Tag: CEQA

First District Holds Stipulated Federal Court Judgments Do Not Preclude Independent Review Under CEQA

In Tiburon Open Space Committee v. County of Marin (2022) 78 Cal.App.5th 700, the First District Court of Appeal held that Marin County properly limited the scope of its environmental review to comport with its legal obligations pursuant to two stipulated federal judgments. In the same vein, the Court rejected appellants’ claim challenging the scope of the EIR’s project description, which incorporated the constraints imposed by the judgments. The Court also rejected appellants’ claims that the County abused its discretion by rejecting a scaled down project alternative, and making several mitigation findings for impacts to traffic safety and density, a threatened species, and water supply and fire flow.

Background

Real Party in Interest, the Martha Company (Martha), owns a 110-acre property on a mountaintop in Marin County that overlooks the Town of Tiburon. For several decades, Martha attempted to develop single family homes on the property, yet all proposed projects befell to forceful opposition from residents of the Town of Tiburon and the County.

The current dispute is predated by two stints in federal court that resulted in stipulated judgements.

The first federal case occurred in 1975, when the County adopted a re-zoning measure that drastically reduced the number of residences Martha could build on the property from a minimum of 300 to a maximum of 34. Martha sued the County in federal district court, alleging the re-zoning constituted a regulatory taking of property. The case resolved in 1976 by stipulated settlement that (1) Martha could develop no fewer than 43 single family homes on a minimum of half-acre lots; (2) Martha could place some homes on portions of the property named the Ridge and the Upland Greenbelt; and (3) 43 single family homes on half-acre lots is consistent with the goals of the County’s general plan while allowing owners a feasible economic use of their property.

Between federal cases, Martha submitted a project proposal to the County, which directed Martha to file an application with the Town of Tiburon for approval. The Town conducted years of environmental study without rendering a decision, and eventually Martha withdrew its application. In 2005, Martha submitted a new project proposal. The County refused to process Martha’s second application just as it refused to process the first.

The County returned to federal court, seeking relief from the 1976 stipulated settlement. It alleged that California environmental laws had changed in the 30 years since 1976, such that it would be against public policy of the state to “allow a development of this magnitude, on environmentally sensitive and constrained land to proceed without the development and density being subject to CEQA review.” The district court dismissed the County’s complaint and granted the 2007 stipulated settlement, which set a timeline and procedures for enforcing the 1976 judgement.

Martha submitted a third development application for a 43-unit residential development project (the Project). The County circulated a draft EIR for the project in 2011.

In 2017, after years of administrative proceedings, further environmental review, and litigation concerning the project, Martha submitted a modified Master Plan of the development project to comply with the County Board of Supervisors’ request for a “more specific proposal.” Additionally, Martha agreed to a phased review of its development application. The Marin County Board of Supervisors certified the EIR by a 3-2 vote.

Tiburon Open Space Committee and the Town of Tiburon (collectively, the Town) each filed petitions for a Writ of Mandate against the County, alleging the EIR was legally inadequate in numerous respects, and the County’s review process was legally deficient. The trial court denied both petitions. The Town appealed.

The Court of Appeal’s Decision

Implications of the Stipulated Judgments

The Town’s principal allegation was that the County violated CEQA by failing to exercise the full measure of its statutory discretion when it complied with the stipulated judgements. In essence, the Town claimed the County illegally “contracted away its police powers.”

The Court of Appeal rejected these claims, explaining that the Board proceeded “along lines that are in fact expressly embedded in CEQA,” and did not circumvent its obligations under the statute.

First, the Court concluded that the EIR was not a “pro forma” exercise, nor had a preordained outcome as the Town contends. The Court underscored the fact that the EIR underwent several revisions, spanned 850 pages, involved consultation with other agencies, provided meaningful opportunity for public review and comment, and cost considerable time and money. Furthermore, the County retained discretion to shape the contours of the Project during the later phases of approval. Specifically, the Court noted, the EIR proceedings were not “rushed, perfunctory, or short circuited” and were “utterly at odds with the conduct of a public entity that believed itself free to blow off CEQA.”

Second, the County appropriately limited its CEQA analysis to the scope of its discretionary authority. The Court cited Sequoyah Hills Homeowners Association v. City of Oakland (1993) 23 Cal.App.4th 704 for the holding that an agency’s discretion under CEQA is limited by its own legal obligations. For example, the Court remarked that CEQA imposes a duty to mitigate environmental impacts only to the extent feasible. Applied here, the County had a legal obligation to comply with the conditions imposed by the stipulated judgements. Since the stipulated judgments limit the scope of the County’s discretion by requiring certain conditions for the project be met, they also limited the scope of its environmental review. Thus, while legally feasible alternatives and mitigation measures had to be examined by the County, alternatives or mitigation measures that contradicted its obligations under the stipulated judgements were legally infeasible and did not need to be examined. Accordingly, the Court held that the County’s approval of a project that complied with the conditions set by the stipulated settlements was proper.

The Town also raised a corollary argument that the stipulated judgements deprived the members of the County Board of Supervisors from exercising their “independent judgement.” The Court refuted this argument by highlighting its logical flaw; that is, if it can be said that federal judgements are not binding on a public official’s independent discretion, then it can equally be said that inconvenient provisions of state law, namely CEQA, are not binding on independent discretion either.

The Court therefore concluded that the EIR fulfilled the central purpose of CEQA to “disclose to the public the reasons why a governmental agency approved the project in the manner the agency chose,” and the County’s review process appropriately limited the scope of its environmental review to match its discretionary authority.

Project Description

The Court also rejected the Town’s claim that Final EIR’s 34-page project description was “artificially narrow” because it incorporated the legal constraints imposed by the stipulated judgments. The Court explained that the project description provided more detail than CEQA requires, and this argument was a mere variation of the claim that the County “abdicated” its responsibilities under CEQA by complying with the judgments—which it already rejected.

Alternatives

The Court held that the County did not abuse its discretion by rejecting a 32-unit alternative because that alternative was legally infeasible due to the legal requirements imposed by the stipulated judgments. It emphasized that an EIR is not required to review infeasible alternatives “even when such alternatives might be imagined to be environmentally superior.”

Environmental Impacts and Mitigation Findings

The Court of Appeal held that substantial evidence supported the County’s findings that several of the Project’s impacts would be mitigated to a less than significant level.

First, the Court upheld the County’s finding that traffic safety impacts could be mitigated by measures that required the Town to implement them—including removing traffic obstacles such as trash receptacles and enforcing speed limits on narrow winding road. The Court explained that CEQA only requires a “reasonable plan” for mitigation and allows for the approval of a project with a finding that mitigation should be adopted by another entity that has exclusive jurisdiction.

The Court also concluded that substantial evidence supported the EIR’s “level of service” (LOS) methodology for calculating the Project’s traffic density impacts, noting that LOS was an established standard required in the County. Quoting the trial court, the Court of Appeal held that the traffic analyst was entitled to rely on this methodology because it “had the prerogative to resolve conflicting factual conclusions” about the traffic congestion impacts of the Project.

The Court upheld the EIR’s use of best management practices (BMPs) for the mitigation of impacts on the threatened California red-legged frog. It explained that the BMPs did not defer mitigation, but rather qualified as “revisions in the project plans” agreed to by Martha because they were accepted as conditions of approval. Further, the Court noted, the BMPs were already in existence because they were included in the Project’s Stormwater Control Plan. Accordingly, the Court determined that the BMPs were incorporated by reference in the EIR.

The Town’s claims regarding the County’s water supply and fire flow mitigation measures were barred due to its failure to exhaust the issues during the County’s administrative process. The Court nonetheless concluded that the measures requiring Martha to work with local water and fire authorities were sufficient and would not allow Martha to do “nothing” because failing to comply would result in the County not issuing the permits required to proceed with the Project. The Court also concluded that the Town’s demand for more detail in the water supply plan went beyond what CEQA requires.

Lastly, the Court concluded that substantial evidence—specifically, construction and traffic experts’ opinions—supported the County’s determination that mitigation would reduce the Project’s safety impacts resulting from a temporary on-site construction road to less than significant. The Court explained that alternative evidence does not negate the substantial evidence that the County relied on, and that it is within the agency’s discretion to evaluate the credibility of such evidence. It also emphasized that the safety risks were limited to the workers building the Project, and CEQA only requires review of safety risks posed to the public in general.

The Court’s Closing Remarks

The Court of Appeal concluded its opinion by expressing its inclination to afford the trial court’s decision great weight in counties with designated CEQA judges. The Court also generally criticized the use of CEQA lawsuits as “tool[s] of obstruction,” especially for housing developments.

— Jordan Wright & Veronika Morrison

First District Holds Petitioner Exhausted Its Remedies by Raising General Objections That the Project Site Should Be Preserved as Open Space, Finds “No Project” Alternative Analysis Defective

In the published portions of Save the Hill Group v. City of Livermore (2022) 76 Cal.App.5th 1092, the First District Court of Appeal held that Petitioner Save the Hill’s failure to specifically reference the recirculated EIR or the no-project alternative in its comments to the City Council did not bar its CEQA claims regarding preservation of the Project site.

Background

This case involves the City of Livermore’s approval of a development application for a housing development in the Garaventa Hills. The Project underwent multiple revisions, and the Project at issue is a scaled-down version of the original 76-unit residential development. The final Project is a 44-unit development with pedestrian across Altamont creek that also serves as a secondary emergency vehicle access road. The City published a Recirculated Final EIR (RFEIR) for this final revised Project.

Save the Hill filed a petition for writ of mandate challenging the City’s approval of the Project and certification of the RFEIR for failure to consider significant environmental impacts, adequately investigate and evaluate the no-project alternative, and mitigate significant environmental impacts. The trial court denied the petition, determining that Save the Hill failed to exhaust its administrative remedies in challenging the RFEIR. Save the Hill appealed.

The Court of Appeal’s Decision

Exhaustion

The Court of Appeal held that Save the Hill did not fail to exhaust its administrative remedies before challenging the City’s failure to evaluate the no-project alternative. While Save the Hill did not mention the environmental documents or the lack of a no-project alternative specifically, it did express its desire to preserve the Project site as open space. The Court emphasized that CEQA does not require public interest groups such as Save the Hill—which are often unrepresented by counsel at administrative hearings—to do more than “fairly apprise” the agency of their complaints to preserve them for appeal.

Several Save the Hill representatives voiced support for preserving the Project site as open space in perpetuity at the City Council hearing for the RFEIR’s certification. These comments sparked questions from city councilmembers regarding the possibility of preserving the Project site and a discussion of available funding to purchase Garaventa Hills for conservation. This option was shut down by the City Attorney, who advised the City Council that its evaluation should be limited to the Project as set before them, and that if it were to change the zoning to permanent open space on the property, the City would likely face a takings lawsuit.

The Court determined that these comments and the ensuing discussion reflected the City Council’s consideration of a no-project alternative as a result of Save the Hill’s objections. It concluded that Save the Hill’s failure to specifically refer to the RFEIR’s Project alternatives evaluation was immaterial to the fact that it fairly appraised the City of its position. The court further explained that even if Save the Hill framed its arguments in the context of the RFEIR’s no-project alternative, “the evidence is overwhelmingly that, had it done so, the result would have been the same: [t]he City would have rejected the group’s proposal and certified the RFEIR” because it was improperly instructed to limit its focus to the presented Project.

Accordingly, the Court held that an exception to the exhaustion requirement applied because the aggrieved party—Save the Hill—could “positively state” what the lead agency’s decision would be in its particular case.

No Project Alternative Analysis

On the merits of Save the Hill’s alternative analysis claim, the Court held that the RFEIR failed to disclose and analyze information regarding the availability of funding sources that could have been used to purchase and permanently conserve the Project site. The Court explained that zoning changes are within the City’s police power, and the RFEIR accordingly should have discussed the feasibility of rezoning the site as permanent open space.

Mitigation Measures Adequacy

Save the Hill asserted that the mitigation measures for impacts to vernal pool fairy shrimp were inadequate because they would only be implemented if the fairy shrimp were detected at the site. The Court explained that CEQA allows deferred mitigation where the agency commits to achieving specific performance standards, which it did here, and that the mitigation measures were adequate because the RFEIR assumed that the fairy shrimp were present.

The Court also held that the preservation of an 85-acre compensatory mitigation site was adequate, despite Save the Hill’s contention that the City’s General Plan required the location to be preserved as open space. The Court concluded that the General Plan is “merely aspirational,” while the RFEIR’s mitigation measure created a “perpetual legal restraint on development” at the site, including requiring funding for upkeep and enforcement. Moreover, distinguishing this case from King & Gardiner Farms, LLC v. County of Kern (2020) 45 Cal.App.5th 814 (“King”), the Court explained that this Project involved the loss of only 32 acres—as opposed to the loss of 6,450 acres in King—and CEQA does not require mitigation measures to “completely eliminate the environmental impacts of a project.”

Hydrological Impacts Adequacy

The Court held that the City’s finding of no significant hydrological impacts was supported by substantial evidence because Save the Hill failed to refute the City’s points in its reply brief. The Court refused to afford any weight to Save the Hill’s argument that the Project would degrade downstream water quality because a larger development project (which originally included this Project) would have a significant downstream water quality impact. The Court determined that impacts from a project almost 200 acres larger than this Project were not relevant.

Settlement Agreement Obligation Claims

Lastly, the Court held that that Save the Hill forfeited its claim that the City violated CEQA by failing to preserve the Project site to satisfy its obligations under two settlement agreements by failing to raise the issue prior to appeal. Moreover, Save the Hill was not a party to either settlement agreement and thus lacked standing to enforce those obligations.

FIRST DISTRICT HOLDS RESIDENTIAL DEVELOPMENT PROJECT THAT IS CONSISTENT WITH SPECIFIC PLAN AREA IS EXEMPT FROM FURTHER ENVIRONMENTAL REVIEW

In Citizens’ Committee to Complete the Refuge v. City of Newark (2021) 74 Cal.App.5th 460, the First District Court of Appeal upheld the city’s determination that a residential project within a specific plan area was exempt from further environmental review under Government Code section 65457, which provides an exemption from CEQA for housing development proposals that follow a city’s specific plan.

Background

In 2010, the city certified an environmental impact report (EIR) for a specific plan. The specific plan allowed for development of up to 1,260 residential units, and a golf course and related facilities spread across identified subareas (Areas 3 and 4). Area 4 contained wetland habitat for the salt marsh harvest mouse, a state-protected species. After petitioners filed suit under CEQA, the trial court found several deficiencies with the EIR.

In response, the city prepared a recirculated EIR (REIR), which stated that it was a program-level analysis of the impacts related to development of housing and the golf course in Areas 3 and 4 because the final design of those components was not yet known. In March 2015, the city certified the final REIR and re-adopted the 2010 specific plan.

In 2019, the developer submitted a proposed subdivision map for approval of 469 residential lots, omitting the golf course that was previously authorized by the specific plan.

The city prepared a checklist to determine whether the REIR adequately analyzed the environmental impacts of the proposed subdivision map and concluded that the project was consistent with the specific plan and that there were no changed circumstances or new information that might trigger additional environmental review. Accordingly, the city determined the project qualified for the statutory CEQA exemption under Government Code section 65457.

Petitioners challenged the city’s determination, arguing that a subsequent EIR was required due to changes in the project showing that it would have new significant impacts on the endangered harvest mouse.

Court of Appeal’s Decision

To qualify for the Government Code section 65457 exemption, a project must be for residential development, must be consistent with a specific plan for which an EIR was previously certified, and circumstances requiring subsequent environmental review (Pub. Resources Code, § 21166; CEQA Guidelines, § 15162) must not be present.

Petitioners alleged that three changes to the project created new significant impacts triggering the requirement for a subsequent EIR:

(1) Fill of only uplands and not wetlands inhibited wetland migration;

(2) Omission of the golf course deprived the harvest mouse of escape habitat; and

(3) Use of riprap on the banks of elevated upland increased predation of the harvest mouse.

The court disagreed, finding that substantial evidence supported the city’s conclusion that none of the changes significantly increased the impacts on the harvest mouse beyond what the REIR analyzed, i.e., the impacts of the complete development of all of Area 4. The court noted that the project as approved would develop fewer total acres and include far fewer residential units than analyzed in the REIR.

In regard to petitioners’ specific arguments of new impacts, the court held the REIR addressed the impact of loss of upland escape habitat and found that the impact would be less than significant because the uplands did not provide high quality transitional habitat as they were regularly used for agriculture. The project would develop less upland than previously analyzed, meaning the project would eliminate less, not more, upland escape habitat. Additionally, because of the low value of upland habitat, the REIR’s less-than-significant determination did not depend on the golf course continuing to provide upland habitat. Accordingly, the elimination of the golf course did not affect that determination.

While the REIR did not discuss the use of riprap to stabilize the slopes of the filled and raised development areas, the court found this did not require subsequent environmental review because the REIR already examined the issue of rat predation on the harvest mouse and petitioners cited to no evidence that the riprap would substantially increase the severity of predation effects. The court acknowledged that there could be some potential increase in predation due to riprap but recognized that the Section 65457 exemption sets a higher threshold for environmental review. Like other statutory exemptions, the court said, Section 65457 reflects the Legislature’s determination that the interest promoted, which here was to increase the housing supply, was important enough to justify foregoing the benefits of environmental review.

The court also rejected petitioners’ claim that changed circumstances and new information related to sea level rise triggered subsequent review. Petitioners argued that the city was required, due to new scientific insights concerning the amount and rate of sea level rise, to analyze whether the project would exacerbate the effects of sea level rise because of how the project would interact with wetlands in the area (e.g., wetland migration). Even assuming wetland migration must be analyzed under CEQA, the court found that it was mentioned in the original 2010 EIR and the REIR assumed that all developable areas would be impacted. Accordingly, the court concluded that petitioners should have raised this argument in response to the REIR, or even the 2010 EIR.

Finally, the court rejected petitioners’ claim that an adaptive management approach to sea level rise was impermissibly deferred mitigation. The court held that the city’s adaptive responses were not mitigation because sea level rise is not an environmental impact caused by the project that needs to be analyzed under CEQA.

– Nina Berglund

FOURTH DISTRICT UPHOLDS EIR FOR MULTI-FAMILY HOUSING PROJECT AND FINDS CITY PROPERLY USED A PLANNED DEVELOPMENT PERMIT TO ALLOW A VARIATION FROM CONVENTIONAL ZONING REGULATIONS

In Ocean Street Extension Neighborhood Association v. City of Santa Cruz (2022) 73 Cal.App.5th 985, the Fourth District Court of Appeal held that an EIR for a multi-family housing project properly relied on the biological resources analysis and mitigation measures identified in the initial study for the project, and sufficiently addressed the project objectives, alternatives, and cumulative impacts to water supply and traffic. Reversing the trial court, the Court of Appeal also held that the City complied with its municipal code by using a planned development permit as a variation from its conventional slope regulations.

Background

The proposed project consisted of a 40-unit residential complex on a vacant lot in the City of Santa Cruz. The City prepared an initial study that discussed, among other topics, biological impacts that would be reduced to less-than-significant with mitigation, and later circulated a draft EIR and recirculated draft EIR before certifying the final EIR. The City Council approved a reduced-housing alternative with 32 units.

Along with a general plan amendment, rezone, and other entitlements, the City approved a planned development permit (PDP) to allow a variation from the conventional slope regulations in the City’s zoning code.

The Ocean Street Extension Neighborhood Association (OSENA) filed a petition for writ of mandate challenging the EIR and the City’s approval of the PDP. The trial court ruled that the City complied with CEQA, but found the City violated its municipal code by not requiring compliance with the conventional slope regulations. OSENA appealed and the City and Real Parties in Interest cross-appealed.

The Court of Appeal’s Decision

CEQA and Adequacy of the EIR

Upholding the trail court’s ruling on the CEQA claims, the Court of Appeal concluded that the EIR was adequate. The court held that impacts that are less than significant with mitigation may be discussed in an initial study rather than in the EIR as long as the EIR fulfills its purpose as an informational document. The court noted that the EIR summarized the impacts and mitigation measures, and the EIR’s reference to the initial study—which was attached to the EIR as appendix—sufficiently alerted the public to the environmental issues and provided readers with adequate information. Accordingly, the court determined that it was appropriate for the EIR to rely on the biological resources analysis and mitigation measures identified in the initial study.

The court also rejected OSENA’s argument that the mitigation measures were vague and improperly deferred because OSENA failed to exhaust its administrative remedies as to this issue and did not raise it in the trial court proceedings. The court nonetheless explained that even if it considered this issue on the merits, it would reject OSENA’s arguments because the question of effectiveness of a mitigation measure is a factual one, which, in this case, was supported by substantial evidence in the record.

The court further concluded that the project’s objectives and alternatives analyses were adequate, and that OSENA’s arguments amounted to mere disagreement with the City’s conclusions. The court explained that rejecting or approving an alternative is a decision only for the decisionmakers, and they may reject alternatives that are undesirable for policy reasons or fail to meet project objectives. While the project objectives included specific targets, those objectives did not improperly restrict the range of alternatives analyzed in the EIR, and the City justified its reasons for rejecting alternatives with even less housing than the 32-unit alternative.

Additionally, the court determined that the EIR sufficiently analyzed the project’s cumulative impacts on water supply and traffic. Regarding water supply, the court explained that the EIR’s analysis properly considered the water supply impact in light of city-wide needs and future demand, and properly relied on the City’s Urban Water Management Plan. Regarding traffic, the court held that OSENA’s arguments challenging the EIR’s analysis of LOS impacts were moot because CEQA Guidelines section 15064.3, which took effect after the case was initiated, provides that a project’s effects on automobile delay shall not constitute a significant environmental impact.

Therefore, the Court affirmed the portion of the trial court’s order and judgment concluding that the City complied with CEQA.

Santa Cruz Municipal Code

Reversing the trial court’s ruling on OSENA’s municipal code claims, the Court of Appeal held that the City did not violate its municipal code by granting a PDP without also requiring compliance with the conventional slope modification regulation procedures in its zoning code. The City’s PDP ordinance allows a variation from certain zoning regulations including “Slope Regulations Modifications, pursuant to procedures set forth in Chapter 24.08, Part 9 (Slope Regulations Modifications).” Rejecting OSENA’s claim that the City was required to comply with the conventional regulations in Chapter 24.08, Part 9, in addition to the requirements for a PDP, the court explained that the City should be afforded deference in the interpretation of its own municipal code. The court upheld the City’s determination that the granting of a PDP does not require compliance with the conventional slope regulations, as this interpretation was consistent with the text and purpose of the ordinance and interpreting the PDP ordinance as requiring compliance with both the PDP ordinance and the slope regulations would have served no readily apparent purpose.

RMM Partners Christopher L. Stiles and Tiffany K. Wright represented the Real Parties in Interest in this case.  Chris Stiles argued the case in Court of Appeal on behalf of the City and Real Parties.

-Veronika S. Morrison

THIRD DISTRICT UPHOLDS CITY’S DETERMINATION THAT PROJECT WAS CONSISTENT WITH APPLICABLE PLANNING DOCUMENTS

In Old East Davis Neighborhood Association v. City of Davis (2021) 73 Cal.App.5th 895, the Third District found the trial court erred in concluding the record did not support the city’s decision that a mixed-use development project was consistent with the general plan, specific plan, and design guidelines. Rather, using the deferential standard of review applied to general plan consistency determinations, the court found sufficient evidence to support that the city’s consistency determination was not unreasonable.

Background

The challenged project is a four-story mixed-use building development offering ground floor retail and apartment units on the three upper levels. The project is located in an area referred to as a “transition area” between the Downtown Core and the Old East Davis residential neighborhood. Both the Downtown Core and the project site are subject to the Core Area Specific Plan and the Downtown and Traditional Residential Neighborhoods Design (DTRN) Guidelines.

A Sustainable Communities Environmental Assessment/Initial Study (SCEA) prepared for the project concluded the project would be consistent with the general plan and would adhere to the design guidelines.

The staff report recommending approval of the project found the project consistent with general plan policies requiring an “architectural fit” with the city’s existing scale and specific plan policies “encouraging more intense mixed-use development and accommodating buildings with floor areas up to three times the site area, while still maintaining scale transition and small city-character.” The report further explained that consistent with the DTRN guidelines the project had been designed to provide a transition area from Downtown to the Old East Neighborhood and to remain in scale with the adjacent area through use, in part, of stepped-back upper stories to concentrate building mass away from the nearby residential properties.

The city council approved the project finding it conformed with the general plan and the specific plan. Petitioner filed suit challenging the approval on the basis that the project failed to meet requirements for an SCEA assessment and that the project was inconsistent with applicable planning guidelines.

The trial court granted the petition in part reasoning that the project did not meet the general plan’s “fundamental policy” that it be a transition property. The city appealed and petitioner cross-appealed.

Court of Appeal’s Decision

On appeal, the city argued that the trial court failed to afford the appropriate deference to the city’s consistency determination. The appellate court agreed. Articulating the applicable standard of review, the court explained that a general plan consistency determination will only be reversed if it is unreasonable based on all the evidence in the record. It further noted that the city is uniquely competent to interpret adopted planning policies and the reviewing court’s role is only to decide whether the city considered the applicable policies and the extent to which the project conforms with those policies.

Applying the correct standard of review, the court found substantial evidence supported the city’s finding that the project serves as a “transition.” The court noted that the applicable planning documents did not provide a formula for determining what constitutes a “transition.” The determination instead rests on subjective criteria, e.g., “architectural fit” and “appropriate scale and character.” The court rejected petitioner’s arguments that the project could not be a transition between Downtown and Old East Davis because it was the largest building in the area, noting that nothing in the planning documents compels such a conclusion. Accordingly, the court held that the trial court erred in applying a formulistic approach that discounted the step-back design, the SCEA analysis, and other factors relied on by the city.

Petitioner also argued that the project violated DTRN guideline language stating that “a building shall appear to be in scale with traditional single-family houses along the street front” — asserting that the use of the word “shall” makes this language mandatory. The court disagreed. The DTRN guidelines explained that, unlike standards, which use unequivocal language to prescribe minimum acceptable limits, guidelines are descriptive statements that illustrate a preferred course of action. Given this, the court held that the DTRN guideline language was “decidedly subjective.” Even if the language could be deemed mandatory, the court found that the city’s conclusion that the scale of the project was consistent with the DTRN guidelines was reasonable based on the evidence in the record.

Petitioner’s cross-appeal raised three issues with the SCEA that were raised in the trial court, but the judgment did not address. Petitioner argued 1) the SCEA failed to adequately analyze historic resources impacts to the Old East Davis conservation district; 2) the SCEA failed to analyze changes to the project that would be necessary if a lease on part of the project site were not renewed; and 3) the SCEA failed to adequately analyze potential hazardous material impacts associated with the historic railroad use of the site.

The Court of Appeal concluded that petitioner had forfeited its claims because it did not challenge the trial court’s tentative decision, and, in any case, found Petitioner’s claims to be without merit. First, the court found that SCEA concluded that the Old East Davis conservation district was not a historic resource. Second, the SCEA did analyze the potential loss of the lease, and the project approvals allowed for that contingency. Third, the SCEA analyzed the potential for discovering hazardous materials and concluded that any impacts would be addressed through standard regulatory conditions.

Lastly, petitioner argued that the project did not meet the requirements for relying on a SCEA because of potential impacts to historic resources and that the city’s findings under Public Resources Code, section 21155.2, were not supported by substantial evidence. The court rejected these arguments, concluding that petitioner relied on the wrong statutory provision in claiming the project did not qualify for a SCEA and failed to raise its challenge to the City’s findings in its opening brief.

– Nina Berglund

FIRST DISTRICT UPHOLDS STATE WATER RESOURCES CONTROL BOARD’S RELIANCE ON CEQA’s MINISTERIAL EXEMPTION FOR REGISTRATION OF APPROPRIATION OF WATER FOR DOMESTIC USE UNDER THE WATER RIGHTS PERMITTING REFORM ACT

In Mission Peak v. State Water Resources Control Board (2021) 72 Cal.App.5th 873, the First District Court of Appeal held that the State Water Resources Control Board’s (Board’s) registration process is ministerial and therefore exempt from CEQA.

Background

The Water Rights Permitting Reform Act of 1988 permits eligible persons to acquire a right to appropriate up to 10 acre-feet per year of  water for domestic or other specified uses by completing a registration process with the Board. Pursuant to this Act, the State Water Resources Control Board granted a small domestic use registration to two Alameda County property owners without conducting environmental review on the premise that the action was ministerial and thereby did not trigger CEQA.

Mission Peak Conservancy and Kelly Abreau (collectively, Mission Peak) sued the Board, alleging that it violated CEQA by approving the registration without conducting CEQA review. Mission Peak contended that the Board’s approval was discretionary and that it should have denied the registration because the property owners did not qualify for small domestic use and also because their registration form contained false information. The Board filed a demurrer, which the trial court sustained without leave to amend. Mission Peak appealed.

Court of Appeal’s Decision

The Court of Appeal determined that the Board’s registration process was indeed a ministerial act, not discretionary, and was therefore exempt from CEQA pursuant to Public Resources Code section 21080, subdivision (b)(1). As the court explained, “[m]inisterial projects involve ‘little or no personal judgment by the public official as to the wisdom or manner of carrying out the project.’ (Guidelines, § 15369.) . . . The test is whether the law governing the agency’s decision to approve the project gives it authority to require changes that would lessen the project’s environmental effects.”

The court determined the Board did not have such authority here. Although the Board has statutory authority to impose general conditions applicable to all registrations, it did not have authority “to place conditions on the . . . registration to lessen its environmental effects.” The Board determines whether a registration is compliant by applying a checklist of fixed criteria, and the registration is automatically deemed complete if it meets these criteria. Accordingly, there is no discretion involved in the registration, and it is therefore not subject to CEQA.

Specifically, the Court rejected Mission Peak’s argument that “a different agency, the Department of Fish and Wildlife, has discretion to impose conditions that could ameliorate the project’s environmental impacts” and therefore the the process is discretionary. Not so. As the court explained, another agency’s discretionary authority for its review cannot be imputed to the Board. Mission Peak then argued that “the project did not satisfy the requirements for a small domestic use registration because the [applicant] misrepresented facts,” and thereby the Board did have discretion in that it could deny the project or request changes to meet program requirements. But, “the test is whether the Board had the legal authority to impose environmentally beneficial changes as conditions of the project,” not whether the agency could request changes on an application or deny it.  Lastly, Mission Peak argued that the Board violated CEQA because the project did not meet program requirements. The court pointed out that “this is simply an argument that the Board made an erroneous ministerial decisions.” And such an error is not the basis for a CEQA claim. Plainly stated, “CEQA does not regulate ministerial decisions—full stop.”

– Veronika S. Morrison

SIXTH DISTRICT HOLDS COASTAL COMMISSION VIOLATED CEQA BY FAILING TO COMPLETE ENVIRONMENTAL REVIEW OF COASTAL DEVELOPMENT PERMIT PRIOR TO PROJECT APPROVAL

In Friends, Artists, and Neighbors of Elkhorn Slough v. California Coastal Commission (2021) 72 Cal.App.5th 666, the Sixth District Court of Appeal held that the California Coastal Commission (CCC) violated CEQA by analyzing a coastal development permit’s environmental impacts and adopting findings in support thereof after it had approved the permit and underlying project. Although the CCC is authorized to issue “revised findings” when the Commission’s action differs from what was proposed in the staff report, the court held that the revised findings in this case went too far and were an improper pot-hoc rationalization.

Background

In 2000, Real Party in Interest Heritage/Western Communities, Ltd., applied to the County of Monterey for a combined development permit and coastal development permit (CDP) for the Rancho Los robles Subdivision. The project proposed more than 100 residential units on a commercial parcel. Monterey County prepared an EIR containing several alternatives, including one with a reduced number of units.

In 2008, the County Planning Commission recommended denying the project due to water supply and traffic congestion issues. Heritage/Western appealed the denial to the County Board of Supervisors. The Board disagreed with the Planning Commission and approved the project. The Board also certified the EIR and adopted a statement of overriding considerations regarding significant and avoidable impacts to traffic, groundwater, and seawater intrusion.

In 2009, Friends, Artists, and Neighbors of Elkhorn Slough (FANS) appealed the Board’s decision to the CCC, alongside two Coastal Commissioners. CCC staff issued a staff report recommending denial of the CDP primarily due to lack of adequate water supply. The staff report concluded further analysis for certain issues was unwarranted in light of staff’s recommendation to deny the permit.

On November 8, 2017, the CCC held a de novo hearing and voted to approve the CDP, despite staff recommending denial.

In August 2018, CCC staff issued a subsequent report, containing revised findings in support of the CCC’s approval of the CDP. The 2018 report concluded that water supply was no longer an issue that necessitated denying the project. The 2018 staff report also considered other impacts previously identified in the 2017 report and determined they were no longer relevant or significant, and that staff’s prior conditions of approval would still apply to the project but be adjusted where necessary and implemented in a manner consistent with the project as approved by the Commission. Finally, the report concluded that the project was consistent with CEQA because it adequately addressed any potential adverse impacts to coastal resources, and there were no additional feasible alternatives or mitigation measures that would substantially lessen adverse impacts. The CCC approved the revised findings at a public hearing on September 13, 2018, approximately ten months after the CDP was approved.

FANS filed a petition for writ of mandate challenging the CCC’s approval of the CDP. The trial court denied the petition, rejecting FANS’ assertion that the CCC violated CEQA by approving the project without conducting environmental review before making findings. FANS appealed.

Court of Appeal’s Decision

On appeal, FANS asserted that the CCC failed to employ the proper procedures required by CEQA and the Coastal Act because its “revised findings” were a post-hoc rationalization for the CCC’s prior decision to approve the project and went beyond what was permitted by the CCC’s regulations. The Court of Appeal agreed and reversed the trial court.

The Court of Appeal outlined the steps for seeking CCC review of an approved CDP application and noted that the Commission’s de novo review of a permit application mimics CEQA’s environmental review process. The analysis and recommendation in a staff report must be accompanied by specific findings regarding—among other factors—the project’s conformity with the Coastal Act and CEQA. If the CCC’s action on the project substantially differs from staff’s recommendation, the prevailing Commissioners must separately state the basis to allow staff to prepare a revised staff report with proposed revised findings that reflect the action taken by the Commissioners. Under section 13096 of the CCC’s regulations, a public hearing must be held before the revised findings are adopted. (Cal. Code Regs., tit. 13, § 13096, subd. (c).) After the hearing, the CCC must vote on whether to adopt the revised findings.

Based on the facts of the case, the court held that the CCC’s environmental review for the CDP was incomplete at the time of approval, and the revised finding did not make up for the shortcoming. The court determined that the CCC’s decision to approve the project relied on a staff report that failed to contain elements required by CEQA (and the Commission’s certified regulatory program), including project alternatives, feasible mitigation measures to substantially lessen significant adverse effects, and conditions of approval.

In reaching its conclusion, the court explained the importance of these factors: “Requiring specific findings about alternatives and mitigation measures ‘ensures there is evidence of the public agency’s actual consideration of alternatives and mitigation measures, and reveals to citizens the analytical process by which the public agency arrived at its decision.’ [Citation.]” (Opinion, p. 32.) Through this lens, the court clarified that section 13096 “requires commissioners to set forth the analytic route between the evidence and the action at the hearing before approval.” The court further observed that no prior case law involved facts similar to this one, where the CCC’s environmental analysis was this incomplete at the time a CDP was approved. Accordingly, the court found that the CCC abused its discretion because it was required to conduct the analysis before it approved the project.

– Bridget McDonald

FOURTH DISTRICT UPHOLDS EIR FOR ROADWAY CONNECTION PROJECT AND HOLDS CITY’S QUASI-LEGISLATIVE APPROVALS WERE NOT SUBJECT TO PROCEDURAL DUE PROCESS REQUIREMENTS

In Save Civita Because Sudberry Won’t v. City of San Diego (2021) 72 Cal.App.5th 957, a partially published opinion, the Fourth District Court of Appeal held that the City of San Diego did not violate CEQA by failing to summarize revisions made in its recirculated draft EIR, and that the City’s certification of the Final EIR and approval of the project were quasi-legislative acts not subject to procedural due process requirements.

Background

In 2008, as part of an alternative to a proposed mixed-use development project, the City of San Diego proposed a four-lane major roadway in Mission Valley that would directly connect the development to local roadways. This connector roadway required an amendment to the Serra Mesa Community Plan (SMCP) and the City’s General Plan.

In April 2016, the City issued examined this connector roadway as its own project and prepared a programmatic draft EIR (PDEIR) for the SMCP and General Plan amendments. In March 2017, when roadway construction became foreseeable and upon a large volume of public comment, the City issued a revised and recirculated draft EIR (RE-DEIR) that looked at both the programmatic portion of the project, the adoption of amendments, as well as the actual construction of the roadway. In August 2017, the City issued the Final EIR for the project. Also in August 2017, the Planning Commission voted unanimously, with one member recusing, to recommend approval of the project and certification of the FEIR, with the City Council’s Smart Growth & Land Use Committee voting the same a month later. The City Council certified the Final EIR and approved the project in October 2017.

Save Civita Because Sudberry Won’t (Save Civita) filed a petition for writ of mandate and complaint for declaratory and injunctive relief challenging the City’s certification of the Final EIR and approval of the project on several grounds, namely here that it violated the requirement in CEQA Guidelines section 15088.5, subdivision (g) that a recirculated EIR summarize the revisions made to the prior EIR, and also that it violated procedural due process rights. The trial court denied the petition and complaint. Save Civita appealed.

The Court of Appeal’s Decision

Save Civita argued that the City violated CEQA Guidelines section 15088.5, subdivision (g), because it failed to summarize the changes in the RE-DEIR from the PDEIR, thereby forcing readers to “‘leaf through thousands of pages,’” and cause them “‘to have the mistaken belief’” that the two EIRs address the same project. The Court of Appeal disagreed, holding that statements in the RE-DEIR adequately summarized the changes to the PDEIR, and that these summary provisions informed the public that the revisions to the PDEIR were extensive and the PDEIR had been effectively “replaced” by the RE-DEIR. To make its determination, the court also looked to section 15088.5, subdivision (f), which requires that an agency inform the public that, when an EIR is so substantially revised that the document is recirculated, then comments on the prior EIR will not receive a response. The City fulfilled this criteria.

Furthermore, the court concluded that even if the City had failed to comply with the summation requirements of section 15088.5, any such failure was not prejudicial because it did not deprive the public of a meaningful opportunity to discuss and critique the project. Specifically, the court noted that the administrative record contained “ample and vigorous” public discussion of the RE-DEIR, proof that there were not fatal obstacles to public discourse created by any absence of a revision summary.

Save Civita also argued that the City’s certification of the Final EIR and project approval violated the public’s procedural right to due process and a fair hearing because a member of the City Council, who voted to approve the project was, according to Save Civita, “‘a cheerleader for the Project’” who had predetermined his vote. The court foreclosed this claim by explaining that procedural due process requirements are applicable only to quasi-adjudicatory hearings. Here, the City’s actions were quasi-legislative because they involved the adoption of generally applicable rules on the basis of broad public policy. The project approved by the City and analyzed in its EIR—construction of the roadway and amendment of planning documents—were, as the court determined, matters of public policy that required it to assess a broad spectrum of community costs and benefits. Therefore, procedural due process did not apply.

– Veronika S. Morrison

Second District Holds That Labor Union’s Interest in CEQA Action Was Not Sufficiently Direct and Immediate for Permissive Intervention

In South Coast Air Quality Management District v. City of Los Angeles (2021) 71 Cal.App.5th 314, the Second District Court of Appeal upheld the trial court’s decision to deny a labor union’s motion for permissive intervention in a CEQA case.

Background

This case involved the City of Los Angeles’s issuance of a permit authorizing a shipping company owned by the Chinese government to construction of a terminal within the Port of Los Angeles. In 2008, the City completed an EIR that concluded that the project would have significant and unavoidable environmental impacts. The EIR incorporated over 50 mitigation and lease measures to reduce these impacts.

In 2020, the City prepared a revised EIR that eliminated some of the mitigation measures required in the 2008 EIR. The revised EIR also concluded that the project would have significant, unavoidable, and increased impacts on air quality, and that it would exceed a threshold for cancer risk. The 2020 EIR did not contain enforcement provisions for the mitigation measures, did not require a lease amendment, and did not require the project applicant to implement or pay for the mitigation measures.

The South Coast Air Quality Management District filed a petition for writ of mandate, claiming that the City violated CEQA by failing to enforce the measures required by the 2008 EIR, and certifying the 2020 EIR, allowing the project to operate under allegedly inferior measures.

The petition named the City of Los Angeles, the Los Angeles City Council, the Los Angeles Harbor Department, and the Los Angeles Board of Harbor Commissioners as respondents, and several shipping companies as real parties in interest.

The California Attorney General and the California Air Resources Board sought permissive intervention pursuant to Code of Civil Procedure section 387, subdivisions (d)(1) and (d)(2). The trial court granted both parties’ motions.

The International Longshore and Warehouse Union, Locals 13, 63, and 94 also sought permissive intervention, arguing that no existing party could advocate for its members’ interests adequately. Specifically, the Union claimed that it was the only party that could properly protect the 3,075 jobs at stake. The trial court denied the Union’s motion, determining that its interest was speculative and consequential, rather than direct and immediate, as required for permissive intervention. The Union appealed.

The Court of Appeal’s Decision

The Court of Appeal upheld the trial court’s denial of the Union’s motion for permissive intervention. The court explained that pursuant to Code of Civil Procedure section 387, the statute for permissive intervention, there must be a balancing of the interests of those affected by a judgment against the interests of the original parties in pursuing their case unburdened by others. It also emphasized that trial courts are afforded broad discretion to strike this balance, and that the reviewing court reviews for abuse of discretion—reversing only if the appellant establishes the decision results in a miscarriage of justice or exceeds the bounds of reason.

The court further explained that the Union failed to articulate any unique interest that was not already represented by the other parties. The court found that the Union’s position on the merits was duplicative, that it had no concerns with the actual environmental analysis in the 2020 EIR, and that it was not the only party advocating for a remedy that did not result in a shut down of the project or rescission of its permits. Therefore, the Court of Appeal concluded that it was reasonable for the trial court to determine that the Union’s participation in the case would be largely cumulative and would unduly complicate an already complex case involving numerous parties, and to accordingly deny the Union’s motion for permissive intervention.