by the section 401 certificate.

In 2017, when project construction was nearly complete, the RWQCB issued a WDR order that required the Corps and the District to provide addition mitigation for the project’s impacts to waters and wetlands. The order stated that it suspended and replaced the prior 401 certification.

The District filed a petition for writ of mandate against the RWQCB, challenging the WDR order under CEQA, as well as section 401 of the Clean Water Act, the Porter-Cologne Act, and other state laws. The trial court denied the petition. The District appealed.

Court of Appeal’s Decision

On appeal, the District argued the RWQCB violated CEQA because: (1) the RWQCB’s failure to impose mitigation requirements as part of the RWQCB’s CEQA review barred it from imposing mitigation via the WDR order; and (2) the RWQCB prejudicially abused its discretion by failing to support the mitigation requirements with substantial evidence. The Court of Appeal rejected both arguments.

Relying on CEQA Guidelines section 15096, the District argued that the RWQCB’s only opportunity to impose mitigation was through the CEQA process. CEQA Guidelines section 15096 provides that a responsible agency that disagrees with the adequacy of a lead agency’s EIR must either sue the lead agency within 30 days, be deemed to have waived any objections to the EIR, prepare a subsequent EIR if legitimate grounds exist, or, assume the role of a lead agency as provided by Guidelines section 15052, subdivision (a)(3). Because the RWQCB did not challenge the District’s certification of the EIR or find that a subsequent EIR was required, the District argued that the EIR was deemed adequate and no additional mitigation measure could be imposed. As explained by the court, however, Public Resources section 21174 includes a savings clause that makes clear that CEQA does not prevent an agency from exercising it independent authority under statutes other than CEQA. The court determined, therefore, that the RWQCB did not violate CEQA by issuing the WDRs because it did so pursuant to its duties under the Porter-Cologne Act. Although the District, acting as lead agency, had not imposed CEQA mitigation measures requiring WDRs, the RWQCB, as a responsible agency, was not precluded from separately discharging its authority under the Porter-Cologne Act. Although the appellate court noted that unified CEQA review and other environmental regulation should be the norm, there may be times when an agency’s own environmental regulation can take place after CEQA review, as recognized by Public Resources Code section 21174.

The court also rejected the District’s claim that the RWQCB’s WDR order imposed “excessive” mitigation that was not supported by substantial evidence. The court concluded that the District failed to engage in sufficient analysis of the evidence supporting the RWQCB’s conclusions, and therefore, failed to carry its burden. The court also concluded that the District’s arguments lacked merit even if they had been properly briefed because the RWQCB’s determinations were supported by substantial evidence.

– Bridget McDonald

Fifth District Holds Kern County’s Ordinance for Streamlining Oil and Gas Well Permits Must Be Set Aside Due to Multiple CEQA Violations, Including Deferred Formulation of Mitigation Measures and Failure to Use Proper Threshold of Significance for Analyzing Noise Impacts

In King and Gardiner Farms, LLC v. County of Kern et al. (2020) 45 Cal.App.5th 814, the Fifth District Court of Appeal held that the County of Kern must rescind its approval of a gas and oil ordinance that would streamline the County’s permitting process for new oil and gas wells. In the published portions of the decision, the court held: (1) the mitigation measures for the ordinance’s significant impacts to water supplies impermissibly deferred formulation of the measures or delayed the actual implementation of the measures and the EIR’s discussion of the effectiveness of the mitigation measures was inadequate; (2) the County’s finding that the ordinance’s conversion of agricultural land would be mitigated to a less-than-significant level was not supported by substantial evidence because, among other things, the mitigation measures allowed for conservation easements, which do not constitute actual mitigation; (3) the County inappropriately applied a single threshold for determining the significance of the project’s noise impacts; and (4) the County must rescind the ordinance and not re-approve the ordinance until the County has complied with CEQA.

Background

In November 2015, the Kern County Board of Supervisors approved an ordinance to streamline the permitting process for new oil and gas wells and certified an EIR for the ordinance. Because some of the impacts of the ordinance would be significant and unavoidable, the Board of Supervisors adopted a statement of overriding considerations, finding that the ordinance’s benefits outweighed its significant environmental impacts.

A private farm (KG Farms) and a group of environmental organizations, including Sierra Club, filed petitions for writ of mandate alleging that the County violated CEQA and the State Planning and Zoning Law in approving the ordinance. The trial court held that the EIR violated CEQA regarding impacts on rangelands and from paving as an air pollutants mitigation measure. The petitioners appealed, arguing that the County violated CEQA in additional respects. The Court of Appeal agreed with the petitioners.

Water Supply Mitigation Measures

The County’s EIR concluded that the ordinance would have a significant and unavoidable impact on water supplies because implementation of the ordinance would deplete the County’s municipal and industrial water supplies. To mitigate this impact, the EIR proposed several mitigation measures. One measure provided that, to the extent feasible, applicants for permits under the ordinance shall increase or maximize the re-use of produced water. Produced water is groundwater that naturally occurs in oil and gas reservoirs brought to the surface with the extracted oil and gas and separated from the hydrocarbons after extraction. The Court of Appeal held that the requirement for applicants to increase or maximize their use of produced water violated CEQA because it merely set forth a generalized goal, rather than establishing specific performance standards that must be met. The court opined that were it to hold such a measure satisfied CEQA, lead agencies and project proponents—aware of the court’s precedent—would have scant incentive to define mitigation measures for other projects in specific terms. Instead, planning documents or ordinances adopted by local governments could merely state that permit applicants must reduce environmental impacts to the extent feasible. Allowing such an approach, the court reasoned, would undermine CEQA purpose of “systematically identifying” feasible mitigation measures that will reduce environmental impacts. (See Pub. Resources Code, § 21002.)

Another provision of the County’s water supply mitigation required that the five biggest oil industry users of municipal and industrial water work together to develop and implement a plan identifying new measures to reduce municipal and industrial water use by 2020. The court held that this mitigation measure—which unquestionably deferred formulation of mitigation—violated CEQA because it lacked specific performance standards to include in the plan. Moreover, the measure did not commit the County to the measures ultimately included in the plan. Further, it assigned the duty to implement the measure to unidentified third parties who might not agree to participate in the task or who might not act in good faith. Yet another flaw with this mitigation measure was that the plan was not required to be developed until 2020, whereas the ordinance took effect in 2015. Thus, the measure allowed permits for oil and gas activities to be issued without being subject to the measures contained in the plan. Accordingly, the measure violated the CEQA principle against delayed implementation of mitigation measures.

Another mitigation measure adopted by the County specified that “[i]n the County’s required participation for the formulation of a Groundwater Sustainability Agency [pursuant to the Sustainable Groundwater Management Act (Senate Bill 1281)], the Applicant shall work with the County to integrate into the Groundwater Sustainability Plan for the Tulare Lake-Kern Basin, best practices from the oil and gas industry to encourage the re-use of produced water from oil and gas activities.” The mitigation measure set a re-use “goal” of 30,000 acre-feet per year. The Court of Appeal held that this mitigation measure violated CEQA because the groundwater sustainability plan mentioned in the measure must be adopted by January 31, 2020—four years after the ordinance was approved.  Therefore, the measure was improperly deferred. Furthermore, the goal of re-using 30,000 acre-feet per year of produced water was merely a goal, and not an enforceable commitment, as required by CEQA.

The Court of Appeal further held that because the water supply mitigation measures were of unknown effectiveness, in order for the County to properly adopt a statement of overriding considerations under CEQA, the EIR must “(1) describe the mitigation measures that are available (i.e., currently feasible) and (2) identify and explain the uncertainty in the effectiveness of those measures.” The court reasoned that such a requirement is mandated by the general rule that an EIR must alert the public and decisionmakers of the significant problems a project would create and must discuss currently feasible mitigation measures.

Agricultural Mitigation

The County’s EIR found that, without mitigation, the project has the potential to convert Prime Farmland, Unique Farmland, or Farmland of Statewide Importance to non-agricultural use because the ordinance would allow oil and gas activities, including new wells, to be located on agricultural lands. The EIR concluded, however, that, with mitigation, this impact would be reduced to less than significant. The mitigation measure adopted by the County for this impact allowed permit applicants to comply by adopting one or more of four options (a through d). The court held that because not all of the options constituted adequate mitigation under CEQA, the County lacked substantial evidence to support its conclusion that the ordinance would have a less-than-significant impact on agriculture.

In particular, option “a” of the agricultural mitigation measure authorized the use of agricultural conservation easements at a 1:1 ratio (one acre of agricultural land conserved for every one acre converted to non-agricultural uses). The court held that conservation easements do not constitute adequate mitigation because they do not create new agricultural land to replace the agricultural land being converted to other uses. Rather, conservation easements simply prevent the future conversion of the agricultural land. In other words, conservation easements do not actually offset a project’s impacts on agriculture. Accordingly, the inclusion of option “a” in the agricultural mitigation measure rendered the mitigation measure ineffective.

Option “b” of the agricultural mitigation measure allowed for the purchase of conservation credits from an established agricultural mitigation bank. The court agreed with the petitioners that there was no evidence in the administrative record that such banks existed. Thus, the record lacked substantial evidence to support a finding that this option would actually mitigate agricultural impacts. Therefore, it was not sufficient mitigation under CEQA.

The court also concluded that the County had failed to adequately respond to comments suggesting that the County adopt a mitigation measure requiring the clustering of wells so that fewer acres of agricultural lands would be converted under the ordinance. The County’s response to such comments noted that the County’s General Plan includes a policy requiring the clustering of wells, but the response did not specifically address the feasibility of adopting a mitigation measure requiring well clustering. Therefore, court concluded that the County’s responses to comments failed to comply with the requirements of section 15088, subdivision (b) of the CEQA Guidelines, which require a “reasoned analysis” in response to comments raising “significant environmental issues.”

Noise Thresholds of Significance

To determine whether implementation of the ordinance would cause significant noise impacts, the County used a quantitative threshold of 65 dBA DNL, meaning that the ordinance would not cause a significant noise impact if noise levels stayed below that threshold. The court held that the County’s use of a single threshold violated CEQA because the threshold did not measure the increase in noise levels over ambient levels. Comments on the EIR, as well as the County’s own noise report that was appended to the Draft EIR, suggested using an increase of 5 dBA to determine whether the increase in noise above ambient levels constituted a significant impact. For unexplained reasons, the County did not do so. Instead, the County argued that it was entitled to substantial deference in selecting the significance thresholds. Although the court agreed that the County is entitled to deference in its choice of significance thresholds, the court held that the County’s use of an absolute noise threshold for evaluating all ambient noise impacts violated CEQA because it did not provide a “complete picture” of the noise impacts that may result from implementation of the ordinance.

Remedy

The County requested the court to exercise its equitable powers, which include the power to order the status quo preserved, and allow the ordinance to remain in effect while the County corrects the deficiencies in the EIR and mitigation measures. The court declined to do so. The court reasoned that the usual remedy in a CEQA case is to order the respondent to rescind its approvals; the court saw no reason not to do so in this case. Unlike other cases that allowed an ordinance that benefited the environment to remain in place, the oil and gas permitting ordinance was not adopted for the benefit of the environment.

The court also directed that the new EIR prepared by the County should include updated baselines for the water supply and air quality analyses because conditions have changed since the County issued the notice of preparation (NOP) of the original draft EIR that warrant updating the baseline.

California Supreme Court holds that CEQA requires EIRs to show a reasonable effort to substantively connect a project’s air quality impacts to likely health impacts

In a much-anticipated opinion, the California Supreme Court in Sierra Club v. County of Fresno (Dec. 24, 2018) 6 Cal.5th 502 held that portions of the air quality analysis in Fresno County’s EIR for the 942-acre Friant Ranch Specific Plan violated CEQA. In reaching this decision, the Court made four important holdings:  (1) when reviewing whether an EIR’s discussion of environmental effects “is sufficient to satisfy CEQA,” the court must be satisfied that the EIR “includes sufficient detail to enable those who did not participate in its preparation to understand and consider meaningfully the issues the proposed project raises”; (2) an EIR must show a “reasonable effort to substantively connect a project’s air quality impacts to likely health consequences”; (3) “a lead agency may leave open the possibility of employing better mitigation efforts consistent with improvements in technology without being deemed to have impermissibly deferred mitigation measures”; and (4) “[a] lead agency may adopt mitigation measures that do not reduce the project’s adverse impacts to less than significant levels, so long as the agency can demonstrate in good faith that the measures will at least be partially effective at mitigating the Project’s impacts.”

The Friant Ranch project is a Specific Plan calling for approximately 2,500 age-restricted (ages 55+) residential units, and other uses, including a commercial center and a neighborhood electric vehicle network. Fresno County’s EIR for the project generally discussed the health effects of air pollutants such as Reactive Organic Gases (ROG), oxides of nitrogen (NOx), and particulate matter (PM), but without predicting any specific health-related impacts resulting from the project. The EIR found that the project’s long-term operational air quality effects were significant and unavoidable, even with implementation of all feasible mitigation measures. The EIR recommended a mitigation measure that included a “substitution clause,” allowing the County, over the course of project build-out, to allow the use of new control technologies equally or more effective than those listed in the adopted measure.

After the trial court denied Sierra Club’s petition for writ of mandate, the Court of Appeal reversed, holding that the EIR’s air quality analysis and air quality mitigation measures violated CEQA. On October 1, 2014, the Supreme Court granted review of the appellate court’s decision. In a unanimous decision issued December 24, 2018, the Supreme Court reversed in part, and affirmed in part, the Court of Appeal’s decision.

The Court first considered which standard of judicial review applies to claims that an EIR’s discussion of environmental impacts is inadequate or insufficient. The Court explained that an EIR’s discussion of environmental impacts is adequate and sufficient where “the discussion sufficiently performs the function of facilitating ‘informed agency decisionmaking and informed public participation.” To that end, an EIR must “reasonably describe the nature and magnitude of the adverse effect.” The evaluation does not need to be exhaustive, but the courts will review the discussion “in light of what is reasonably feasible.” Claims that an EIR lacks analysis or omits the magnitude of the impact involve mixed questions of law and fact, and thus are generally reviewed de novo. The courts will apply the substantial evidence standard, however, to claims challenging the EIR’s underlying factual determinations, such as which methodologies to employ. “Thus, to the extent a mixed question requires a determination whether statutory criteria were satisfied, de novo review is appropriate; but to the extent factual questions predominate, a more deferential standard is warranted.”

The Court next considered whether the Friant Ranch EIR’s air quality analysis complied with CEQA. The Court held that an EIR must reflect “a reasonable effort to discuss relevant specifics regarding the connection between” and the estimated amount of a given pollutant the project will produce and the health impacts associated with that pollutant. Further, the EIR must show a “reasonable effort to put into a meaningful context” the conclusion that the project will cause a significant air quality impact. Although CEQA does not mandate an in-depth health risk assessment, CEQA does require an EIR to adequately explain either (a) how “bare [emissions] numbers” translate to or create potential adverse health impacts; or (b) what the agency does know, and why, given existing scientific constraints, it cannot translate potential health impacts further.

With respect to the Friant Ranch EIR, the EIR quantified how many tons per year the project will generate of ROG and NOx (both of which are ozone precursors), but did not quantify how much ozone these emissions will create. Although the EIR explained that ozone can cause health impacts at exposures for 0.10 to 0.40 parts per million, this information was meaningless because the EIR did not estimate how much ozone the Project will generate. Nor did the EIR disclose at what levels of exposure PM, carbon monoxide, and sulfur dioxide would trigger adverse health impacts. In short, the EIR made “it impossible for the public to translate the bare numbers provided into adverse health impacts or to understand why such translation is not possible at this time (and what limited translation is, in fact, possible).”

The Court noted that, on remand, one possible topic to address would be the impact the Project would have on the number of days of nonattainment of air quality standards per year, but the Court stopped short of stating such a discussion is required. Instead, the County, as lead agency, has discretion in choosing the type of analysis to supply.

The Court further held that the EIR did not fulfill CEQA’s disclosure requirements in that it stated that the air quality mitigation would “substantially reduce” air quality impacts but failed to “accurately reflect the net health effect of proposed air quality mitigation measures.”

Next, the Court examined whether the air quality mitigation measure impermissibly deferred formulation of mitigation because it allowed the County to substitute equally or more effective measures in the future as the Project builds out. The Court held that this substitution clause did not constitute impermissible deferral of mitigation because it allows for “additional and presumably better mitigation measures when they become available,” consistent with CEQA’s goal of promoting environmental protection. The Court also explained that mitigation measures need not include quantitative performance standards. If the mitigation measures are at least partially effective, they comply with CEQA; this is true even if the measures will not reduce the project’s significant impacts to less-than-significant levels.

RMM attorneys Jim Moose, Tiffany Wright, and Laura Harris represented the Real Party in Interest in the case.

(Laura M. Harris)