Tag: Alternatives

Banning Ranch Conservancy v. City of Newport Beach

Banning Ranch Conservancy v. City of Newport Beach (2017) 2 Cal.5th 918

The California Supreme Court ruled that the Environmental Impact Report prepared for the proposed “Banning Ranch” project was inadequate because the EIR did not identify “environmentally sensitive habitat areas” (ESHA) under the Coastal Act that might be present on the property, and therefore did not consider mitigation measures and alternatives designed to reduce impacts on those areas. Although the project required a coastal development permit, and the Coastal Commission would make a determination regarding ESHA as part of that permit, the Court held the EIR had to include a prediction of where ESHA would likely be found in order to serve its information purposes under CEQA. Whit Manley argued the case for the City of Newport Beach.

First District Court of Appeal Upholds EIR for Plan Bay Area that Correctly Excluded Statewide Emissions Reductions in Developing Strategies to Meet SB 375’s Emissions Targets

In Bay Area Citizens v. Association of Bay Area Governments (2016) 248 Cal.App.4th 966, the First District Court of Appeal interpreted SB 375 as requiring the California Air Resources Board (Board) and regional agencies to set and meet the emissions reductions targets through regionally-developed land use and transportation strategies that are independent of existing statewide clean technology mandates. Therefore, the court of appeal upheld the Bay Area Metropolitan Transportation Commission and the Association of Bay Area Government’s (collectively, the Agencies) “Plan Bay Area” and its EIR, finding the opponent’s arguments failed because they were based on a misinterpretation of SB 375’s requirements.

SB 375 requires the Board to provide greenhouse gas emissions reduction targets to each region while taking into account statewide mandates such as the Low Carbon Fuel Standard and the New Vehicle Emissions Standards. Then, each regional metropolitan planning organization (MPO) must prepare a sustainable communities strategy to meet those targets. The Agencies prepared Plan Bay Area. The petitioners commented on the Plan’s EIR stating that the Agencies should have counted reductions expected from preexisting statewide mandates. When the Board’s staff conducted a technical review of the Plan, however, they stated that the Agencies had appropriately excluded greenhouse gas emissions reductions from other technology and fuel programs. The Board then issued an executive order with the staff’s technical report attached, accepting that Plan Bay Area, if implemented, would achieve the targets.

The petitioners alleged that the Agencies failed to comply with CEQA by incorrectly assuming that SB 375 compelled them to exclude compliance with statewide mandates when assessing strategies to meet emissions reductions targets. First, the court looked to the plain meaning and purpose of the statute and found that because the emissions reductions from the statewide mandates are projected to dwarf those achieved by SB 375, the whole statute would be superfluous if the MPOs were simply allowed to cite the expected reductions from preexisting initiatives. Further, the Board’s AB 32 Scoping Plan repeatedly emphasized that the regional land use and transportation strategies were distinct from the statewide mandates. Although the Board was required to take the statewide mandates into account when setting targets under SB 375, the statute did not require any specific approach and the board had discretion to instruct MPOs to exclude consideration of reductions expected from statewide mandates. The Board made this instruction clear when it approved of Plan Bay Area with the exclusion of reductions from statewide mandates.

On the alleged inadequacy of the Plan’s EIR, the court stated that the petitioner’s arguments were based on their misinterpretation of SB 375 and found the EIR adequate. The Agencies were not required to consider the appellants proposed alternative that relied on statewide mandates because, as discussed above, it did not comply with SB 375 and was therefore infeasible. Contrary to the appellants’ contentions, the EIR did not ignore statewide mandates. Consideration of the New Vehicle Emissions Standards and the Low Carbon Fuel standard were included when determining whether implementation of the Plan would result in a net increase in emissions and whether it would impede the goals of AB 32. Further, the court found that in light of the Agencies’ sufficient disclosures throughout the EIR, including when they did and did not consider statewide mandates, the appellant’s arguments amounted to an impermissible substantive attack on the plan.

Written by Sabrina S. Eshaghi

Court Rejects EIR for Pest Program, Finding Objectives Too Narrowly Defined, and Thus No Reasonable Range of Alternatives

The Third District Court of Appeal reversed the decision of the trial court and held that a programmatic EIR for a seven-year program to control an invasive pest violated CEQA. (North Coast Rivers Alliance v. Kawamura (2015) 243 Cal.App.4th 647. The draft EIR evaluated eradication of the light brown apple moth, but the California Department of Food and Agriculture adopted a program to control the moth due to intervening spread of the moth and ultimate infeasibility of eradication. The court held that even before new information on feasibility of eradication came to light, the EIR contained an impermissibly narrow project objective, resulting in omitted analysis of pest control as an alternative to eradication.

The light brown apple moth is native to Australia and was introduced to California in 2007. Its traits of eating plant leaves and buds, adapting to new plants, and multiplying rapidly posed a significant danger to California ecology and agriculture, including potential extinction of sensitive species. This threat prompted the CDFA to prepare an EIR for a moth eradication program.

The draft EIR included five “alternatives” to the program, which the court determined were not true alternatives, but were instead tools to achieve eradication. The tools focused on disrupting mating patterns and introducing pesticides and natural predators. The draft EIR did not evaluate control as an alternative to eradication, and stated that the two mechanisms were fundamentally different because eradication had an end date, but control could potentially continue forever. Although the certified final EIR was for the eradication program, the adopted findings evaluated a seven-year control program. The program’s objective was also changed from eradication to protecting food supply and California’s agricultural economy.

The court held that even without this last-minute change from eradication to control, the EIR violated CEQA because the EIR failed to analyze pest control as a reasonable alternative to the eradication program. The process of selecting alternatives, it stated, begins with the establishment of project objectives, and the project’s artificially narrow objective of eradication precluded evaluation of alternatives that might have lesser environmental effects. Rather, protection of plants and crops were “clearly” the objectives and underlying purpose of the eradication program. The revised objectives in the final EIR underscored this conclusion.

The EIR’s failure to analyze the alternative “infected the entire EIR insofar as it dismissed out of hand anything that would not achieve complete eradication” of the moth. Though the department claimed the approved control program was narrower (less intensive) than the eradication program, and therefore fit within that program, the failure to analyze the control program in the EIR left the department unable to support this assertion with substantial evidence. The court held the final EIR’s selection of an alternative not analyzed in the EIR was prejudicial error.

The court continued with petitioners’ other contentions despite having already found reversible error. The court held petitioners’ claims of insufficiency of the evidence did not constitute a separate grounds for reversal of the judgment, and petitioners failed to show reversible error regarding the “No-Program” alternative or the EIR’s impact analyses. The court did not address the cumulative impacts contentions, finding that the reversible error necessitated a new cumulative impacts discussion.

Third District Court of Appeal Upholds EIR for Sacramento Kings’ Downtown Arena Project

The Third District Court of Appeal held that the City did not prematurely commit to the arena project by entering into a nonbinding term sheet with the Sacramento Kings or by engaging in land acquisition through eminent domain before the EIR process was complete. The court further determined that the EIR included an appropriate range of alternatives and adequately analyzed traffic and safety impacts. Saltonstall v. City of Sacramento (Feb. 18, 2015) ___ Cal.App.4th ___, Case No. C077772.

The case involves a challenge to the certification of an EIR and approval of a new entertainment and sports arena in downtown Sacramento that will eventually house the Sacramento Kings. To facilitate the timely opening of the new downtown arena, the Legislature modified several deadlines under CEQA by adding section 21168.6.6 to the Public Resources Code.

The City certified the EIR and approved the project in May 2014. Opponents of the project immediately filed a lawsuit against the City and sought a preliminary injunction to stay construction. The trial court denied the preliminary injunction, and the Court of Appeal affirmed that decision. The appellate court ruled that petitioners failed to satisfy the requirements for a preliminary injunction and held that section 21168.6.6 was not unconstitutional. (Saltonstall v. City of Sacramento (2014) 231 Cal.App.4th 837.) The trial court subsequently rejected the lawsuit in its entirety. Petitioners appealed.

In the appeal, petitioners argued (1) the City violated CEQA by committing itself to the downtown arena project before completing the EIR process, (2) the City’s EIR failed to consider remodeling the current Sleep Train Arena as a feasible alternative to building a new downtown arena, (3) the EIR did not properly study the effects of the project on interstate traffic traveling on the nearby section of Interstate Highway 5, and (4) the City did not account for large outdoor crowds expected to congregate outside the downtown arena during events. Petitioners also argued that the trial court erred in denying their motion to augment the record and in denying their Public Records Act request to the City to produce e-mail communications with the NBA. The Court of Appeal rejected all of petitioners’ claims.

The Third District first dismissed the claim that the City prematurely committed itself to approving the project. Petitioners claimed the City violated CEQA by engaging in land acquisition for its preferred site and entering into a preliminary term sheet with Sacramento Basketball Holdings LLC before finishing the EIR. Rejecting this argument, the Court held that the City was allowed to engage in land acquisition for its preferred site before finishing its EIR under CEQA Guidelines section 15004 and Public Resources Code section 21168.6.6. Guidelines section 15004, subdivision (b)(2)(a), expressly provides that “agencies may designate a preferred site for CEQA review and may enter into land acquisition agreements when the agency has conditioned the agency’s future use of the site on CEQA compliance.” Moreover, Public Resources Code section 21168.6.6 expressly allowed the City to exercise its eminent domain power to acquire the 600 block of K Street as the site of the arena before finishing the EIR. Finally, the court held that the preliminary term sheet did not improperly commit the City to approving the arena as proposed. The preliminary nonbinding term sheet constituted an agreement to negotiate regarding the project and did not foreclose environmental review, mitigation, or even rejection of the project.

Turning to petitioners’ claim that the alternatives analysis was inadequate, the court held that the City was not required to study remodeling the current Sleep Train Arena as a project alternative in the EIR. The City studied a “no project” alternative involving continued use of the Sleep Train Arena and an alternative that involved building a new arena next to the current arena in Natomas. Both the no project and new Natomas arena alternatives failed to meet most of the City’s objectives for the project to revitalize its downtown area. The remodel alternative suggested by petitioners would have suffered the same problems of location that caused the City to reject the two Natomas-based alternatives. Noting that “infeasible alternatives that do not meet project objectives need not be studied[,]” the court held the Sleep Train Arena remodel alternative did not need to be analyzed.

The court next addressed petitioners’ claim that the EIR’s traffic analysis was defective for failure to adequately analyze interstate traffic on I–5. The EIR studied and disclosed existing problems with the nearby section of I–5 at peak traffic times as well as how the downtown arena project would worsen traffic congestion. The EIR reached the conclusion that levels of service would—at times—reach the worst rating given by Caltrans for traffic flow. Even with proposed mitigation measures, the City acknowledged the adverse impact of the project on I–5 traffic would be significant and unavoidable. While petitioners acknowledged the City did study local I–5 traffic congestion, they argued the study was inadequate for not considering “mainline” I–5 traffic ranging from Canada to Mexico. Rejecting this argument, the court explained that the City was not required to separately study the effect on interstate motorists who will be impacted in the same way as other, local motorists sharing the same section of I–5. The court also noted the EIR did account for mainline traffic because it used the sampling data of mainline freeway traffic collected by Caltrans.

Petitioners also argued the City’s traffic study was deficient because the EIR understated the number of persons who would surround the downtown arena. The court again was not persuaded. The City’s review of crowd size included a national survey of similar entertainment and sports facilities as well as review of crowd sizes during the Sleep Train Arena’s history. The court held that the City did not err “in declining to speculate that the same games played a few miles away would suddenly and inexplicably draw large crowds of persons who would not watch the game but simply mill about in the winter nighttime.”

Addressing petitioners’ final CEQA claim, the court held that petitioners’ contention regarding failure to study post-event crowd safety and potential for violence did not implicate CEQA because petitioners failed to show any potential for environmental impacts. Petitioners argued the EIR both understated the number of persons who can be expected to congregate around the downtown arena as well as their proclivities toward drunken violence. The court ruled that the argument focused on a social issue for which no environmental effect was described.

Finally, regarding petitioners’ attempt to augment the administrative record, the court held that their challenge to the trial court’s denial of their Public Records Act request seeking over 62,000 emails related to communications between the City and the NBA was not properly before the court. Denial of such a request is reviewed only by petition for writ of mandate, not direct appeal. The court also held that petitioners forfeited their argument regarding the introduction of certain additional materials because they failed to offer any meaningful analysis on the issue.

Third Appellate District Upholds Department of Fish and Wildlife EIR, But Finds Department Violated APA in Adopting Underground Regulations

The Third District Court of Appeal held that the California Department of Fish and Wildlife’s program EIR analyzing the Department’s statewide fish hatchery and stocking enterprise passed muster. The Department did not abuse its discretion in the manner it organized the EIR, analyzed the project, and mitigated numerous impacts. The court also found, however, that the Department had violated the Administrative Procedure Act (APA) by adopting three mitigation measures, which imposed new obligations on private aquaculture facilities and required the Department to perform new duties, without complying with APA procedures. Center for Biological Diversity v. Dept. of Fish and Wildlife (Feb. 10, 2015) ___ Cal.App.4th ___, Case No. C072486.

The Department operates 14 trout hatcheries and 10 salmon and steelhead hatcheries throughout the state, stocking fish at close to 1,000 locations each year. After CEQA’s enactment, the hatching and stocking enterprise was found categorically exempt from complying with CEQA. Subsequently, concerns arose regarding the enterprise’s impact on native and wild animals due to predation and genetic hybridization. To address these concerns, the Department developed aquatic biodiversity management plans and hatchery genetic management plans. Center for Biological Diversity sued the Department in 2006, and the trial court agreed with the Center that the enterprise was not categorically exempt from CEQA because it likely caused significant environmental impacts. The court in this prior suit ordered the Department to prepare an EIR and comply with CEQA.

The Department prepared a broad-scope, program EIR/environmental impact statement pursuant to that decision and to additionally comply with NEPA. The EIR analyzed the statewide hatchery and stocking enterprise, as well as three other programs, including the Fishing in the City Program (providing fishing opportunities in urban areas), and the Private Stocking Permit Program (authorizing fish stocking by private aquaculture facilities in private and public lakes and ponds). The Department selected operations from 2004 to 2008 as the baseline and identified more than 200 impacts on biological resources. The EIR proposed a number of mitigation measures to lessen these impacts, and laid out three project alternatives. The EIR did not consider closing the hatcheries or eliminating trout stocking as alternatives.

The Department’s EIR was challenged by the Center and other plaintiffs representing environmental interests in two separate CEQA suits, with plaintiffs representing recreational fishing interests bringing a third suit under the APA. The trial court upheld the EIR and found no violations of the APA. The appellate court affirmed in part and reversed in part.

First, the Third District addressed the EIR’s level of analysis. The CEQA Guidelines do not specify the level of analysis required to be performed in a program EIR. Rather, the Guidelines require an EIR to provide sufficient information in light of what is reasonably feasible. The court found the EIR satisfied that standard. The document reviewed and analyzed the hatchery and stocking enterprise specifically and comprehensively, but within reason, providing for further environmental review where warranted. Given the nature and statewide scope of the project and the consistency of its impacts across the state, the court found the analysis adequate to serve as a program EIR that also operated as project EIR. No additional site-specific environmental review was required given the agency’s determination that site-specific impacts were sufficiently addressed in the program EIR, and there were no new impacts. Indeed, that is the function of a program EIR.

The court also found the EIR did not impermissibly defer formulation of mitigation measures, as it provided sufficient performance standards for future mitigation to meet. The court noted that the rule prohibiting deferred mitigation prohibits loose or open-ended performance criteria. Here, in contrast, the EIR’s performance standards were sufficient to inform the Department what it had to do and accomplish, and committed the Department to mitigating impacts before proceeding with the enterprise. The performance standards were sufficient to ensure the aquatic biodiversity management plans would mitigate impacts in mountain lakes to insignificance. The Department also relied upon federal regulations to develop mitigation measures for impacts on anadromous fish.

The court held that the Department properly used the existing enterprise as the environmental baseline. The court rejected the Center’s contention that the EIR must use the existing environmental conditions—absent the project—as the baseline. It noted that though the origin of present conditions may interest enforcement agencies, such information is irrelevant to CEQA baseline determinations. The CEQA baseline must include existing conditions even when those conditions have never been reviewed and are unlawful. Furthermore, despite using the existing enterprise as the baseline, the EIR described, as much as reasonably possible the impacts hatcheries and stocking have had statewide on the environment from the enterprise’s inception more than a century ago, and proposed mitigation for those continuing impacts. Thus, the EIR did exactly what the Center sought.

Finally, the court held the EIR considered an adequate range of alternatives. For the no project alternative, the EIR considered the baseline project—continuation of the existing enterprise without making any changes. The court upheld this decision, noting that where the EIR is reviewing an existing operation or changes to that operation, the no project alternative is the existing operation; it is a factually based forecast of the environmental impacts of preserving the status quo. The court rejected the Center’s argument that the no project alternative should have been the elimination of the stocking enterprise, stating that the EIR is not the approval of a new program, but review of an ongoing one. The Department was not required to analyze the alternative scenario of discontinuing its hatchery and production enterprise, as it had no legal authority to implement a no-stocking alternative.

Turning to the APA contentions, the court concluded that three mitigation measures imposed by the Department were underground regulations, i.e., regulations adopted without complying with the notice and procedure requirements imposed by the APA. The mitigation measures at issue were: MM BIO-226 (Implement Private Stocking Permit Evaluation Protocol), MM BIO-229 (Require and Monitor Invasive Species Controls at Private Aquaculture Facilities), and MM BIO-233b (Implement Private Stocking Permit Evaluation Protocol). The court found that the measures fell within the definition of a “regulation” and were not exempt from APA requirements. The court rejected the Department’s argument that MM BIO-226 was exempt as a regulation relating “only to the internal management of the state agency,” and that MM BIO-229 and MM BIO-233b were exempt as regulations that embody the “only legally tenable interpretation of a provision of law.” In particular, the court concluded that MM BIO-226 required the Department to “perform a new duty” and MM BIO-229 imposed on a “class of persons a new affirmative duty.” The court’s application of the APA to mitigation measures in a state agency’s EIR appears to be a first and could have far-reaching implications on other EIRs studying statewide activities.

First District Holds Timber Management Plan Does Not Violate CEQA

The court held that a Nonindustrial Timber Management Plan (NTMP) approved by the California Department of Forestry and Fire Protection (Cal Fire) authorizing logging on 615 privately owned acres in Mendocino County did not violate CEQA. Center for Biological Diversity v. Cal. Dept. of Forestry and Fire Protection (Dec. 30, 2014) ___ Cal.App.4th ___, Case No. A138914.

Timberland use in California is primarily governed by the Forest Practice Act and Forest Practice Rules. An NMTP is a long-term plan for sustained yield timber production utilized by owners of less than 2500 acres of timberland and whose focus is not manufacturing forest products. Though Cal Fire’s approval of timber operations is generally subject to CEQA, the Forest Practice Act’s regulatory scheme is a certified regulatory program. An NTMP functions as the equivalent of an EIR.

In October 2008, the Bower family submitted a proposed NTMP to Cal Fire seeking authorization for timber harvesting activities northeast of Gualala. Petitioners took issue with the fact that Cal Fire approved, and the Department of Fish and Wildlife (DFW) did not object to, logging activity on a 17-acre section that DFW identified as a Late Succession Forest Stand (LSFS). This LSFS was considered a potential functional nesting habitat for a threatened seabird, the marbled murrelet. At the same time, there was no known history of any actual murrelet nesting in the LSFS.

Following a preharvest inspection of the Bowers’ property, a forester asserted the LSFS had only marginal potential for marbled murrelet occupation. A revised NTMP submitted in 2009 required retention of several large-diameter trees to benefit wildlife. Cal Fire issued responses to public comments on the NTMP and approved the document, concluding that large wildlife trees were being preserved, and species largely dependent on late seral habitat features would not be adversely impacted. DFW did not submit a nonconcurrence.

Petitioners filed a petition for a writ, complaint for breach of public trust, and request for injunctive relief. Petitioners contended that Cal Fire, in approving the NTMP, had failed to comply with CEQA and the Forest Practice Rules. They insisted the cumulative impacts of the proposed logging would eliminate enough large trees in the LSFS to render the stand unsuitable for murrelet nesting. Petitioners also argued the NTMP violated the California Endangered Species Act (CESA) by authorizing logging that would be adverse to nesting habitat essential for the survival and recovery of the murrelet.

Reviewing Cal Fire’s approval under the substantial evidence standard, the court denied the petition. It characterized petitioners’ contentions as disagreements over the evidence—parties drawing “dramatically differing conclusions from the same record.” The calculations and comparisons petitioners attempted to make, even if accurate, did not offer a complete description of the resulting environment, the court stated. Furthermore, Cal Fire was entitled to choose between differing expert opinions. Petitioners failed to affirmatively show that there was no substantial evidence in the record to support Cal Fire’s findings. The court also rejected petitioners’ claims that the NTMP did not analyze a reasonable range of alternatives.

Petitioners also claimed the NTMP should have been recirculated based on “significant new information” added prior to certification. They cited to a 2009 one-page memorandum from a Cal Fire biologist recommending additional protective measures for large tree retention. Each of the biologist’s recommendations were addressed in additional mitigation measures. The court found that the memo disclosed no new environmental impacts nor any substantial increase in the severity of an impact. The mitigation measures added in response to the memo were discussed in a second review, in which petitioners participated, and were accepted eight days prior to the close of the public comment period.

Petitioners’ CESA claims failed because Cal Fire found that implementation of the plan, as mitigated, would not result in take, jeopardy, or adverse modification of habitat in violation of the CESA. That finding was supported by substantial evidence.

Petitioners’ claim against DFW also failed. Petitioners cited no authority for the proposition that an NTMP is subject to review through traditional mandamus under CCP section 1085, particularly when the petition is not directed to the agency with authority to approve or reject the project. DFW’s decision not to actively oppose Cal Fire’s decision was merely an exercise of agency discretion.

Court of Appeal Holds Federal Law Does Not Preempt CEQA for High-Speed Train Project; Upholds Program EIR for Bay Area to Central Valley Route

The Third District Court of Appeal held that the application of CEQA to the California High-Speed Train project was not preempted by federal law in Town of Atherton v. California High Speed Rail Authority (July 24, 2014, Case No. C070877). On the merits, the Court ruled in favor of the Authority on all claims, finding that the Authority’s program EIR wholly complied with CEQA.

As California’s plans for a high-speed train system have developed over the past two decades, the system’s alignment from the Central Valley to the San Francisco Bay Area became an area of contention. The particular dispute was over the Authority’s decision that trains travelling between the Central Valley and the Bay should travel through the Pacheco Pass, which turns west from between Fresno and Merced, rather than farther north at the Altamont Pass, which turns west from the Central Valley south of Stockton. According to the Authority’s corridor evaluation report, the Altamont Pass would require additional tracks to provide train service to San Jose, resulting in less frequent service to San Francisco and San Jose absent the provision of additional trains. Based upon this determination, the Authority prepared an EIR identifying the Pacheco Pass as the preferred alternative.

After a legal challenge to the initial EIR, the Authority revised its program EIR and again selected the Pacheco Pass route as the preferred alternative. The South Bay town of Atherton challenged the adequacy of the revised EIR and approval of the Pacheco Pass alternative, arguing that the program EIR violated CEQA because it (1) provided an inadequate analysis of the vertical profile options for alignment (i.e., where to elevate the track) along the San Francisco Peninsula; (2) used a flawed revenue and ridership model; and (3) had an inadequate range of alternatives because it rejected an alternative proposed by one expert consulting company.

Preemption

Prior to oral argument, the Authority asked the court to dismiss the case, contending that federal law, specifically the Interstate Commerce Commission Termination Act (ICCTA), preempted any CEQA remedy. It argued that the ICCTA created exclusive federal regulatory jurisdiction and a federal agency, the Surface Transportation Board, had recently assumed jurisdiction over the High-Speed Train. The court found it did not need to decide whether the ICCTA preempts CEQA as to the train, however, because at least one exception to preemption applied here. Under the market participation doctrine, proprietary state actions are protected from federal preemption. The court found no evidence supporting the Authority’s contention that the market participant exception could only be asserted defensively. Accordingly, the court held that CEQA applies to the project and proceeded to address petitioners’ claims on the merits.

Adequacy of the Program EIR

The court next addressed petitioners’ claims regarding the adequacy of the program EIR. The court upheld the Authority’s use of a program EIR and held that the Authority properly deferred site-specific analysis, including the vertical alignment, to a later project EIR. The court stated that the precise vertical alignment of the train at specific locations is the type of site-specific consideration that must be examined in detail in a project-level EIR. Requiring such analysis at the program level, the court reasoned, would undermine the purpose of tiering and would create a burdensome level of detail in the larger-scale program EIR.

The court also held that the challenge to the revenue and ridership modeling presented a disagreement among experts that did not make the revised final project EIR inadequate. Petitioners failed to show that the Authority’s ridership model was “clearly inadequate or unsupported,” and the modelers had followed generally accepted professional standards. Thus, substantial evidence supported use of that model.

Finally, the court held that the Authority studied an adequate range of alternatives and was not required to analyze the Altamont Pass alternative proposed by petitioners’ consulting company, given that the alternative was substantially similar to the alternatives already studied and that range of alternatives was not shown to be inadequate.

Appellate Court Upholds Permit for Landfill Expansion in Solano County

After years of environmental review and litigation, the First District Court of Appeal upheld permits authorizing the expansion of a landfill in Solano County. Waste Connections, Inc., has sought for more than a decade to expand the Potrero Hills Landfill, which is in an upland “secondary management area” of Suisun Marsh. In SPRAWLDEF v. San Francisco Bay Conservation and Development Commission, ___Cal.App.___, an environmental group challenged the San Francisco Bay Conservation and Development Commission’s approval of the permits, arguing that the commission should have approved a smaller expansion that would not affect a marsh watercourse. The court disagreed. Applying CEQA case law to the county ordinance at issue, the court held that substantial evidence in the record supported the commission’s determination that smaller alternatives were not economically reasonable.

Solano County Ordinance, section 31-300, allows modification of a marsh watercourse only if no “reasonable alternative” exists. The commission determined that a smaller expansion alternative, designed to avoid encroaching on the intermittent watercourse, would not be economically realistic. The trial court agreed with the petitioner, Sustainability, Parks, Recycling and Wildlife Legal Defense Fund (SPRAWLDEF), that no substantial evidence supported the commission’s determination. The Court of Appeal reversed.

In evaluating whether the commission had substantial evidence for its decision, the court applied CEQA principles. The court noted that, under CEQA, governments must choose “feasible” alternatives and “feasible” mitigation measures to lessen the significant environmental impacts of projects. Employing CEQA’s definition of “feasible” and CEQA case law concerning economic infeasibility, the court concluded that CEQA’s definition of economic “feasibility” embraces the concept of reasonableness. From there, the court engaged in an extensive discussion of CEQA case law.

The court distinguished this case from CEQA cases where a determination of economic infeasibility was legally inadequate. In those cases, meaningful comparison of the proposal and the alternatives was not possible because there was no evidence regarding the cost of the alternatives. Here, the court focused on the commission’s ability to compare the costs of the proposed expansion with that of the alternatives. Waste Connections, Inc. the landfill operator, explained its profit margins and advised the commission that the economic consequences of the alternatives would be so great that the project would not be “financially viable.” It submitted data for both the proposed expansion and the alternatives, comparing the per unit cost, capacity, and the life of the landfill for each. Thus, according to the court, the commission had an “adequate record before it to fairly determine the smaller alternatives were not economically reasonable.”

The court stated that there was “no merit” to SPRAWLDEF’s assertion that the economic information regarding the costs of the proposal and alternatives should be discounted or ignored because it was provided by the real party in interest, Waste Connections, and that it was within the province of the commission to find the information credible and accept it as accurate and relevant. The court determined that this data provided the commission with “some context” to assess the economic feasibility of the alternatives and held that there was substantial evidence to support the commission’s determination that the smaller alternatives were not economically feasible.

Third Appellate District Court Finds Analysis of Urban Decay and Energy Impacts in a Programmatic EIR for Commercial Development Fails to Comply with CEQA

California Clean Energy Committee v. City of Woodland, Case No. C072033 (April 1, 2014)

Petrovich Development Company, LLC proposed to develop a 234-acre regional shopping center knows as “Gateway II” on undeveloped agricultural land located on the outskirts of the City of Woodland. After preparing a programmatic EIR, the city council reduced the size of the project to 61.3 acres and approved the project. California Clean Energy Committee (CCEC) filed a petition for writ of mandate challenging the city’s approval of the project. The trial court denied the petition.

On appeal CCEC contended (1) the trial court erred in concluding the project did not conflict with the city’s general plan, (2) the city’s mitigation measures are insufficient to ameliorate the urban decay that the project could cause, (3) the city did not give meaningful consideration to feasible project alternatives such as the mixed-use alternative, and (4) the final EIR did not properly identify and analyze potentially significant energy impacts generated by the project.

In an unpublished portion of the opinion, the court rejected CCEC’s first claim that city’s actions in approving Gateway II violated the State Planning and Zoning Law because the project was inconsistent with the city’s general plan policy of revitalizing its downtown. The court held the CCEC had failed to preserve this argument because its CEQA petition had failed to plead a separate violation of the Planning and Zoning Law.

With respect to CCEC’s claims regarding the City’s urban decay mitigation measures, the court agreed with CCEC that the measures were inadequate to mitigate the urban decay anticipated to result from the project. The mitigation measures the city adopted required the developer (1) to apply for a master conditional use permit subject to future evaluation and potential further environmental review and indicating a list of specific project uses that “shall primarily consist of regional retail uses that do not include entertainment uses and other uses that would compete with retail in Downtown Woodland”; (2) to submit a market study and urban decay analysis for review and approval by the city’s Community Development Department showing either that adequate retail demand exists or require additional mitigation or an alternate use; (3) to contribute funds toward the development of a “Retail Strategic Plan” to be prepared by the city; (4) to contribute funds toward the preparation of an “Implementation Strategy for the Downtown Specific Plan” to be prepared by the city; and (5) to “coordinate with the current owner of the County Fair Mall to prepare a strategic land use plan for the County Fair Mall to analyze potential viable land uses for the site.” The EIR determined, however, that even with the implementation of this mitigation, the city still anticipated the urban decay impact to be significant and unavoidable, in part because it was unknown at the time of approval what specific uses and stores could be proposed in the future in the project area.

The court found, as to the first mitigation measure, it was permissible under CEQA because it served to ensure the primary retail uses for the development will be regional and would not outright ban all retail uses that compete with the city’s downtown. The court also accepted the city’s representation that it “merely found that this measure would help, albeit not enough to avoid the significant urban decay impact identified by the EIR.” The court found, however, that the measure was inadequate, standing alone, to mitigate the potential adverse impacts of the development.

The court found that the second mitigation measure, by requiring the developer to prepare the market study, impermissibly ceded the city’s responsibility for studying an environmental impact to the developer. The court rejected CCEC’s claim that the city council erred by delegating the responsibility to implement the mitigation measure to the community development department, finding that delegation of responsibility for a monitoring program is appropriate under CEQA. Further, the court found the market study measure was inadequate because it did not commit the city to any specific mitigation action or impose any performance standards for determining whether it needed to undertake any future measures. Despite the fact that the EIR was a programmatic review which anticipated potential future environmental review for site-specific discretionary projects, the court concluded that, given the city’s recognition that the project would cause urban decay, the mitigation was required to do more than merely agree to a future study of the problem.

The court found the third and fourth mitigation measures were similarly inadequate for their failure to commit the city to any feasible or enforceable mitigation measures to ameliorate the adverse effects of the project on urban decay elsewhere in Woodland. The requirement for preparation of the Retail Strategic Plan and Implementation Strategy for a downtown specific plan appeared in the Draft EIR without further discussion or analysis. The final EIR adopted these mitigation measures without elaboration. The court explained that although mitigation fee programs may constitute adequate mitigation to address the adverse effects of a project, the mere payment of fees does not presumptively establish full mitigation for a discretionary project if there is no evidence that there is an established fee program in place. Here, the court found the city’s EIR did not adequately assess the scope of the program or fees necessary to adequately address the urban decay impacts expected to result from the project.

Finally, the court found that the fifth measure, although it purported to alleviate expected urban decay at Woodland’s County Fair Mall, required the city to take no action other than to coordinate with the current owner to prepare a plan for viable land uses at the County Fair Mall. The court found the mitigation measure does not require any action by the city to mitigate the urban decay it may discover to result for the County Fair Mall. As such, the court held this purported mitigation measure was inadequate. The court found that, though the EIR was a programmatic EIR, tiering of environmental review and deferring environmental analysis and mitigation measures to later phases would only be appropriate in cases where the impacts or mitigation measures are specific to those later phases. Here, because the EIR studied and attempted to mitigate the urban decay effects from the project as a whole, the city could not be permitted to excuse inadequate mitigation by putting off corrective action to a future date.

The court then held the city failed to comply with CEQA when it rejected the mixed-use alternative as infeasible. The Draft EIR concluded that the alternative was infeasible due to economic considerations; however, the city council’s findings rejected the alternative as environmentally inferior to the project. The court found the city had adopted a rationale for rejecting the alternative that was unsupported by the EIR analysis, which assumed certain impacts would be similar to the project impacts.

Finally, the court found the city’s treatment of energy impacts was inadequate. The court noted that the EIR’s discussion of energy lacked detail as it comprised less than one page. Furthermore, the court found the discussion inadequate as it did not provide an assessment of or mitigation for certain energy impact categories set forth in Appendix F of the CEQA Guidelines including transportation energy impacts, construction energy impacts, and renewable energy impacts. While the EIR did require the project’s compliance with the state building code and green building standards, the court found such standards alone would not adequately mitigate construction and operational energy impacts of the project.